How long do stairs permits take in San Francisco's Excelsior neighborhood?

In the Excelsior neighborhood of San Francisco, of the 29 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, down from 6 days a year earlier. Of the 31 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 150 days of being issued, down from 204 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's ExcelsiorneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/excelsior/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202629 issued148 issued6
Permit issued to final sign-offOctober 2023 through September 202431 finished15028 finished204

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q310802520too recent
2026-Q212621810too recent
2026-Q1766411410too recent
2025-Q4119119571012010too recent
2025-Q319174170121502700too recent
2025-Q21413710381413050too recent
2025-Q113101110061592630too recent
2024-Q48865652024250too recent
2024-Q31010629102643780yes
2024-Q212123798983670yes
2024-Q1871761043460yes
2023-Q49875172753701yes
2023-Q3121036081726481yes
2023-Q21111636101995131yes
2023-Q111828153074565yes
2022-Q46625652113881yes
2022-Q38737851486931yes
2022-Q2139949372455023yes
2022-Q1131123316103325571yes
2021-Q4151446523121856692yes
2021-Q312111735181446853yes
2021-Q298623445yes
2021-Q16614877555157490yes
2020-Q4141450292122494571yes
2020-Q31097625084146511yes
2020-Q2555525293240yes
2020-Q1550141yes
2019-Q4871138052313782yes
2019-Q387213862583702yes
2019-Q2202022176172314163yes
2019-Q11311014101242721yes
2018-Q4161420597113287762yes
2018-Q3181716180141483143yes
2018-Q21413121509492343yes
2018-Q155143241yes
2017-Q4871572305860yes
2017-Q314131200113557711yes
2017-Q210882987482881yes
2017-Q1551467041yes
2016-Q485812331yes
2016-Q317151156121287091yes
2016-Q276934541yes
2016-Q1108131,13061502063yes
2015-Q4774930062827070yes
2015-Q316157635141489952yes
2015-Q27501141yes
2015-Q15440yes
2014-Q41513025102031,4253yes
2014-Q366140241yes
2014-Q212110148752463yes
2014-Q17701251542212yes
2013-Q455144032yes
2013-Q35532751042320yes
2013-Q29901981495621yes
2013-Q1879571453051,4012yes
2012-Q411100291332901yes
2012-Q38802726621272yes
2012-Q21413111813983430yes
2012-Q1770161412021yes
2011-Q4551451282950yes
2011-Q3111001707952682yes
2011-Q2141413113743851yes
2011-Q114140233141032070yes
2010-Q412120681604642yes
2010-Q3121111491192851yes
2010-Q27722375893102yes
2010-Q1751127642yes
2009-Q41111029592661yes
2009-Q311112125101082840yes
2009-Q213121289762671yes
2009-Q19901088742601yes
2008-Q413124489803092yes
2008-Q38837661042571yes
2008-Q21313039402171yes
2008-Q18801016971500yes
2007-Q4131303121061761yes
2007-Q3108036471702yes
2007-Q21515089842342yes
2007-Q11515016381082252yes
2006-Q4990071082940yes
2006-Q3131303276902621yes
2006-Q2161500111101882yes
2006-Q165011821yes
2005-Q41312009822170yes
2005-Q312120317472852yes
2005-Q29901267432841yes
2005-Q1990061243520yes
2004-Q4880061724321yes
2004-Q31010018844yes
2004-Q2101001048843960yes
2004-Q113130012702660yes
2003-Q4111001691134551yes
2003-Q313120291092960yes
2003-Q2141400121147881yes
2003-Q13330yes
2002-Q42220yes
2002-Q314140245121733141yes
2002-Q215150101102064970yes
2002-Q1121201137802900yes
2001-Q4101005661422540yes
2001-Q31312025481845610yes
2001-Q214140159872820yes
2001-Q1111102758544760yes
2000-Q4870840yes
2000-Q3111102027725310yes
2000-Q27704830yes
2000-Q17701140yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

113 of the 1,120 stairs permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Excelsior neighborhood

Shown apart, with their own page here: bathroom remodel (2,869 filed, 2,106 finished; contractors); kitchen remodel (1,940 filed, 1,370 finished; contractors); stairs (1,120 filed, 785 finished; contractors); deck (780 filed, 535 finished; contractors). Other types: 12,100 permits. All permits in San Francisco's Excelsior neighborhood

Nearby neighborhoods

Outer Mission, McLaren Park, Glen Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.