How long do bathroom remodel permits take in San Francisco's Excelsior neighborhood?

In the Excelsior neighborhood of San Francisco, of the 95 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 3 days, up from 1 day a year earlier. Of the 86 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 174 days of being issued, down from 190 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sExcelsior neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/excelsior/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202695 issued3121 issued1
Permit issued to final sign-offOctober 2023 through September 202486 finished17488 finished190

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q43000too recent
2026-Q3312002910too recent
2026-Q2242066471001050too recent
2026-Q129242556911660too recent
2025-Q434313120221472510too recent
2025-Q333316147201623120too recent
2025-Q22623228171043090too recent
2025-Q12523062171763900too recent
2024-Q44544170372023630too recent
2024-Q33636249282193860yes
2024-Q22928297221403710yes
2024-Q11716053161524780yes
2023-Q426245139202163960yes
2023-Q322207108201805771yes
2023-Q23227640251503446yes
2023-Q124220108171613174yes
2022-Q4302716394262204603yes
2022-Q32221890192464271yes
2022-Q2242227529182585343yes
2022-Q1343310102292025084yes
2021-Q4323014212263177125yes
2021-Q3232210327151836026yes
2021-Q2252038334142845916yes
2021-Q127250383191683775yes
2020-Q4343241290272085033yes
2020-Q33129794232204544yes
2020-Q266146342yes
2020-Q122220582163416304yes
2019-Q436314572252828515yes
2019-Q332316480233146626yes
2019-Q2262310241212738783yes
2019-Q12220451171905893yes
2018-Q441367354282366097yes
2018-Q3373212211272306902yes
2018-Q23231242241785573yes
2018-Q133307318242386506yes
2017-Q43532349281735293yes
2017-Q33129561231836244yes
2017-Q2363312576251643506yes
2017-Q12222117212624561yes
2016-Q427259285221763981yes
2016-Q33230461251916744yes
2016-Q217156240121424792yes
2016-Q127261158201821,0265yes
2015-Q435354124251747745yes
2015-Q33131144232528665yes
2015-Q244393249321996015yes
2015-Q12827368191404024yes
2014-Q44545264352016097yes
2014-Q3413901392618341410yes
2014-Q23635022301084793yes
2014-Q1363542272221249511yes
2013-Q432312491811827810yes
2013-Q337372182525757610yes
2013-Q23333148261925003yes
2013-Q13128283201584137yes
2012-Q41817119131353523yes
2012-Q339381139301242904yes
2012-Q24139034341243582yes
2012-Q1262501021792024yes
2011-Q4282705231423593yes
2011-Q32321014191604061yes
2011-Q22424164181243703yes
2011-Q1272608241162011yes
2010-Q42524218201194974yes
2010-Q3313003329913701yes
2010-Q2313107241342816yes
2010-Q12322111191088081yes
2009-Q4343107271207155yes
2009-Q32626012201683192yes
2009-Q22824425211893621yes
2009-Q11818049151683783yes
2008-Q42020015181743372yes
2008-Q33030069241504193yes
2008-Q2242403221402581yes
2008-Q11615016111682863yes
2007-Q43129014231675686yes
2007-Q3232205161292302yes
2007-Q222220017702271yes
2007-Q13030020231713441yes
2006-Q412120081212532yes
2006-Q3242402017912810yes
2006-Q228280151181362376yes
2006-Q125240121162223620yes
2005-Q4232100141562503yes
2005-Q3212100162143321yes
2005-Q21919023121003145yes
2005-Q11616088121654012yes
2004-Q4212000111233093yes
2004-Q322220304161504054yes
2004-Q2252500171624731yes
2004-Q12525096201763864yes
2003-Q41818060141806011yes
2003-Q3383600271703295yes
2003-Q2212100181764642yes
2003-Q12222017191254192yes
2002-Q41515058131403810yes
2002-Q32323029211582510yes
2002-Q2252300201704121yes
2002-Q11413012101342290yes
2001-Q413130172112592940yes
2001-Q31919081171266580yes
2001-Q22120041181804910yes
2001-Q1151503693805060yes
2000-Q41615050131142630yes
2000-Q31010010671735040yes
2000-Q22726072191532960yes
2000-Q1121204151132710yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

303 of the 2,869 bathroom remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Excelsior neighborhood

Shown apart, with their own page here: bathroom remodel (2,869 filed, 2,106 finished; contractors); kitchen remodel (1,940 filed, 1,370 finished; contractors); stairs (1,120 filed, 785 finished; contractors); deck (780 filed, 535 finished; contractors). Other types: 12,100 permits. All permits in San Francisco's Excelsior neighborhood

Nearby neighborhoods

Outer Mission, McLaren Park, Glen Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.