W E Lyons Construction Co
- Based in
- Walnut Creek
- On San Francisco permits
- Aug 2000 to Aug 2026
- Last 24 months
- 8 permits filed
60 permits since 2000: 31 completed, 7 in progress, 19 never finaled, 3 expired or cancelled.
Of the 19 never-finaled permits, 1 is 3 to 5 years old, 13 are 5 to 10 years old, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 11, 2026 | In progress issued Aug 2026 | 1 South Van Ness Av | rev to pa# 2022-0307-9381: replacement of superseded sffd pre application meeting notes & addition of sffd reference forms revised pre application meeting notes dated 7/9/2026. indicatrs approved alternate access door/panel at freight elevater hoistway.Details
rev to pa# 2022-0307-9381: replacement of superseded sffd pre application meeting notes & addition of sffd reference forms revised pre application meeting notes dated 7/9/2026. indicatrs approved alternate access door/panel at freight elevater hoistway. | |
| Jul 21, 2026 | In progress issued Jul 2026 | 1 South Van Ness Av | ref 202602092623- all work completed for drawings and cals for transformer rackDetails
ref 202602092623- all work completed for drawings and cals for transformer rack | |
| Jun 23, 2026 | In progress issued Jun 2026 | 1 South Van Ness Av | revision to pa #202203079381. at passenger elevators #1 and #2 machine room. addition of screen divider between disconnects for elevator #2Details
revision to pa #202203079381. at passenger elevators #1 and #2 machine room. addition of screen divider between disconnects for elevator #2 | $15,000 |
| Mar 26, 2026 | In progress issued Mar 2026 | 1 South Van Ness Av | revision to pa# 202203079381: addition to partial single line diagram for new scope and reference sheet for as-builts single line diagram. removal of intimescent paint reference over non-combustible partial height wall.Details
revision to pa# 202203079381: addition to partial single line diagram for new scope and reference sheet for as-builts single line diagram. removal of intimescent paint reference over non-combustible partial height wall. | |
| Mar 12, 2026 | In progress issued Mar 2026 | 1 South Van Ness Av | revision to pa #2022-0307-9381: addition to partial single line diagram for new scope and reference sheet for as builts single line diagram. removal of intumescent paint reference over non combustible partial height wall.Details
revision to pa #2022-0307-9381: addition to partial single line diagram for new scope and reference sheet for as builts single line diagram. removal of intumescent paint reference over non combustible partial height wall. | |
| Feb 12, 2026 | In progress filed Feb 2026, not yet issued | 601 Laguna St | pacifica sfo is renovating an existing residential care facility for the elderly into an adult residential facility for sf dph as part of a purchase agreement with ccsf. the scope of work includes repair, replacement & or restoration of finishes, replacement of hvac equipment, accessibility upgradesDetails
pacifica sfo is renovating an existing residential care facility for the elderly into an adult residential facility for sf dph as part of a purchase agreement with ccsf. the scope of work includes repair, replacement & or restoration of finishes, replacement of hvac equipment, accessibility upgrades | $1,264,297 |
| Sep 3, 2025 | In progress issued Oct 2025 | 1 South Van Ness Av | revison to pa# 202203079381: create a temporary structural floor opening in existing deck floor. construction consists of structural support and new pan deck welded back with dowels in concrete after equipment is installedDetails
revison to pa# 202203079381: create a temporary structural floor opening in existing deck floor. construction consists of structural support and new pan deck welded back with dowels in concrete after equipment is installed | $10,000 |
| Feb 11, 2025 | Completed final sign-off Jan 2026 | 1450 Franklin St | replace existing exterior plaster. stucco removal and replacement. selected balcony repairs. inspection and repair of roof parapet wall stucco.Details
replace existing exterior plaster. stucco removal and replacement. selected balcony repairs. inspection and repair of roof parapet wall stucco. | $1,000,000 |
| Jul 27, 2023 | Completed final sign-off Aug 2025 | 201 Van Ness Av | revision to bpa#201803274726 & 202210204766, additional drawings for elevator #1 & #2 modernizationDetails
revision to bpa#201803274726 & 202210204766, additional drawings for elevator #1 & #2 modernization | $70,000 |
| Dec 20, 2022 | Completed final sign-off Dec 2025 | 822 Geary St | ***priority review***: t.i. & occupancy change from merchantile to business occupancy. work includes selective demo, hvac, plumbing, lighting, new work includes new partitions, lighting, hvac, roofDetails
***priority review***: t.i. & occupancy change from merchantile to business occupancy. work includes selective demo, hvac, plumbing, lighting, new work includes new partitions, lighting, hvac, roof | $11,874,978 |
| Dec 20, 2022 | Completed final sign-off Dec 2025 | 629 Hyde St | selective demo of exteriro elements, storage building, select retaining walls, conc, paving and asphalt new work includes accessible landing, new retating walls, new pre fabricated structure, plumbing & elec work as required to support the projectDetails
selective demo of exteriro elements, storage building, select retaining walls, conc, paving and asphalt new work includes accessible landing, new retating walls, new pre fabricated structure, plumbing & elec work as required to support the project | $2,409,511 |
| Mar 7, 2022 | Never finaled issued Aug 2023, no final | 1 South Van Ness Av | priority prj-modernize 3 (e) elevators: replace/refurbish (e) equipment, car control panels& lobby fixtures.upgrade elevator call system of passenger elevators to destination dispatch system & provide emergency 2-way/ visual based, text based interactive communication system in cab control panels.Details
priority prj-modernize 3 (e) elevators: replace/refurbish (e) equipment, car control panels& lobby fixtures.upgrade elevator call system of passenger elevators to destination dispatch system & provide emergency 2-way/ visual based, text based interactive communication system in cab control panels. | $1,226,500 |
| Sep 23, 2019 | Never finaled issued Oct 2019, no final | 1171 Mission St | rev to pa# 201611082224; mech n/a maherDetails
rev to pa# 201611082224; mech n/a maher | $5,000 |
| Sep 14, 2018 | Expired or cancelled cancelled Dec 2018 | 301 Mission St | unit# 35b:remove countertop and gyp board under window sill as shown on attached drawings for inspection of curtain wall fire stop at floor. repair wall as required. no alteration to curtain wall framing, and structure. maintain (e) fire rating. investigate curtain wall connectionsDetails
unit# 35b:remove countertop and gyp board under window sill as shown on attached drawings for inspection of curtain wall fire stop at floor. repair wall as required. no alteration to curtain wall framing, and structure. maintain (e) fire rating. investigate curtain wall connections | $10,000 |
| Sep 14, 2018 | Never finaled issued Sep 2018, no final | 301 Mission St | unit# 37b: remove counter and gyp board under window sill as shown on attached drawings for inspection of curtain wall fire stop at floor. repair wall as required. no alteration to curtain wall framing, and structure. maintain (e) fire rating. investigate curtain wall comnections.Details
unit# 37b: remove counter and gyp board under window sill as shown on attached drawings for inspection of curtain wall fire stop at floor. repair wall as required. no alteration to curtain wall framing, and structure. maintain (e) fire rating. investigate curtain wall comnections. | $10,000 |
| Sep 14, 2018 | Completed final sign-off Nov 2018 | 301 Mission St | unit# 36b: remove countertop and gyp board under window sill as shown on attached drawing. inspect fire stop. repair if necessary (fire stop) repair wall and countertop. no alteration to curtain wall framing, and structure. maintain (e) fire rating.Details
unit# 36b: remove countertop and gyp board under window sill as shown on attached drawing. inspect fire stop. repair if necessary (fire stop) repair wall and countertop. no alteration to curtain wall framing, and structure. maintain (e) fire rating. | $10,000 |
| May 4, 2018 | Never finaled issued Jul 2018, no final | 301 Mission St | wall coring garage. basement wall testing core 6-6" diameter hole at existing retaining wall located at basement level b4 & b5 under podium bldg, two @ level b4, four @ level b5Details
wall coring garage. basement wall testing core 6-6" diameter hole at existing retaining wall located at basement level b4 & b5 under podium bldg, two @ level b4, four @ level b5 | $35,000 |
| Apr 6, 2018 | Never finaled issued Apr 2018, no final | 301 Mission St | unit 47a - remove and replace gyp board @ floor slab, curtain wall, heat pumps, demising walls, furred soffits for defect investigation opening to be restored to there match. (e) fire resistive constructionDetails
unit 47a - remove and replace gyp board @ floor slab, curtain wall, heat pumps, demising walls, furred soffits for defect investigation opening to be restored to there match. (e) fire resistive construction | $10,000 |
| Apr 5, 2018 | Never finaled issued Apr 2018, no final | 301 Mission St | investigation construction defect testing.cut off gypsun board at floor slab edge to review fire resistive construction at curtain wall, heat pump penetrations & demishing walls and soffits. openings will be restored back to match existing fire-rated construction.Details
investigation construction defect testing.cut off gypsun board at floor slab edge to review fire resistive construction at curtain wall, heat pump penetrations & demishing walls and soffits. openings will be restored back to match existing fire-rated construction. | $10,000 |
| Mar 29, 2018 | Never finaled issued Mar 2018, no final | 301 Mission St | unit 39b - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated constructionDetails
unit 39b - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated construction | $10,000 |
| Mar 29, 2018 | Never finaled issued Mar 2018, no final | 301 Mission St | unit 5a - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated constructionDetails
unit 5a - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated construction | $10,000 |
| Mar 29, 2018 | Expired or cancelled cancelled Apr 2018 | 301 Mission St | unit 1102 - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated constructionDetails
unit 1102 - ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated construction | $10,000 |
| Mar 29, 2018 | Never finaled issued Mar 2018, no final | 301 Mission St | ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated constructionDetails
ur&r gyp board at flr slab edge. to review fire resistive construction at control wall, heat pump penetrations fire rated demissing walls ferred sofits, opening to be restored to match (e) fire rated construction | $10,000 |
| Jan 18, 2018 | Never finaled issued Jan 2018, no final | 301 Mission St | remove (e) fire stopping at rise pipes, clean and prep and apply (n) fire stopping.clean and prep surfaces at curtain wall mullions to receive fire seals; install fire blocking inside gaps at vertical mullions; prep, patch and seal exterior wall gaps at curtain wall. ref 201801128507. maher n/a.Details
remove (e) fire stopping at rise pipes, clean and prep and apply (n) fire stopping.clean and prep surfaces at curtain wall mullions to receive fire seals; install fire blocking inside gaps at vertical mullions; prep, patch and seal exterior wall gaps at curtain wall. ref 201801128507. maher n/a. | $10,000 |
| Jan 12, 2018 | Completed final sign-off Jan 2018 | 301 Mission St | ur&r gyp board at floor slab edge to review fire resistive construction and curtain wall, heat pump penetrations, fire-rated demising wall,furred soffit condition,unit 36b only, gyp board to be restored to original condition upon completion of work. any repair wor will be filed under seperate permitDetails
ur&r gyp board at floor slab edge to review fire resistive construction and curtain wall, heat pump penetrations, fire-rated demising wall,furred soffit condition,unit 36b only, gyp board to be restored to original condition upon completion of work. any repair wor will be filed under seperate permit | $10,000 |
| Sep 8, 2017 | Completed final sign-off Jul 2018 | 725 Fulton St | repair concrete deck > 50 % repair steel beamsDetails
repair concrete deck > 50 % repair steel beams | $300,000 |
| May 31, 2017 | Never finaled issued Feb 2018, no final | 1171 Mission St | revision to 201612205431: title 24 maher na,Details
revision to 201612205431: title 24 maher na, | $27,000 |
| May 31, 2017 | Never finaled issued Feb 2018, no final | 1171 Mission St | revision to 201611082224: title 24 only, fire alarm under separate permit fp under seperate permit maher naDetails
revision to 201611082224: title 24 only, fire alarm under separate permit fp under seperate permit maher na | $25,550 |
| Dec 20, 2016 | Never finaled issued Jan 2017, no final | 1171 Mission St | g/f- remodel (e) service facility include new restrooms, remodel (e) restrooms, new break room, exam room, isolation room, men's/women's small respite rooms, new nurse station & remodel (e) nurse station, new exterior security gates & fence at mission street. mep & life safety deferred.Details
g/f- remodel (e) service facility include new restrooms, remodel (e) restrooms, new break room, exam room, isolation room, men's/women's small respite rooms, new nurse station & remodel (e) nurse station, new exterior security gates & fence at mission street. mep & life safety deferred. | $300,000 |
| Nov 8, 2016 | Never finaled issued Nov 2016, no final | 1171 Mission St | remodel (e)social service facility,replace entrance doors @(e)location,new 1st flr restrooms w/showers @sleeping area,new first flr office & meeting room,new partitions,finishes,new wire mesh enclosure @basement,new disable accssble parking space,new unisex restrm near reception,infill (e)roll-upDetails
remodel (e)social service facility,replace entrance doors @(e)location,new 1st flr restrooms w/showers @sleeping area,new first flr office & meeting room,new partitions,finishes,new wire mesh enclosure @basement,new disable accssble parking space,new unisex restrm near reception,infill (e)roll-up | $180,000 |
| May 8, 2014 | Completed final sign-off Apr 2015 | 3911 Alemany Bl | repairs to existing exhaust shaft. shaft is located in the restaurant at level 1, and extends to roof level of a four story mixed use building. level 1 is retail and type 1 construction. podium and above is residential and type v-b construction. the current shaft is compromised.Details
repairs to existing exhaust shaft. shaft is located in the restaurant at level 1, and extends to roof level of a four story mixed use building. level 1 is retail and type 1 construction. podium and above is residential and type v-b construction. the current shaft is compromised. | $35,000 |
| Aug 30, 2013 | Completed final sign-off Jun 2015 | 8100 Oceanview Tr | removing old siding, windows and non structural concrete patio topping slabs to rewaterproof building. windows like for like. work is exterior common area only.Details
removing old siding, windows and non structural concrete patio topping slabs to rewaterproof building. windows like for like. work is exterior common area only. | $3,000,000 |
| Aug 23, 2012 | Completed final sign-off Jul 2013 | 2121 Evans Av | minor revision to pa# 2011-1004-6121, 2011-0209-9905 & 2012-0521-0904-raise elevation to curb & gutters, modify sprinkler system & add new landscape water meter to comply with green landscape ord. add retaining wall drainage piping & replacement of property line fenceDetails
minor revision to pa# 2011-1004-6121, 2011-0209-9905 & 2012-0521-0904-raise elevation to curb & gutters, modify sprinkler system & add new landscape water meter to comply with green landscape ord. add retaining wall drainage piping & replacement of property line fence | |
| May 21, 2012 | Completed final sign-off Jul 2013 | 2121 Evans Av | parking lot lighting and landscapingDetails
parking lot lighting and landscaping | $86,000 |
| Oct 4, 2011 | Completed final sign-off Jul 2013 | 2121 Evans Av | grading is new 6 acre asphalt parking lot complete with curb & gutter site drainage & new driveway.Details
grading is new 6 acre asphalt parking lot complete with curb & gutter site drainage & new driveway. | $87,500 |
| Feb 9, 2011 | Completed final sign-off Jul 2012 | 2121 Evans Av | demolish a storageDetails
demolish a storage | $450,000 |
| May 14, 2010 | Completed final sign-off Apr 2012 | 2310 Hyde St | removal of (e) siding in-kind to match (e) apperance, color and material. perform spot re-pointing and masonry repairs as neccessary @ all sides.Details
removal of (e) siding in-kind to match (e) apperance, color and material. perform spot re-pointing and masonry repairs as neccessary @ all sides. | $350,000 |
| Feb 5, 2008 | Completed final sign-off Mar 2008 | 765 Fulton St | installation of sprayed on fireproofing at building only on beams/deck, application of fire stop on entire deck at all openings. revision to pa# 2008-01-11-2293-changed ul listing from d744 and d925 to d759 and n759Details
installation of sprayed on fireproofing at building only on beams/deck, application of fire stop on entire deck at all openings. revision to pa# 2008-01-11-2293-changed ul listing from d744 and d925 to d759 and n759 | |
| Jan 11, 2008 | Completed final sign-off Mar 2008 | 765 Fulton St | to renew to final only pa# 200707035845Details
to renew to final only pa# 200707035845 | |
| Jan 11, 2008 | Never finaled issued Jan 2008, no final | 765 Fulton St | revision to appl #200801041828 - installation of sprayed-on fireproofing @ beams, underside of deck @ bldg only. installation of firestopping material around all openings @ existing concrete deck.Details
revision to appl #200801041828 - installation of sprayed-on fireproofing @ beams, underside of deck @ bldg only. installation of firestopping material around all openings @ existing concrete deck. | |
| Jan 4, 2008 | Never finaled issued Jan 2008, no final | 745 Fulton St | work on 765 fulton street - installation of fire proofing on ceiling/beams in parking garage on 765 fulton. installation of fire stopping material around all openings at (e) concrete deck and unrestrianed beams. revision to pa# 2007.05.31.2621 and 2007.12.18.0738.Details
work on 765 fulton street - installation of fire proofing on ceiling/beams in parking garage on 765 fulton. installation of fire stopping material around all openings at (e) concrete deck and unrestrianed beams. revision to pa# 2007.05.31.2621 and 2007.12.18.0738. | $20,000 |
| Dec 18, 2007 | Completed final sign-off Dec 2007 | 11 Banneker Wy | revision to app#200606154179 & #200711268877. individual units as 1d-1f-11c-11e-15c-15d-15e-15f-18c-18d-18e-18f repair. (clarification per inspectors instructions).Details
revision to app#200606154179 & #200711268877. individual units as 1d-1f-11c-11e-15c-15d-15e-15f-18c-18d-18e-18f repair. (clarification per inspectors instructions). | |
| Dec 18, 2007 | Never finaled issued Dec 2007, no final | 765 Fulton St | revision to app# 200705312621. install spray on fire proofing at beam and underside of deck at bldgs.Details
revision to app# 200705312621. install spray on fire proofing at beam and underside of deck at bldgs. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 2 Banneker Wy | renew pa# 2006/06/15/4176 for final inspection only.Details
renew pa# 2006/06/15/4176 for final inspection only. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 745 Fulton St | bldg#a. renew pa#200606244738 for final inspection.Details
bldg#a. renew pa#200606244738 for final inspection. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 8 Banneker Wy | renew pa# 2006/06/22/4731 for final inspection only.Details
renew pa# 2006/06/22/4731 for final inspection only. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 3 Banneker Wy | renew pa# 2006/06/15/4173 for final inspection only.Details
renew pa# 2006/06/15/4173 for final inspection only. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 11 Banneker Wy | renew pa# 2006/06/15/4179 for final inspection only.Details
renew pa# 2006/06/15/4179 for final inspection only. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 780 Grove St | bldg#b.renew pa#200606224739 for final inspection.Details
bldg#b.renew pa#200606224739 for final inspection. | |
| Nov 26, 2007 | Completed final sign-off Dec 2007 | 750 Grove St | bldg#c. renew pa#200606224734 for final inspection.Details
bldg#c. renew pa#200606224734 for final inspection. | |
| Nov 13, 2007 | Completed final sign-off Jan 2008 | 765 Fulton St | to add a new retaining wall (6' high) to an existing retaining wall at rear of new bldg. revision to pa# 2006.11.29.8741Details
to add a new retaining wall (6' high) to an existing retaining wall at rear of new bldg. revision to pa# 2006.11.29.8741 | $50,000 |
| Jul 3, 2007 | Expired or cancelled expired Sep 2008 | 765 Fulton St | build 8' cmu wall with concrete pad and install doors closure to trash compactor, one electrical and water to trash compactor. this is a revision to appl#200611298741Details
build 8' cmu wall with concrete pad and install doors closure to trash compactor, one electrical and water to trash compactor. this is a revision to appl#200611298741 | $8,900 |
| May 31, 2007 | Never finaled issued Sep 2007, no final | 765 Fulton St | installation (reconstruction) of fire proofing at ceiling. no mechanical under this permit.Details
installation (reconstruction) of fire proofing at ceiling. no mechanical under this permit. | $38,000 |
| Feb 5, 2007 | Completed final sign-off Dec 2007 | 760 Webster St | interior alterations to apt# unit#a to enlarge bathroom. add / relocate door & add window. construct exterior ramp at rear of apt# unit a.Details
interior alterations to apt# unit#a to enlarge bathroom. add / relocate door & add window. construct exterior ramp at rear of apt# unit a. | $45,000 |
| Feb 5, 2007 | Completed final sign-off Dec 2007 | 765 Fulton St | interior alterations to apt# 765b, # 775a, # 775b & 765a. units to enlarge bathrooms. add / relocate door & add 4' x 5' window. exterior ramps at rear of units. revision to pa# 2006/07/13/6444.Details
interior alterations to apt# 765b, # 775a, # 775b & 765a. units to enlarge bathrooms. add / relocate door & add 4' x 5' window. exterior ramps at rear of units. revision to pa# 2006/07/13/6444. | $40,000 |
| Nov 29, 2006 | Completed final sign-off Jan 2008 | 765 Fulton St | to erect 1 story assembly & office building.Details
to erect 1 story assembly & office building. | $300,000 |
| Jul 2, 2004 | Never finaled issued Jul 2004, no final | 900 Green St | scaffold bldg, repair damage to eifs, repair deck, roof as required, flooring.Details
scaffold bldg, repair damage to eifs, repair deck, roof as required, flooring. | $1,600,000 |
| Jan 14, 2002 | Completed final sign-off May 2002 | 2090 Evans Av | shotcrete infill 4 windows and 2 overhead doors openings.Details
shotcrete infill 4 windows and 2 overhead doors openings. | $63,000 |
| Aug 21, 2000 | Completed final sign-off Jun 2001 | 2045 Evans Av | revision of(e)approved fire protection drwgs.original drwg show fdc.notation on original#20000105262Details
revision of(e)approved fire protection drwgs.original drwg show fdc.notation on original#20000105262 | |
| Aug 3, 2000 | Completed final sign-off Jun 2001 | 2045 Evans Av | frame and close walls all other permits to be applied for separateley ref only#9823576s ck access onDetails
frame and close walls all other permits to be applied for separateley ref only#9823576s ck access on | $20,000 |