Permit GraphShortlistSan Francisco building permits since 2000

Truebeck Construction

Contractor license
903798
State license record
Based in
San Mateo
On San Francisco permits
Jun 2008 to Sep 2026
Last 24 months
34 permits filed

610 permits since 2000: 476 completed, 14 in progress, 79 never finaled, 41 expired or cancelled.

Of the 79 never-finaled permits, 3 are 3 to 5 years old, 31 are 5 to 10 years old, 45 are over 10 years old. 1 was filed but never issued.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for pergola or trellis across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Pergola or trellis permits

AllRoof deck 9Pergola or trellis 4Deck 3Stairs 32Kitchen remodel 9Bathroom remodel 13

4 pergola or trellis permits: 2 completed, 2 in progress. Typically 30 days from filing to permit and 116 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
Sep 25, 2026In progress
issued Nov 2026
530 Jackson Ston level 5: the existing west exterior terrace is to be renovated. the e. exterior doors to the terrace are to be raplaced with new sliding doors & a new egress swing door. a new contilevered trellis, new millwork, new light fixtures & tiled flooring are to be added. revision to 2025 1217 2080
Details
Permit
202609258640
Permit issued
Nov 10, 2026

on level 5: the existing west exterior terrace is to be renovated. the e. exterior doors to the terrace are to be raplaced with new sliding doors & a new egress swing door. a new contilevered trellis, new millwork, new light fixtures & tiled flooring are to be added. revision to 2025 1217 2080

Open the permit page

$750,000
Mar 20, 2026In progress
issued May 2026
755 Ocean Avnew pergola (freestanding) at an existing courtyard space between the (e) classroom building and theatre building.
Details
Permit
202603207981
Permit issued
May 27, 2026

new pergola (freestanding) at an existing courtyard space between the (e) classroom building and theatre building.

Open the permit page

$523,000
May 9, 2013Completed
final sign-off Oct 2013
370 03rd Stadd new temporary sun shade structure, 6 vertical poles with vertical fabric sun shades at existing roof deck. new support structural steel at 7th floor. fire alarm under sep. permit
Details
Permit
201305096580
Permit issued
May 22, 2013
Final sign-off
Oct 4, 2013

add new temporary sun shade structure, 6 vertical poles with vertical fabric sun shades at existing roof deck. new support structural steel at 7th floor. fire alarm under sep. permit

Open the permit page

$35,000
Feb 18, 2010Completed
final sign-off May 2010
1090 Bryant Strevision to application 200911050655. minor changes to original application. addition of interior architectural trellis and change to layout of interior partition walls.
Details
Permit
201002186786
Permit issued
Feb 18, 2010
Final sign-off
May 26, 2010

revision to application 200911050655. minor changes to original application. addition of interior architectural trellis and change to layout of interior partition walls.

Open the permit page

$6,000