- 8 permits filed
394 permits since 2000: 267 completed, 8 in progress, 87 never finaled, 32 expired or cancelled.
Of the 87 never-finaled permits, 4 are 3 to 5 years old, 16 are 5 to 10 years old, 67 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Stairs permits
5 stairs permits: 5 completed. Typically 21 days from filing to permit and 117 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 12, 2021 | Completed final sign-off Aug 2022 | 209 Post St | interior tenant improvement, interior demo (n) interior wall partitins (n) interior stair and opening between 11th & 12 fl. mep upgradeDetails
interior tenant improvement, interior demo (n) interior wall partitins (n) interior stair and opening between 11th & 12 fl. mep upgrade | $605,044 |
| Mar 20, 2017 | Completed final sign-off Aug 2017 | 18 Geary St | 2nd floor - interior improvements at 2nd floor space (only) to include new unisex restroom and new kitchenette. selective demo at (e) interior partitions, new entry door adjacent stair, interior doors, mep work included. n/a maherDetails
2nd floor - interior improvements at 2nd floor space (only) to include new unisex restroom and new kitchenette. selective demo at (e) interior partitions, new entry door adjacent stair, interior doors, mep work included. n/a maher | $125,000 |
| Mar 25, 2013 | Completed final sign-off Jun 2013 | 1548 Stockton St | re-locate 2 bathrooms, bar and one set of stairs. replace misc finishes including flooring a lighting.Details
re-locate 2 bathrooms, bar and one set of stairs. replace misc finishes including flooring a lighting. | $50,000 |
| Mar 1, 2013 | Completed final sign-off Apr 2013 | 1548 Stockton St | demolition only-removal of (e) restrooms, bar, drywall, arches, floor finishes. stairs to remain, construction under seperate permitDetails
demolition only-removal of (e) restrooms, bar, drywall, arches, floor finishes. stairs to remain, construction under seperate permit | $3,500 |
| Mar 27, 2000 | Completed final sign-off Dec 2005 | 111 Cambon Dr | repair of existing trusses two perlin ties, two upgrades to bathrm, parking lot, stairs, title 24, #Details
repair of existing trusses two perlin ties, two upgrades to bathrm, parking lot, stairs, title 24, # | $200,000 |