Permit GraphShortlistSan Francisco building permits since 2000

N M S Brosnan Construction

Contractor license
787529
State license record
Based in
Milbrae
On San Francisco permits
Feb 2001 to Aug 2026
Last 24 months
3 permits filed

52 permits since 2000: 36 completed, 4 in progress, 8 never finaled, 4 expired or cancelled.

Of the 8 never-finaled permits, 3 are 3 to 5 years old, 3 are 5 to 10 years old, 2 are over 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Stairs permits

AllRoof deck 1Deck 1Stairs 3Kitchen remodel 10Bathroom remodel 21

3 stairs permits: 1 completed, 1 in progress, 1 never finaled. Typically 127 days from filing to permit and 48 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
May 10, 2022Never finaled
issued Sep 2022, no final
2526 27th Avgound flr: to add (1) (n) bedroom, fam rm, full bath, office and laundry room. relocate (e) furnace and water heater. 2nd flr convert (e) sunroom to full bath, to reconfirgure (e) stair from 2nd second floor to the groud floor. to recessed garage door to add a door opening.
Details
Permit
202205103941
Status
issued
Filed
May 10, 2022
Permit issued
Sep 14, 2022
Declared cost
$120,000
Address
2526 27th Av

gound flr: to add (1) (n) bedroom, fam rm, full bath, office and laundry room. relocate (e) furnace and water heater. 2nd flr convert (e) sunroom to full bath, to reconfirgure (e) stair from 2nd second floor to the groud floor. to recessed garage door to add a door opening.

Open the permit page

$120,000
Aug 12, 2020In progress
issued Jan 2025
2566 39th Avtwo story rear yard horizontal addition. new bathroom at 2nd floor. new rear yard deck & stair. first floor addition & alterations, proposed under bpa #202008121637 to legalize unauthorized dwelling unit.
Details
Permit
202008121633
Status
issued
Filed
Aug 12, 2020
Permit issued
Jan 8, 2025
Declared cost
$83,398
Address
2566 39th Av

two story rear yard horizontal addition. new bathroom at 2nd floor. new rear yard deck & stair. first floor addition & alterations, proposed under bpa #202008121637 to legalize unauthorized dwelling unit.

Open the permit page

$83,398
Aug 9, 2006Completed
final sign-off Sep 2006
2958 Bush St(work to be done at lot 2958 lot 045 only )replace rear stair way "in kind" to yard.
Details
Permit
200608098988
Status
complete
Filed
Aug 9, 2006
Permit issued
Aug 9, 2006
Final sign-off
Sep 26, 2006
Declared cost
$4,000
Address
2958 Bush St

(work to be done at lot 2958 lot 045 only )replace rear stair way "in kind" to yard.

Open the permit page

$4,000
N M S Brosnan Construction, contractor license 787529 | Permit Graph