- 3 permits filed
15 permits since 2000: 12 completed, 2 in progress, 1 never finaled.
Of the 1 never-finaled permit, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Kitchen remodel permits
3 kitchen remodel permits: 2 completed, 1 in progress. Typically 0 days from filing to permit and 458 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 7, 2026 | In progress issued Jan 2026 | 2525 22nd Av | revision to pa #202506259388: new wall to align with existing wall at s.w. corner, part of horizontal expansion/change walls at interior stair to kitchen/new slider patio door at n-w patio/change windows 0034 004 size(smaller) changes in layout of new bath 1 & 2, furnace & water, heater moved intoDetails
revision to pa #202506259388: new wall to align with existing wall at s.w. corner, part of horizontal expansion/change walls at interior stair to kitchen/new slider patio door at n-w patio/change windows 0034 004 size(smaller) changes in layout of new bath 1 & 2, furnace & water, heater moved into | |
| May 15, 2024 | Completed final sign-off Jul 2024 | 1284 18th Av | unit 102: 1 kitchen & 1 bathroom remodel in-kind. replace kitchen cabinet, applicances, sink, garbage disposal. new tile backsplash. replace e) tub, shower walls & floor (tile) replace plumbing fixture, shower sliding glass door, vanity sink cabinet. replace e) heat lampDetails
unit 102: 1 kitchen & 1 bathroom remodel in-kind. replace kitchen cabinet, applicances, sink, garbage disposal. new tile backsplash. replace e) tub, shower walls & floor (tile) replace plumbing fixture, shower sliding glass door, vanity sink cabinet. replace e) heat lamp | $30,000 |
| Dec 30, 2021 | Completed final sign-off Jun 2024 | 7 Upper Tr | remodel (e) bathroom, change cabinets/counter @ (e) kitchenDetails
remodel (e) bathroom, change cabinets/counter @ (e) kitchen | $15,000 |