Permit GraphShortlistSan Francisco building permits since 2000

Kenneth Smith

Contractor license
885942
State license record
Based in
San Francisco
On San Francisco permits
Feb 2009 to Jul 2025
Last 24 months
1 permit filed

25 permits since 2000: 25 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Stairs permits

AllRoof deck 1Deck 2Stairs 4Kitchen remodel 7Bathroom remodel 5

4 stairs permits: 4 completed. Typically 88 days from filing to permit and 45 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
Feb 18, 2021Completed
final sign-off Dec 2021
640 09th Avconstruction of (n) stairs in rear of building to replace the (e) that was red tagged by dbi for disrepair & unsafe condition. the rear stair is a required secondary exit for the apts & this permit needs to be expedited per the inspector dominic keane's
Details
Permit
202102184900
Status
complete
Filed
Feb 18, 2021
Permit issued
Sep 14, 2021
Final sign-off
Dec 21, 2021
Declared cost
$50,000
Address
640 09th Av

construction of (n) stairs in rear of building to replace the (e) that was red tagged by dbi for disrepair & unsafe condition. the rear stair is a required secondary exit for the apts & this permit needs to be expedited per the inspector dominic keane's

Open the permit page

$50,000
Mar 18, 2019Completed
final sign-off Oct 2019
1582 Fulton Strebuilding deck stairs to provide 3ft setbacks at rear(north) & side (west) per residential design advisory team review
Details
Permit
201903185458
Status
complete
Filed
Mar 18, 2019
Permit issued
Sep 9, 2019
Final sign-off
Oct 25, 2019
Declared cost
$10,000
Address
1582 Fulton St

rebuilding deck stairs to provide 3ft setbacks at rear(north) & side (west) per residential design advisory team review

Open the permit page

$10,000
Feb 22, 2011Completed
final sign-off Mar 2011
208 States Stper physical inspection: cc-5779; provide approved handrail for stairs @ rear of unit. guardrail if needed, handrail between 34" to 38" above tread nosing.
Details
Permit
201102220666
Status
complete
Filed
Feb 22, 2011
Permit issued
Feb 22, 2011
Final sign-off
Mar 1, 2011
Declared cost
$1,000
Address
208 States St

per physical inspection: cc-5779; provide approved handrail for stairs @ rear of unit. guardrail if needed, handrail between 34" to 38" above tread nosing.

Open the permit page

$1,000
Feb 24, 2010Completed
final sign-off Apr 2010
226 Missouri Stcomply with his nov 201032021 dated 2/11/2010. replace stairway post in rear yard and provide handrails
Details
Permit
201002247082
Status
complete
Filed
Feb 24, 2010
Permit issued
Feb 24, 2010
Final sign-off
Apr 9, 2010
Declared cost
$200
Address
226 Missouri St

comply with his nov 201032021 dated 2/11/2010. replace stairway post in rear yard and provide handrails

Open the permit page

$200