Hathaway Dinwiddie Co.
- Based in
- San Francisco
- On San Francisco permits
- Jan 2000 to Sep 2026
- Last 24 months
- 111 permits filed
2,989 permits since 2000: 2,253 completed, 59 in progress, 297 never finaled, 380 expired or cancelled.
Of the 297 never-finaled permits, 13 are 3 to 5 years old, 73 are 5 to 10 years old, 211 are over 10 years old. 19 were filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Deck permits
13 deck permits: 9 completed, 1 in progress, 2 never finaled, 1 expired or cancelled. Typically 10 days from filing to permit and 195 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 11, 2026 | In progress filed Sep 2026, not yet issued | 2801 Geary Bl | construct ext wall at kitchen storage room property line. upgrade accessible restroom demo rear deck stair.Details
construct ext wall at kitchen storage room property line. upgrade accessible restroom demo rear deck stair. | $15,000 |
| Dec 23, 2019 | Completed final sign-off Apr 2022 | 185 Berry St | each of the 5 steel buttresses at the ground floor level will be painted with intunescent paint up to the new ceiling so they could be occupied by people. new finishes will be added to the bottom of the concrete deck along the whole length of the wharf side bldg.Details
each of the 5 steel buttresses at the ground floor level will be painted with intunescent paint up to the new ceiling so they could be occupied by people. new finishes will be added to the bottom of the concrete deck along the whole length of the wharf side bldg. | $1,100,000 |
| Dec 1, 2015 | Completed final sign-off May 2017 | 1563 Mission St | 4th floor: remove vault walls. floor will be replaced with a steel framed metal deck/concrete slab in this bay. ref app#201501286888Details
4th floor: remove vault walls. floor will be replaced with a steel framed metal deck/concrete slab in this bay. ref app#201501286888 | $40,000 |
| Aug 14, 2015 | Expired or cancelled cancelled Jan 2026 | 626 Polk St | convert (e) patio area into deck. maher na ref app#201012217097Details
convert (e) patio area into deck. maher na ref app#201012217097 | $5,000 |
| Jul 8, 2015 | Completed final sign-off Dec 2016 | 55 04th St | renovate (e) 4th flr fitness center & existing men's & women's locker rooms & add (4) new treatment rooms incl. new fcu's ductwrok & lighting. renovate (e) 5th flr pool deck & convert to fitness center. infill (e) pool & spa & remove (e) shower & restrm. new finishes & equip thru n/a maher ordinanceDetails
renovate (e) 4th flr fitness center & existing men's & women's locker rooms & add (4) new treatment rooms incl. new fcu's ductwrok & lighting. renovate (e) 5th flr pool deck & convert to fitness center. infill (e) pool & spa & remove (e) shower & restrm. new finishes & equip thru n/a maher ordinance | $450,000 |
| Apr 16, 2015 | Completed final sign-off Jun 2017 | 1563 Mission St | new clinic build out includes new 2/f, inclu new floor slab and struct framing. full build out of 5 floors w/new partitions, plumbing, mech, elec.signage, level 5 will house out patient clinic (oshpd 3 requirements) an awning and signage wil be mounted on mission st facade, deck, planters and roofDetails
new clinic build out includes new 2/f, inclu new floor slab and struct framing. full build out of 5 floors w/new partitions, plumbing, mech, elec.signage, level 5 will house out patient clinic (oshpd 3 requirements) an awning and signage wil be mounted on mission st facade, deck, planters and roof | $6,900,000 |
| Jun 27, 2014 | Completed final sign-off Feb 2015 | 600 Montgomery St | general contractor to remove abandoned existing stairway with associated drywall partitons. new structural steel beams, structural metal deck floor with concrete slab. reconstruct full height drywall partitionon 21st fl. maher not req 155-13Details
general contractor to remove abandoned existing stairway with associated drywall partitons. new structural steel beams, structural metal deck floor with concrete slab. reconstruct full height drywall partitionon 21st fl. maher not req 155-13 | $136,890 |
| Jan 18, 2012 | Never finaled issued Feb 2012, no final | 185 Berry St | 4th & 5th floors-revision to 201108031688. interior warm shell addition of 1 hr rated corridor (full height to metal deck) modify e lighting, e hvac, e sprinklers for new suspended lay in ceiling. add 20 min doors from unfinished shell space into 1 hr corridorDetails
4th & 5th floors-revision to 201108031688. interior warm shell addition of 1 hr rated corridor (full height to metal deck) modify e lighting, e hvac, e sprinklers for new suspended lay in ceiling. add 20 min doors from unfinished shell space into 1 hr corridor | $37,000 |
| May 22, 2009 | Completed final sign-off Jul 2009 | 1900 Jackson St | recoat deck/waterproof. install 2 metal rails on (e) parapet to bring up to code. safety/hazard new railing galvanized iron at back deck.Details
recoat deck/waterproof. install 2 metal rails on (e) parapet to bring up to code. safety/hazard new railing galvanized iron at back deck. | $10,000 |
| Apr 2, 2009 | Completed final sign-off May 2009 | 2211 Van Ness Av | increase cost per inspector's request due to dry/rot repairs to fix walls/ deck area at rear rooms from leakage. replace dry wall and damaged wood on walls/work approved by inspector 4/1. ref permit: 200903204570Details
increase cost per inspector's request due to dry/rot repairs to fix walls/ deck area at rear rooms from leakage. replace dry wall and damaged wood on walls/work approved by inspector 4/1. ref permit: 200903204570 | $25,000 |
| Mar 20, 2009 | Completed final sign-off May 2009 | 2211 Van Ness Av | exploratory demo to fix walls/deck area at rear room and underneath possible leakage from roof/deck. repair and waterproof as needed/no structural work. replace in kind.Details
exploratory demo to fix walls/deck area at rear room and underneath possible leakage from roof/deck. repair and waterproof as needed/no structural work. replace in kind. | $6,000 |
| Apr 10, 2008 | Never finaled issued Apr 2008, no final | 1 Market St | providing beam penetrations for waste pipe below deck of level 27, revision to pa #200711289077Details
providing beam penetrations for waste pipe below deck of level 27, revision to pa #200711289077 | $5,000 |
| Apr 9, 2008 | Completed final sign-off Oct 2008 | 1 Market St | 27th floor, steuart tower - addition of structural members below deck fot i.t. room ups battery, addition of steel platform in i.t. room for server cabinets, revision to pa# 2007-1128-9077Details
27th floor, steuart tower - addition of structural members below deck fot i.t. room ups battery, addition of steel platform in i.t. room for server cabinets, revision to pa# 2007-1128-9077 | $10,000 |