Block 3511, lot 031
1563 Mission St
- City’s use
- Commercial Office
- Built
- 1917
- Stories
- 5
- Units
- 1
- Building
- 50,024 sq ft
- Lot
- 10,149 sq ft
- Zoning
- C3G
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
47 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 15, 2026 | In progress issued Jan 2026 | 1563 Mission St | Battalion One Fire Protection | install one new wireless communicator and one new monitor module.Details
install one new wireless communicator and one new monitor module. | $9,000 |
| Jan 22, 2024 | Completed final sign-off May 2024 | 1563 Mission St | Rapid Fire Safety&Security Llc Dba Pafa | fire alarm t.i. adding 39 horn-strobes and 5 strobes to extg notifier nfs2-320 fire alarm system. ref ti pa 202310037895Details
fire alarm t.i. adding 39 horn-strobes and 5 strobes to extg notifier nfs2-320 fire alarm system. ref ti pa 202310037895 | $29,060 |
| Jan 18, 2024 | In progress issued Jan 2024 | 1563 Mission St | Battalion One Fire Protection | update (e) plans to add smoke beam detectors in the elevator shaft.Details
update (e) plans to add smoke beam detectors in the elevator shaft. | $2,000 |
| Oct 3, 2023 | Completed final sign-off May 2024 | 1563 Mission St | Swinerton Builders | 4th floor: construction of new non-structural partions, acoustical grid and tile drywall ceilings, light fixtures, mill work and finishes. also includes upgraded meps.Details
4th floor: construction of new non-structural partions, acoustical grid and tile drywall ceilings, light fixtures, mill work and finishes. also includes upgraded meps. | $2,907,146 |
| Jun 20, 2023 | Completed final sign-off Mar 2024 | 1563 Mission St | Anderson, Rowe & Buckley, Inc. | t.i - existing fire sprinkler system. 39 relocated and add 2 pendent sprinklers. 12 relocated and add 1 upgright sprinklers, 9 removed sprinklers on the 4/fDetails
t.i - existing fire sprinkler system. 39 relocated and add 2 pendent sprinklers. 12 relocated and add 1 upgright sprinklers, 9 removed sprinklers on the 4/f | $34,000 |
| Oct 7, 2020 | Completed final sign-off Dec 2020 | 1563 Mission St | Acco Engineered Systems Inc. Dba Acco En | rebalance of 3 (e) rooms to be negative. addexhaust ductwork and grilles to these spaces to accommodate new pressure relationshipDetails
rebalance of 3 (e) rooms to be negative. addexhaust ductwork and grilles to these spaces to accommodate new pressure relationship | $40,000 |
| Feb 3, 2020 | Never finaled issued Feb 2020, no final | 1563 Mission St | Capitol Electric Const | as-built permit for errcs replace yag antenna and bda. reprogram new frequencies. ref pa #201703242250.Details
as-built permit for errcs replace yag antenna and bda. reprogram new frequencies. ref pa #201703242250. | $20,000 |
| Sep 17, 2019 | Completed final sign-off Dec 2019 | 1563 Mission St | R. C. Construction | ti @ 2nd fl - remove interior partitions, add new parttions and doorsDetails
ti @ 2nd fl - remove interior partitions, add new parttions and doors | $40,000 |
| Sep 22, 2017 | Never finaled issued Sep 2017, no final | 1563 Mission St | Pacific Auxiliary Fire Alarm | revision to 201504163820, 201709188779: delta 2: field device additions/changes. add 2 control relay shunt trip, 1 dual mod for fsd status, 2 smoke det pendulm mounted replacing duct det, add 1 heat det, elevator control rm,delta 3 add control module for unlocking stair drs & emergency door releaseDetails
revision to 201504163820, 201709188779: delta 2: field device additions/changes. add 2 control relay shunt trip, 1 dual mod for fsd status, 2 smoke det pendulm mounted replacing duct det, add 1 heat det, elevator control rm,delta 3 add control module for unlocking stair drs & emergency door release | $1,820 |
| Sep 18, 2017 | Never finaled issued Sep 2017, no final | 1563 Mission St | Paganini Electric Corp(See Signatories) | revision to pa#201705187028 add life safety control at all stairwell exits, add new door hardware at all doors in exit egress path of travel.Details
revision to pa#201705187028 add life safety control at all stairwell exits, add new door hardware at all doors in exit egress path of travel. | $15,000 |
| May 18, 2017 | Never finaled issued May 2017, no final | 1563 Mission St | Hathaway Dinwiddie Co. | installation of evac signsDetails
installation of evac signs | $6,945 |
| Apr 12, 2017 | Never finaled issued Apr 2017, no final | 1563 Mission St | Golden Gate Fire Protection Inc | fire sprinkler - install 16'-0" of underground piping for new sprinkler system at 1563 misison st. as built to 2015-0515-6443Details
fire sprinkler - install 16'-0" of underground piping for new sprinkler system at 1563 misison st. as built to 2015-0515-6443 | $1,000 |
| Apr 10, 2017 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | to obtain final inspection for work approved under pa#200307230220. all work is complete.Details
to obtain final inspection for work approved under pa#200307230220. all work is complete. | |
| Apr 7, 2017 | Never finaled issued Apr 2017, no final | 1563 Mission St | Pacific Auxiliary Fire Alarm | revision to fire alarm permit 2016-0707-1774. adding remote annunciator and 3 addressable module to supervise new errcs being installed. errcs being installed under 2017-0324-2250.Details
revision to fire alarm permit 2016-0707-1774. adding remote annunciator and 3 addressable module to supervise new errcs being installed. errcs being installed under 2017-0324-2250. | $4,165 |
| Mar 24, 2017 | Completed final sign-off Apr 2018 | 1563 Mission St | Hathaway Dinwiddie Co. | install errcs emergency responder radio coverage system. ref. fa# 201607071774. to pa#2015-0416-3820 & 2017-0407-3492Details
install errcs emergency responder radio coverage system. ref. fa# 201607071774. to pa#2015-0416-3820 & 2017-0407-3492 | $48,000 |
| Feb 1, 2017 | Never finaled issued Feb 2017, no final | 1563 Mission St | street spaceDetails
street space | ||
| Feb 1, 2017 | Never finaled issued Feb 2017, no final | 1563 Mission St | street spaceDetails
street space | ||
| Oct 20, 2016 | Never finaled issued Oct 2016, no final | 1563 Mission St | street spaceDetails
street space | ||
| Oct 4, 2016 | Completed final sign-off Aug 2017 | 1563 Mission St | Golden Gate Fire Protection Inc | revision to pa #201505156443 - add flex head cut sheet to drawings per field fire inspector visual inspection.Details
revision to pa #201505156443 - add flex head cut sheet to drawings per field fire inspector visual inspection. | $1,000 |
| Aug 15, 2016 | Never finaled issued Aug 2016, no final | 1563 Mission St | street space permitDetails
street space permit | ||
| Aug 15, 2016 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | 5th floor: install 2 ahu air handling units. deferred submittal pa#2015-0416-3820.Details
5th floor: install 2 ahu air handling units. deferred submittal pa#2015-0416-3820. | |
| Jul 11, 2016 | Completed final sign-off Jun 2017 | 1563 Mission St | Martinelli Environmental Graph | install single faced electric sign (illuminated)Details
install single faced electric sign (illuminated) | $20,000 |
| Jul 11, 2016 | Completed final sign-off Jun 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | anchorage of electrical cabinets mounted on concrete housekeeping pads at ground floor and roof. ref. 2015-04-16-3820Details
anchorage of electrical cabinets mounted on concrete housekeeping pads at ground floor and roof. ref. 2015-04-16-3820 | $30,000 |
| Jul 7, 2016 | Never finaled issued Jul 2016, no final | 1563 Mission St | Pacific Auxiliary Fire Alarm | install new fire alarm system as part of building retrofit project. ref bldg permit #2015-04-16-3820.Details
install new fire alarm system as part of building retrofit project. ref bldg permit #2015-04-16-3820. | $50,000 |
| Jun 16, 2016 | Completed final sign-off Jun 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | install exterior steel sign structure on 3rd floor. sign is defferredDetails
install exterior steel sign structure on 3rd floor. sign is defferred | $60,000 |
| May 13, 2016 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | install window washing equipment on rooftop. ret. pa#201504163820Details
install window washing equipment on rooftop. ret. pa#201504163820 | $30,000 |
| Feb 12, 2016 | Never finaled filed Feb 2016, never issued | 1563 Mission St | street spaceDetails
street space | ||
| Feb 12, 2016 | Expired or cancelled suspend Dec 2017 | 1563 Mission St | street spaceDetails
street space | ||
| Dec 29, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | install/construct (2) staircases, this is deferred from permit 201501286888Details
install/construct (2) staircases, this is deferred from permit 201501286888 | $100,000 |
| Dec 1, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | 4th floor: remove vault walls. floor will be replaced with a steel framed metal deck/concrete slab in this bay. ref app#201501286888Details
4th floor: remove vault walls. floor will be replaced with a steel framed metal deck/concrete slab in this bay. ref app#201501286888 | $40,000 |
| Dec 1, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | exploratory excavation shows a new grade beam will need to be provided adjacent to extg foundation, east wall. ref app#201501286888Details
exploratory excavation shows a new grade beam will need to be provided adjacent to extg foundation, east wall. ref app#201501286888 | $30,000 |
| Nov 16, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | rev. to pa#201501286888, thicken roof slab by 2-1/2"Details
rev. to pa#201501286888, thicken roof slab by 2-1/2" | $25,000 |
| Nov 9, 2015 | Completed final sign-off Jun 2017 | 1563 Mission St | A & B Construction, Hathaway Dinwiddie Co. | exploratory excavation shows grade beam exists only from a to b grids, add grade beam to connect existing spread footings, orig. ref. permit 201501286888Details
exploratory excavation shows grade beam exists only from a to b grids, add grade beam to connect existing spread footings, orig. ref. permit 201501286888 | $40,000 |
| Nov 2, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | structural revision. ref app#2015-0128-6888, vertical alignment of new shotcrete & reinforcement to match piers & spandrels 0f northwallDetails
structural revision. ref app#2015-0128-6888, vertical alignment of new shotcrete & reinforcement to match piers & spandrels 0f northwall | $20,000 |
| Aug 14, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | removal of existing ground floor slabs on grade approx. 9000 s.f. complaint #201558481 is under separate permit. maher n/a.Details
removal of existing ground floor slabs on grade approx. 9000 s.f. complaint #201558481 is under separate permit. maher n/a. | $30,000 |
| Jul 22, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | excavation near two footings for structural investigation. maher n/a.Details
excavation near two footings for structural investigation. maher n/a. | $10,000 |
| May 15, 2015 | Completed final sign-off Aug 2017 | 1563 Mission St | Golden Gate Fire Protection Inc | fire sprinklers to replace the extg fire sprinkler system with new pump and shell fire system based on 2013 nfpa 13 & 24. future 5th and 3rd floor occupancy designed to ordinary hazard ii where lab work will occur. 1st,2nd, & 4th floor occupancy designed for light hazard medical offices & exam.Details
fire sprinklers to replace the extg fire sprinkler system with new pump and shell fire system based on 2013 nfpa 13 & 24. future 5th and 3rd floor occupancy designed to ordinary hazard ii where lab work will occur. 1st,2nd, & 4th floor occupancy designed for light hazard medical offices & exam. | $257,500 |
| May 7, 2015 | Never finaled issued May 2015, no final | 1563 Mission St | street spaceDetails
street space | ||
| Apr 16, 2015 | Completed final sign-off Jun 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | new clinic build out includes new 2/f, inclu new floor slab and struct framing. full build out of 5 floors w/new partitions, plumbing, mech, elec.signage, level 5 will house out patient clinic (oshpd 3 requirements) an awning and signage wil be mounted on mission st facade, deck, planters and roofDetails
new clinic build out includes new 2/f, inclu new floor slab and struct framing. full build out of 5 floors w/new partitions, plumbing, mech, elec.signage, level 5 will house out patient clinic (oshpd 3 requirements) an awning and signage wil be mounted on mission st facade, deck, planters and roof | $6,900,000 |
| Feb 13, 2015 | Completed final sign-off May 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | soft demolition including removal of all interior finishes, roofing material, 2nd floor intestitial space leaving all concrete structural elements in place. space remain vacant for whole bldg per ab-017.Details
soft demolition including removal of all interior finishes, roofing material, 2nd floor intestitial space leaving all concrete structural elements in place. space remain vacant for whole bldg per ab-017. | $50,000 |
| Jan 28, 2015 | Completed final sign-off Jun 2017 | 1563 Mission St | Hathaway Dinwiddie Co. | seismic retrofit of light industrial bldg. north window, west window and south window replacement. minor interior work including exit stairs and elevators.Details
seismic retrofit of light industrial bldg. north window, west window and south window replacement. minor interior work including exit stairs and elevators. | $12,500,000 |
| Aug 2, 2007 | Completed final sign-off Jul 2014 | 1563 Mission St | Bcw Construction | to comply with nov# 200227101 & # 200227101a. restaurant has been vacant for approx 2 year. side work permit# 03mse-461.Details
to comply with nov# 200227101 & # 200227101a. restaurant has been vacant for approx 2 year. side work permit# 03mse-461. | |
| Feb 23, 2004 | Never finaled issued Feb 2004, no final | 1563 Mission St | sidewalk repair onlyDetails
sidewalk repair only | ||
| Jul 23, 2003 | Expired or cancelled expired May 2017 | 1563 Mission St | handicap access to restaurant entrance, provide auto door opener & control comply w/novDetails
handicap access to restaurant entrance, provide auto door opener & control comply w/nov | $2,200 | |
| Jun 2, 2003 | Completed final sign-off Jul 2003 | 1563 Mission St | to renew app#2002/01/18/7330 for final inspection.Details
to renew app#2002/01/18/7330 for final inspection. | ||
| Mar 21, 2002 | Completed final sign-off Apr 2002 | 1563 Mission St | A-1 Steam & Fire Protection | installed fire suppression system to kitchen hoodDetails
installed fire suppression system to kitchen hood | $2,000 |
| Jan 18, 2002 | Expired or cancelled expired May 2003 | 1563 Mission St | install hood sys. & related kitchen equip., tile flooring for entire restaurant, kitchen counterDetails
install hood sys. & related kitchen equip., tile flooring for entire restaurant, kitchen counter | $50,000 |
Find contractors for work like this