Permit GraphShortlistSan Francisco building permits since 2000

Custom 6 Builders

Contractor license
969484
State license record
Based in
Oakland
On San Francisco permits
May 2011 to Dec 2024
Last 24 months
1 permit filed

18 permits since 2000: 14 completed, 1 in progress, 3 never finaled.

Of the 3 never-finaled permits, 3 are 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Stairs permits

AllDeck 5Stairs 4Kitchen remodel 6Bathroom remodel 12

4 stairs permits: 3 completed, 1 never finaled. Typically 474 days from filing to permit and 370 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
Mar 18, 2021Completed
final sign-off Nov 2022
162 Parker Avadd a studio unit within (e) 1st floor. renovate (e) 2nd fl kitchen, bathroom & bedrooms & add a bathroom, laundry closet & spiral stair to backyard.
Details
Permit
202103186785
Status
complete
Filed
Mar 18, 2021
Permit issued
Nov 12, 2021
Final sign-off
Nov 17, 2022
Declared cost
$235,000
Address
162 Parker Av

add a studio unit within (e) 1st floor. renovate (e) 2nd fl kitchen, bathroom & bedrooms & add a bathroom, laundry closet & spiral stair to backyard.

Open the permit page

$235,000
Jun 24, 2019Never finaled
issued Jun 2021, no final
337 Douglass Sthorizontal & vertical to (e) sfh. vertical of approx 3' @ rear portion of roof. horizontal of 14' @ rear & at sw corner @ front. new interior stair. renovated kitchen & bath & new bathrooms. addition of new bedroom & entertainment room. rear yard retaining walls. deck & pool. replace fence.
Details
Permit
201906244269
Status
issued
Filed
Jun 24, 2019
Permit issued
Jun 1, 2021
Declared cost
$300,000
Address
337 Douglass St

horizontal & vertical to (e) sfh. vertical of approx 3' @ rear portion of roof. horizontal of 14' @ rear & at sw corner @ front. new interior stair. renovated kitchen & bath & new bathrooms. addition of new bedroom & entertainment room. rear yard retaining walls. deck & pool. replace fence.

Open the permit page

$300,000
May 3, 2012Completed
final sign-off Jan 2013
565 Jersey Stexcavate existing basement to create new habitable space including 2 bedrooms & 2 baths. new interior stair to connect new habitable space, partially excavate rear yard for new exterior aptio (demo existing deck), new structural renovations throughout basement level.
Details
Permit
201205039681
Status
complete
Filed
May 3, 2012
Permit issued
May 29, 2012
Final sign-off
Jan 4, 2013
Declared cost
$75,000
Address
565 Jersey St

excavate existing basement to create new habitable space including 2 bedrooms & 2 baths. new interior stair to connect new habitable space, partially excavate rear yard for new exterior aptio (demo existing deck), new structural renovations throughout basement level.

Open the permit page

$75,000
May 16, 2011Completed
final sign-off Oct 2015
439 Clipper Sthorizontal addition, rearrange rooms bathrooms & stair. add rooms bathrms at each floor, add new garage.
Details
Permit
201105166108
Status
complete
Filed
May 16, 2011
Permit issued
Oct 21, 2013
Final sign-off
Oct 28, 2015
Declared cost
$160,000
Address
439 Clipper St

horizontal addition, rearrange rooms bathrooms & stair. add rooms bathrms at each floor, add new garage.

Open the permit page

$160,000