Permit GraphShortlistSan Francisco building permits since 2000

Block 7335, lot 001

403 Font Blvd

The city’s assessor roll has no record for this parcel.

Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

58 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Apr 23, 2026Completed
final sign-off May 2026
116 Juan Bautista CrAtlas Roofing Bay Areareroofing torch down.
Details
Permit
202604239973
Status
complete
Filed
Apr 23, 2026
Permit issued
Apr 24, 2026
Final sign-off
May 15, 2026
Declared cost
$16,030
Address
116 Juan Bautista Cr

reroofing torch down.

Open the permit page

$16,030
Mar 26, 2026Completed
final sign-off Apr 2026
110 Juan Bautista CrAtlas Roofing Bay Areaunit 108 juan bautista: reroof, no hot work.
Details
Permit
202603268352
Status
complete
Filed
Mar 26, 2026
Permit issued
Mar 31, 2026
Final sign-off
Apr 23, 2026
Declared cost
$20,960
Address
110 Juan Bautista Cr

unit 108 juan bautista: reroof, no hot work.

Open the permit page

$20,960
Mar 13, 2026In progress
issued Mar 2026
810 Gonzalez DrRahimi Constructionto comply with ces nov# 20265226. interior lobby finish renovation of drywall patching & infill, and painting of walls & ceilings. no structural work. no change to egress or occupancy.
Details
Permit
202603137552
Status
issued
Filed
Mar 13, 2026
Permit issued
Mar 13, 2026
Declared cost
$23,000
Address
810 Gonzalez Dr

to comply with ces nov# 20265226. interior lobby finish renovation of drywall patching & infill, and painting of walls & ceilings. no structural work. no change to egress or occupancy.

Open the permit page

$23,000
Dec 18, 2025Completed
final sign-off Jan 2026
423 Font BlAtlas Roofing Bay Areare-roofing (no hotworks)
Details
Permit
202512182190
Status
complete
Filed
Dec 18, 2025
Permit issued
Dec 18, 2025
Final sign-off
Jan 14, 2026
Declared cost
$18,624
Address
423 Font Bl

re-roofing (no hotworks)

Open the permit page

$18,624
Dec 12, 2025In progress
filed Dec 2025, not yet issued
810 Gonzalez Drreplace ceiling light fixtures at common area corridors at existing j box on lobby, first to 12/f
Details
Permit
202512121663
Status
filed
Filed
Dec 12, 2025
Declared cost
$20,000
Address
810 Gonzalez Dr

replace ceiling light fixtures at common area corridors at existing j box on lobby, first to 12/f

Open the permit page

$20,000
Dec 12, 2025In progress
filed Dec 2025, not yet issued
355 Serrano Drreplace ceiling light fixtures at common area corridors at existing j box on lobby, first to 12/f
Details
Permit
202512121664
Status
filed
Filed
Dec 12, 2025
Declared cost
$20,000
Address
355 Serrano Dr

replace ceiling light fixtures at common area corridors at existing j box on lobby, first to 12/f

Open the permit page

$20,000
Dec 11, 2025In progress
filed Dec 2025, not yet issued
405 Serrano Drreplace ceiling light fixtures at common area corridors at existing j-box on first to twelve floors and basement.
Details
Permit
202512111515
Status
filed
Filed
Dec 11, 2025
Declared cost
$20,000
Address
405 Serrano Dr

replace ceiling light fixtures at common area corridors at existing j-box on first to twelve floors and basement.

Open the permit page

$20,000
Nov 13, 2025Completed
final sign-off Dec 2025
116 Juan Bautista CrAtlas Roofing Bay Areareroofing: tile lift 1700 sqft, install new underlayment and reset existing tiles. no torch.
Details
Permit
202511139581
Status
complete
Filed
Nov 13, 2025
Permit issued
Nov 14, 2025
Final sign-off
Dec 22, 2025
Declared cost
$8,940
Address
116 Juan Bautista Cr

reroofing: tile lift 1700 sqft, install new underlayment and reset existing tiles. no torch.

Open the permit page

$8,940
Jun 27, 2016Never finaled
issued Jul 2016, no final
750 Gonzalez DrA S F Electric Increvisions to lighting in lobby, revision to lighting & laundry equipment in basement. revision to storage area - create work out area. replace light fixtures. ref pa 2015-0813-4218
Details
Permit
201606270962
Status
issued
Filed
Jun 27, 2016
Permit issued
Jul 12, 2016
Address
750 Gonzalez Dr

revisions to lighting in lobby, revision to lighting & laundry equipment in basement. revision to storage area - create work out area. replace light fixtures. ref pa 2015-0813-4218

Open the permit page

May 16, 2016Never finaled
issued Jun 2018, no final
810 Gonzalez Drexterior landscape & infrastructure improvements incl utilities, site grading, stairs, planting soil, understory planting, tree planting, irrigation, a play area & community garden.
Details
Permit
201605167541
Status
issued
Filed
May 16, 2016
Permit issued
Jun 12, 2018
Declared cost
$4,260,594
Address
810 Gonzalez Dr

exterior landscape & infrastructure improvements incl utilities, site grading, stairs, planting soil, understory planting, tree planting, irrigation, a play area & community garden.

Open the permit page

$4,260,594
Oct 23, 2015Never finaled
filed Oct 2015, never issued
455 Serrano Drerect an 11 story, 248 covered multi-family dwelling unit building
Details
Permit
201510230640
Status
approved
Filed
Oct 23, 2015
Declared cost
$56,227,346
Address
455 Serrano Dr

erect an 11 story, 248 covered multi-family dwelling unit building

Open the permit page

$56,227,346
Aug 13, 2015Completed
final sign-off Mar 2017
750 Gonzalez DrNorthern Sun Associates1400 sf ti work, change finishes at lobby. 1000 sf ti basement, change finishes, laundry. 1200 sf convert storage to workout area replace light fixtures
Details
Permit
201508134218
Status
complete
Filed
Aug 13, 2015
Permit issued
Feb 10, 2016
Final sign-off
Mar 3, 2017
Declared cost
$378,000
Address
750 Gonzalez Dr

1400 sf ti work, change finishes at lobby. 1000 sf ti basement, change finishes, laundry. 1200 sf convert storage to workout area replace light fixtures

Open the permit page

$378,000
Jun 27, 2014Never finaled
issued Jun 2014, no final
355 Serrano Drapt#6 g - street space
Details
Permit
M500387
Status
issued
Filed
Jun 27, 2014
Permit issued
Jun 27, 2014
Address
355 Serrano Dr

apt#6 g - street space

Open the permit page

Apr 28, 2014Completed
final sign-off Sep 2014
355 Serrano DrLegacy Roofing & Waterproofing Increroofing
Details
Permit
201404284286
Status
complete
Filed
Apr 28, 2014
Permit issued
Apr 28, 2014
Final sign-off
Sep 15, 2014
Declared cost
$206,819
Address
355 Serrano Dr

reroofing

Open the permit page

$206,819
Apr 28, 2014Completed
final sign-off Jul 2014
750 Gonzalez DrLegacy Roofing & Waterproofing Increroofing
Details
Permit
201404284287
Status
complete
Filed
Apr 28, 2014
Permit issued
Apr 28, 2014
Final sign-off
Jul 2, 2014
Declared cost
$206,819
Address
750 Gonzalez Dr

reroofing

Open the permit page

$206,819
Jun 26, 2013Completed
final sign-off Oct 2013
405 Serrano DrLegacy Roofing & Waterproofing Increroofing, requred to have sffd permits for hotwork and use of propane
Details
Permit
201306260520
Status
complete
Filed
Jun 26, 2013
Permit issued
Jun 26, 2013
Final sign-off
Oct 10, 2013
Declared cost
$203,145
Address
405 Serrano Dr

reroofing, requred to have sffd permits for hotwork and use of propane

Open the permit page

$203,145
Apr 26, 2012Completed
final sign-off Jul 2012
405 Serrano DrSurber Constructionvoluntary upgrade of basement non bearing partition walls.
Details
Permit
201204269218
Status
complete
Filed
Apr 26, 2012
Permit issued
May 10, 2012
Final sign-off
Jul 18, 2012
Declared cost
$15,000
Address
405 Serrano Dr

voluntary upgrade of basement non bearing partition walls.

Open the permit page

$15,000
Apr 26, 2012Completed
final sign-off Jun 2012
750 Gonzalez DrSurber Constructionvoluntary upgrae of basement non bearing partition walls
Details
Permit
201204269181
Status
complete
Filed
Apr 26, 2012
Permit issued
May 10, 2012
Final sign-off
Jun 22, 2012
Declared cost
$15,000
Address
750 Gonzalez Dr

voluntary upgrae of basement non bearing partition walls

Open the permit page

$15,000
Apr 26, 2012Completed
final sign-off Jun 2012
810 Gonzalez DrSurber Constructionvoluntary upgrade of basement non bearing partition walls
Details
Permit
201204269182
Status
complete
Filed
Apr 26, 2012
Permit issued
May 10, 2012
Final sign-off
Jun 22, 2012
Declared cost
$15,000
Address
810 Gonzalez Dr

voluntary upgrade of basement non bearing partition walls

Open the permit page

$15,000
Apr 26, 2012Completed
final sign-off Jul 2012
355 Serrano DrSurber Constructionvoluntary upgrade of basement non bearing partition walls
Details
Permit
201204269184
Status
complete
Filed
Apr 26, 2012
Permit issued
May 10, 2012
Final sign-off
Jul 18, 2012
Declared cost
$15,000
Address
355 Serrano Dr

voluntary upgrade of basement non bearing partition walls

Open the permit page

$15,000
Sep 10, 2009Completed
final sign-off Nov 2009
810 Gonzalez DrLegacy Roofing & Waterproofing Increroofing
Details
Permit
200909106498
Status
complete
Filed
Sep 10, 2009
Permit issued
Sep 10, 2009
Final sign-off
Nov 23, 2009
Declared cost
$185,000
Address
810 Gonzalez Dr

reroofing

Open the permit page

$185,000
Oct 10, 2008Completed
final sign-off Oct 2008
423 Font BlCal State Roofing Co Increroofing.
Details
Permit
200810103974
Status
complete
Filed
Oct 10, 2008
Permit issued
Oct 10, 2008
Final sign-off
Oct 29, 2008
Declared cost
$25,000
Address
423 Font Bl

reroofing.

Open the permit page

$25,000
Jun 13, 2008Never finaled
issued Jun 2008, no final
700 Gonzalez DrNorthern Pacific Roofingreroofing
Details
Permit
200806134343
Status
issued
Filed
Jun 13, 2008
Permit issued
Jun 13, 2008
Declared cost
$23,900
Address
700 Gonzalez Dr

reroofing

Open the permit page

$23,900
Jun 2, 2008Completed
final sign-off Oct 2008
355 Serrano DrBrayer Electric Companytower 46 - revision to 200712180801: installation of generator at tower 46.
Details
Permit
200806023408
Status
complete
Filed
Jun 2, 2008
Permit issued
Jul 23, 2008
Final sign-off
Oct 10, 2008
Address
355 Serrano Dr

tower 46 - revision to 200712180801: installation of generator at tower 46.

Open the permit page

Jun 2, 2008Completed
final sign-off Oct 2008
810 Gonzalez DrBrayer Electric Companytower 27 - revision to 200712180793: installation of generator at tower 27.
Details
Permit
200806023405
Status
complete
Filed
Jun 2, 2008
Permit issued
Jul 23, 2008
Final sign-off
Oct 14, 2008
Address
810 Gonzalez Dr

tower 27 - revision to 200712180793: installation of generator at tower 27.

Open the permit page

Jun 2, 2008Completed
final sign-off Oct 2008
405 Serrano DrBrayer Electric Companytower 47 - revision to 200712180787: installation of generator at tower 47.
Details
Permit
200806023407
Status
complete
Filed
Jun 2, 2008
Permit issued
Jul 23, 2008
Final sign-off
Oct 14, 2008
Address
405 Serrano Dr

tower 47 - revision to 200712180787: installation of generator at tower 47.

Open the permit page

Jun 2, 2008Completed
final sign-off Oct 2008
750 Gonzalez DrBrayer Electric Companytower 26 - revision to 200712180783: installation of generator at tower 26.
Details
Permit
200806023406
Status
complete
Filed
Jun 2, 2008
Permit issued
Jul 23, 2008
Final sign-off
Oct 14, 2008
Address
750 Gonzalez Dr

tower 26 - revision to 200712180783: installation of generator at tower 26.

Open the permit page

May 30, 2008Completed
final sign-off Sep 2008
810 Gonzalez Drinterior tenant improvements on ground floor, convert activity center to fitness center, new counter, fire rated door & window in (e) business center.
Details
Permit
200805303318
Status
complete
Filed
May 30, 2008
Permit issued
Jun 2, 2008
Final sign-off
Sep 25, 2008
Declared cost
$16,750
Address
810 Gonzalez Dr

interior tenant improvements on ground floor, convert activity center to fitness center, new counter, fire rated door & window in (e) business center.

Open the permit page

$16,750
May 30, 2008Completed
final sign-off Sep 2008
750 Gonzalez Drinterior tenant improvements on ground floor- convert activity center to fitness center, new coutner, fire rated door, window in (e) business center.
Details
Permit
200805303312
Status
complete
Filed
May 30, 2008
Permit issued
Jun 2, 2008
Final sign-off
Sep 19, 2008
Declared cost
$16,750
Address
750 Gonzalez Dr

interior tenant improvements on ground floor- convert activity center to fitness center, new coutner, fire rated door, window in (e) business center.

Open the permit page

$16,750
Apr 10, 2008Never finaled
issued Apr 2008, no final
2 Bucareli DrNorthern Pacific Roofingreroofing.
Details
Permit
200804109311
Status
issued
Filed
Apr 10, 2008
Permit issued
Apr 10, 2008
Declared cost
$5,656
Address
2 Bucareli Dr

reroofing.

Open the permit page

$5,656
Feb 28, 2008Completed
final sign-off Jul 2008
405 Serrano Drground floor: interior tenant improvement, convert activity center to fitness center, new counter in business center, new fire rated doors & windows. comply w/ nov 200841530
Details
Permit
200802285805
Status
complete
Filed
Feb 28, 2008
Permit issued
Mar 3, 2008
Final sign-off
Jul 14, 2008
Declared cost
$16,750
Address
405 Serrano Dr

ground floor: interior tenant improvement, convert activity center to fitness center, new counter in business center, new fire rated doors & windows. comply w/ nov 200841530

Open the permit page

$16,750
Feb 26, 2008Completed
final sign-off Jul 2008
355 Serrano Drinterior tenant improvement to convert activity center to fitness center. construct new counters, new fire rated doors and windows.
Details
Permit
200802265564
Status
complete
Filed
Feb 26, 2008
Permit issued
Feb 26, 2008
Final sign-off
Jul 14, 2008
Declared cost
$16,750
Address
355 Serrano Dr

interior tenant improvement to convert activity center to fitness center. construct new counters, new fire rated doors and windows.

Open the permit page

$16,750
Dec 18, 2007Completed
final sign-off Oct 2008
405 Serrano DrBrayer Electric Companybuild structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.
Details
Permit
200712180787
Status
complete
Filed
Dec 18, 2007
Permit issued
Dec 20, 2007
Final sign-off
Oct 14, 2008
Declared cost
$50,000
Address
405 Serrano Dr

build structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.

Open the permit page

$50,000
Dec 18, 2007Completed
final sign-off Oct 2008
750 Gonzalez DrBrayer Electric Companybuild structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.
Details
Permit
200712180783
Status
complete
Filed
Dec 18, 2007
Permit issued
Dec 20, 2007
Final sign-off
Oct 14, 2008
Declared cost
$50,000
Address
750 Gonzalez Dr

build structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.

Open the permit page

$50,000
Dec 18, 2007Completed
final sign-off Oct 2008
810 Gonzalez DrBrayer Electric Companybuild structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.
Details
Permit
200712180793
Status
complete
Filed
Dec 18, 2007
Permit issued
Dec 20, 2007
Final sign-off
Oct 14, 2008
Declared cost
$50,000
Address
810 Gonzalez Dr

build structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.

Open the permit page

$50,000
Dec 18, 2007Completed
final sign-off Oct 2008
355 Serrano DrBrayer Electric Companybuild structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.
Details
Permit
200712180801
Status
complete
Filed
Dec 18, 2007
Permit issued
Dec 20, 2007
Final sign-off
Oct 10, 2008
Declared cost
$50,000
Address
355 Serrano Dr

build structural concrete pad to support new generator. install new electrical conduit/wiring to (e) building panel board located in basement of building being served. generator installation under separate permit.

Open the permit page

$50,000
Sep 26, 2007Completed
final sign-off Sep 2008
750 Gonzalez DrDome Construction Corpvoluntary accessibility upgrades including van accessible parking space path of travel & new entrance ramp and stair. (n)exterior covered glass canopy & two (n) exterior windows. full interior gut & remodel of the main lobby incl. (n)finishes, millwork & lighting. new ramp retaining wall.
Details
Permit
200709263745
Status
complete
Filed
Sep 26, 2007
Permit issued
Jan 31, 2008
Final sign-off
Sep 19, 2008
Declared cost
$350,000
Address
750 Gonzalez Dr

voluntary accessibility upgrades including van accessible parking space path of travel & new entrance ramp and stair. (n)exterior covered glass canopy & two (n) exterior windows. full interior gut & remodel of the main lobby incl. (n)finishes, millwork & lighting. new ramp retaining wall.

Open the permit page

$350,000
Sep 24, 2007Completed
final sign-off Nov 2008
810 Gonzalez DrDome Construction Corpvolunteer accessibility upgrades inclduing van accessible parking space, path of travel & new entrance & stair. new exterior covered glass canopy & 2 new exterior windows. full interior gut & remodel of the bldg. main lobby including new finishes, millwork & lighting.
Details
Permit
200709243485
Status
complete
Filed
Sep 24, 2007
Permit issued
Jan 31, 2008
Final sign-off
Nov 19, 2008
Declared cost
$350,000
Address
810 Gonzalez Dr

volunteer accessibility upgrades inclduing van accessible parking space, path of travel & new entrance & stair. new exterior covered glass canopy & 2 new exterior windows. full interior gut & remodel of the bldg. main lobby including new finishes, millwork & lighting.

Open the permit page

$350,000
Sep 20, 2007Never finaled
issued Oct 2007, no final
750 Gonzalez DrBrayer Electric Companynew fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator control, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies for strobe circuits. use (e) est-3 panel.
Details
Permit
200709203241
Status
issued
Filed
Sep 20, 2007
Permit issued
Oct 4, 2007
Declared cost
$148,000
Address
750 Gonzalez Dr

new fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator control, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies for strobe circuits. use (e) est-3 panel.

Open the permit page

$148,000
Sep 20, 2007Never finaled
issued Oct 2007, no final
355 Serrano DrBrayer Electric Companynew fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits, ex. est-3 panel.
Details
Permit
200709203247
Status
issued
Filed
Sep 20, 2007
Permit issued
Oct 4, 2007
Declared cost
$148,000
Address
355 Serrano Dr

new fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits, ex. est-3 panel.

Open the permit page

$148,000
Sep 20, 2007Never finaled
issued Oct 2007, no final
810 Gonzalez DrBrayer Electric Companynew fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits.
Details
Permit
200709203233
Status
issued
Filed
Sep 20, 2007
Permit issued
Oct 4, 2007
Declared cost
$148,000
Address
810 Gonzalez Dr

new fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits.

Open the permit page

$148,000
Sep 20, 2007Never finaled
issued Oct 2007, no final
405 Serrano DrBrayer Electric Companynew fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits.
Details
Permit
200709203255
Status
issued
Filed
Sep 20, 2007
Permit issued
Oct 4, 2007
Declared cost
$148,000
Address
405 Serrano Dr

new fire alarm system includes manual pull stations, smoke detectors, control modules and detectors for elevator controle, monitor modules for sprinkler system supervision, audible/visual notification appliances, booster power supplies fo strobe circuits.

Open the permit page

$148,000
Sep 4, 2007Completed
final sign-off Jul 2008
355 Serrano DrDome Construction Corpvoluntary accessibility upgrades including van accessible parking space, path of travel & new entrance & stair, new exterior covered glass canopy & 2 new exterior windows. full interior gut & remodel of bldg. main lobby including new finishes, millwork & lighting.
Details
Permit
200709041695
Status
complete
Filed
Sep 4, 2007
Permit issued
Dec 13, 2007
Final sign-off
Jul 17, 2008
Declared cost
$350,000
Address
355 Serrano Dr

voluntary accessibility upgrades including van accessible parking space, path of travel & new entrance & stair, new exterior covered glass canopy & 2 new exterior windows. full interior gut & remodel of bldg. main lobby including new finishes, millwork & lighting.

Open the permit page

$350,000
Sep 4, 2007Completed
final sign-off Jul 2008
405 Serrano DrDome Construction Corpvoluntary accessibility upgrades including van accessible parking space, path of travel & new entrance ramp & stair. new exterior covered glass, canopy & 2 new exterior windows. full interior gut & remodel of bldg. main lobby including new finisehs, millwork & lighting.
Details
Permit
200709041697
Status
complete
Filed
Sep 4, 2007
Permit issued
Dec 13, 2007
Final sign-off
Jul 17, 2008
Declared cost
$350,000
Address
405 Serrano Dr

voluntary accessibility upgrades including van accessible parking space, path of travel & new entrance ramp & stair. new exterior covered glass, canopy & 2 new exterior windows. full interior gut & remodel of bldg. main lobby including new finisehs, millwork & lighting.

Open the permit page

$350,000
May 16, 2007Completed
final sign-off Jul 2007
14 Bucareli DrNorthern Sun Associatesdryrot repair - remove & replace 2x4 frame 3/4 cdx porch roof (200 sq ft approx) less than 50%. repair in kind.
Details
Permit
200705161399
Status
complete
Filed
May 16, 2007
Permit issued
May 16, 2007
Final sign-off
Jul 12, 2007
Declared cost
$4,000
Address
14 Bucareli Dr

dryrot repair - remove & replace 2x4 frame 3/4 cdx porch roof (200 sq ft approx) less than 50%. repair in kind.

Open the permit page

$4,000
Nov 16, 2006Completed
final sign-off Sep 2007
423 Font BlNorthern Sun Associatesvoluntary seismic upgrade refer to sheet s2.10 for scope of work.
Details
Permit
200611167874
Status
complete
Filed
Nov 16, 2006
Permit issued
Feb 21, 2007
Final sign-off
Sep 18, 2007
Declared cost
$11,270
Address
423 Font Bl

voluntary seismic upgrade refer to sheet s2.10 for scope of work.

Open the permit page

$11,270
Nov 16, 2006Completed
final sign-off Sep 2007
22 Bucareli DrNorthern Sun Associatesvoluntary seismic upgrade refer to sheet s2.13 for scope of work.
Details
Permit
200611167872
Status
complete
Filed
Nov 16, 2006
Permit issued
Feb 21, 2007
Final sign-off
Sep 17, 2007
Declared cost
$15,150
Address
22 Bucareli Dr

voluntary seismic upgrade refer to sheet s2.13 for scope of work.

Open the permit page

$15,150
Nov 16, 2006Never finaled
issued Feb 2007, no final
425 Font BlNorthern Sun Associatesvoluntary seismic upgrade refer to sheet s2.10 for scope of work.
Details
Permit
200611167875
Status
issued
Filed
Nov 16, 2006
Permit issued
Feb 21, 2007
Declared cost
$11,270
Address
425 Font Bl

voluntary seismic upgrade refer to sheet s2.10 for scope of work.

Open the permit page

$11,270
Nov 16, 2006Completed
final sign-off Sep 2007
24 Bucareli DrNorthern Sun Associatesvoluntary seismic upgrade refer to sheet s2.13 for scope of work.
Details
Permit
200611167873
Status
complete
Filed
Nov 16, 2006
Permit issued
Feb 21, 2007
Final sign-off
Sep 17, 2007
Declared cost
$15,150
Address
24 Bucareli Dr

voluntary seismic upgrade refer to sheet s2.13 for scope of work.

Open the permit page

$15,150
Mar 31, 2006Never finaled
issued Mar 2006, no final
411 Font BlNorthern Pacific Roofingreroofing
Details
Permit
200603317980
Status
issued
Filed
Mar 31, 2006
Permit issued
Mar 31, 2006
Declared cost
$4,000
Address
411 Font Bl

reroofing

Open the permit page

$4,000
Jan 25, 2006Never finaled
issued Jan 2006, no final
104 Juan Bautista CrNorthern Pacific Roofingreroofing
Details
Permit
200601252959
Status
issued
Filed
Jan 25, 2006
Permit issued
Jan 25, 2006
Declared cost
$5,925
Address
104 Juan Bautista Cr

reroofing

Open the permit page

$5,925
Nov 16, 2005Never finaled
issued Nov 2005, no final
22 Bucareli DrNorthern Pacific Roofingreroofing
Details
Permit
200511168214
Status
issued
Filed
Nov 16, 2005
Permit issued
Nov 16, 2005
Declared cost
$4,800
Address
22 Bucareli Dr

reroofing

Open the permit page

$4,800
Nov 16, 2004Expired or cancelled
expired Apr 2006
750 Gonzalez DrDiversified Fire Productsemergency fire alarm panel replacement. under separate permit, we will upgrade complete building,
Details
Permit
200411169283
Status
expired
Filed
Nov 16, 2004
Permit issued
Nov 16, 2004
Declared cost
$9,600
Address
750 Gonzalez Dr

emergency fire alarm panel replacement. under separate permit, we will upgrade complete building,

Open the permit page

$9,600
Sep 4, 2003Never finaled
issued Sep 2003, no final
80 Juan Bautista CrNorthern Sun Associatesrevise to appln #200208285068 - add 1/2 plywood at roof "as built"
Details
Permit
200309043843
Status
issued
Filed
Sep 4, 2003
Permit issued
Sep 4, 2003
Declared cost
$9,000
Address
80 Juan Bautista Cr

revise to appln #200208285068 - add 1/2 plywood at roof "as built"

Open the permit page

$9,000
May 5, 2003Completed
final sign-off Nov 2003
80 Juan Bautista CrBay Alarm Companyinstall fire alarm system
Details
Permit
200305053825
Status
complete
Filed
May 5, 2003
Permit issued
May 29, 2003
Final sign-off
Nov 24, 2003
Declared cost
$6,500
Address
80 Juan Bautista Cr

install fire alarm system

Open the permit page

$6,500
Aug 28, 2002Completed
final sign-off Oct 2003
80 Juan Bautista CrNorthern Sun Associatesto erect 1 story school
Details
Permit
200208285068
Status
complete
Filed
Aug 28, 2002
Permit issued
Jan 21, 2003
Final sign-off
Oct 16, 2003
Declared cost
$900,000
Address
80 Juan Bautista Cr

to erect 1 story school

Open the permit page

$900,000
Feb 4, 2002Expired or cancelled
expired Jun 2002
114 Juan Bautista CrHornstein Roofingreroofing
Details
Permit
200202048325
Status
expired
Filed
Feb 4, 2002
Permit issued
Feb 4, 2002
Declared cost
$4,470
Address
114 Juan Bautista Cr

reroofing

Open the permit page

$4,470
Apr 9, 2001Expired or cancelled
expired Aug 2001
706 Gonzalez Drsidewalk repair
Details
Permit
M15908
Status
expired
Filed
Apr 9, 2001
Permit issued
Apr 10, 2001
Address
706 Gonzalez Dr

sidewalk repair

Open the permit page

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.