Permits filed here
26 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 26, 2024 | Expired or cancelled withdrawn Dec 2024 | 555 19th St | install non-electric single faced wall sign "robust intelligence"Details
install non-electric single faced wall sign "robust intelligence" | $5,500 | |
| Dec 14, 2023 | Completed final sign-off Feb 2024 | 555 19th St | Bay Alarm Company | the intent of this submittal is to show the upgrade of the existing dedicated functions fire alarm system with group 2 elevator recall, water flow and supervisory monitoringDetails
the intent of this submittal is to show the upgrade of the existing dedicated functions fire alarm system with group 2 elevator recall, water flow and supervisory monitoring | $9,495 |
| Mar 9, 2023 | Completed final sign-off Mar 2023 | 555 19th St | Project Contractor Inc | 1/f: modify fire sprinkler system to accommodate new shower room partitioning per nfpa13. total relocate 2, add 3 sprinkler heads, ref to pa# 202211227035.Details
1/f: modify fire sprinkler system to accommodate new shower room partitioning per nfpa13. total relocate 2, add 3 sprinkler heads, ref to pa# 202211227035. | $3,000 |
| Nov 22, 2022 | Completed final sign-off Apr 2023 | 555 19th St | Modern Construction Inc | interior t.i. includes 2 new accessible shingle user shower rooms with one shower and one lavatory each on level one.Details
interior t.i. includes 2 new accessible shingle user shower rooms with one shower and one lavatory each on level one. | $28,000 |
| Apr 5, 2021 | Completed final sign-off Jul 2022 | 555 19th St | change f-1 industrial (cbc) occupancy and 16-manufacturing (sfpc) use to b-business office (cbc) occupancy and 10-office (sfpc) use. the basement remains s-1 storage. no physical change to the building. this permit is to document the return to the previously approved b-business office occupancyDetails
change f-1 industrial (cbc) occupancy and 16-manufacturing (sfpc) use to b-business office (cbc) occupancy and 10-office (sfpc) use. the basement remains s-1 storage. no physical change to the building. this permit is to document the return to the previously approved b-business office occupancy | ||
| Oct 8, 2019 | Expired or cancelled withdrawn Dec 2019 | 555 19th St | Arrow Sign Company | install electric wall sign single faced | $3,250 |
| Feb 15, 2019 | Completed final sign-off May 2019 | 555 19th St | Modern Construction Inc | revision to 201802070675. install sloped floor adjacent to break room to accomodate 2 inch drop in elevation due to actual field conditions and metal guard at the edge of sloped floor.Details
revision to 201802070675. install sloped floor adjacent to break room to accomodate 2 inch drop in elevation due to actual field conditions and metal guard at the edge of sloped floor. | |
| Dec 5, 2018 | Completed final sign-off May 2019 | 555 19th St | Modern Construction Inc | revision to pa 201802070675. eliminate several partitioned work spaces. change in egress path, eleminate kitchen counter and sliding glass door, add sloped floor (not a ramp) to coordinate floor height difference at 1st flr, floor slope @ 2% approx.Details
revision to pa 201802070675. eliminate several partitioned work spaces. change in egress path, eleminate kitchen counter and sliding glass door, add sloped floor (not a ramp) to coordinate floor height difference at 1st flr, floor slope @ 2% approx. | |
| Feb 7, 2018 | Completed final sign-off Jun 2019 | 555 19th St | Modern Construction Inc | minor remodel of existing industrial space to provide small enclosed workshop spaces w/ doors/partitions, a remodeled break area, and conversion of urinals to toilet in two bathrooms 1st, 2nd, 3rd floor. maher ord 155-13 naDetails
minor remodel of existing industrial space to provide small enclosed workshop spaces w/ doors/partitions, a remodeled break area, and conversion of urinals to toilet in two bathrooms 1st, 2nd, 3rd floor. maher ord 155-13 na | $35,000 |
| Mar 10, 2015 | Completed final sign-off May 2015 | 555 19th St | Devcon Construction | non-rated, non structural, aluminum framed, tempered, glass partitions and doors.Details
non-rated, non structural, aluminum framed, tempered, glass partitions and doors. | $31,465 |
| Sep 29, 2014 | Completed final sign-off Mar 2015 | 555 19th St | Universal Cell Site Services Inc | a (n) unmanned att telecommunication facility conssiting of installing (1) (n) roof mounted antenna, (1)(n) indoor antenna, (n) 4'x8' equipment backboard w/ (3) (n) repeaters, & (6) (n) runs of coaxDetails
a (n) unmanned att telecommunication facility conssiting of installing (1) (n) roof mounted antenna, (1)(n) indoor antenna, (n) 4'x8' equipment backboard w/ (3) (n) repeaters, & (6) (n) runs of coax | $30,000 |
| Jan 13, 2014 | Completed final sign-off Apr 2014 | 555 19th St | Principal Builders Inc. | 1st to 3rd floor mechanical work - modify existing duct work & existing heating & cooling installation of new transfer air fan. refer to pa #2013.12.16.4254. compliance with ordinance no. 155-13 not required. excavation < 50 cu.yd.Details
1st to 3rd floor mechanical work - modify existing duct work & existing heating & cooling installation of new transfer air fan. refer to pa #2013.12.16.4254. compliance with ordinance no. 155-13 not required. excavation < 50 cu.yd. | $28,950 |
| Dec 31, 2013 | Completed final sign-off Jan 2014 | 555 19th St | Ayoob & Peery Plumbing Co Inc | add & relocate fire sprinkler heads pendant improvement 2nd fl: (8 add), (3 relocate). 3rd fl: (4 add), (3 relocate) ref pa# 201302200511Details
add & relocate fire sprinkler heads pendant improvement 2nd fl: (8 add), (3 relocate). 3rd fl: (4 add), (3 relocate) ref pa# 201302200511 | $9,252 |
| Dec 16, 2013 | Completed final sign-off Apr 2014 | 555 19th St | Principal Builders Inc. | t.i. includes:new non-rated, non-structural partitions, work spaces, break areas, and voluntary multi accomodation toilet rooms. mep, sprinkler under separate permit.Details
t.i. includes:new non-rated, non-structural partitions, work spaces, break areas, and voluntary multi accomodation toilet rooms. mep, sprinkler under separate permit. | $241,945 |
| Dec 5, 2013 | Completed final sign-off Feb 2014 | 555 19th St | Simply Building Inc | revision to counter and cabinetry of break area of pa# 201302200511.Details
revision to counter and cabinetry of break area of pa# 201302200511. | |
| Feb 20, 2013 | Completed final sign-off Feb 2014 | 555 19th St | ti. new non rated, non structural partitions, new convenience wc, new break area in units 102, 202, 302. mep under separate permit.Details
ti. new non rated, non structural partitions, new convenience wc, new break area in units 102, 202, 302. mep under separate permit. | $52,500 | |
| Sep 25, 2012 | Completed final sign-off Nov 2012 | 555 19th St | to obtain final inspection for pa#201004281206 all work has been completedDetails
to obtain final inspection for pa#201004281206 all work has been completed | ||
| Jun 18, 2012 | Completed final sign-off Jul 2012 | 555 19th St | K K Electric & Alarm Company | modify permit issued under #2011-0523-6513 1. eliminated smoke & heat detector& heat detector unside elevator maching room. 2. relocate facp to 3rd street side.Details
modify permit issued under #2011-0523-6513 1. eliminated smoke & heat detector& heat detector unside elevator maching room. 2. relocate facp to 3rd street side. | |
| Jun 14, 2012 | Completed final sign-off Jun 2012 | 555 19th St | Westco Roofing Co. Inc. | reroofingDetails
reroofing | $60,000 |
| Mar 23, 2012 | Completed final sign-off Apr 2012 | 555 19th St | to renew permit application #2004-01-20-4340 for final completion.Details
to renew permit application #2004-01-20-4340 for final completion. | ||
| Jan 25, 2012 | Never finaled issued Jan 2012, no final | 555 19th St | street space permit | ||
| Nov 17, 2011 | Never finaled issued Nov 2011, no final | 555 19th St | street space | ||
| Aug 4, 2011 | Never finaled issued Aug 2011, no final | 555 19th St | street space permit | ||
| Jun 8, 2011 | Never finaled issued Jun 2011, no final | 555 19th St | street space permit | ||
| May 23, 2011 | Completed final sign-off Jul 2012 | 555 19th St | K K Electric & Alarm Company | installation of fire sprinkler monitoring and elevator recall systemDetails
installation of fire sprinkler monitoring and elevator recall system | $3,000 |
| May 23, 2001 | Completed final sign-off Jun 2001 | 2203 03rd St | Sun Roofing & Constr. Company, Inc. | reroofingDetails
reroofing | $26,884 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Modern Construction Inc (4), K K Electric & Alarm Company (2), Principal Builders Inc. (2), Arrow Sign Company, Ayoob & Peery Plumbing Co Inc, Bay Alarm Company, Devcon Construction, Project Contractor Inc, Simply Building Inc, Sun Roofing & Constr. Company, Inc., Universal Cell Site Services Inc, Westco Roofing Co. Inc.
- Architects
- Neil Kaye (3), Natoma Architects, Inc., Neil Kaye, Simon Kwan
- Engineers
- Antonio Jacksalem, Meng Hsiu Chen
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.