Permit GraphShortlistSan Francisco building permits since 2000

Permit 201302200511

555 19th St

ti. new non rated, non structural partitions, new convenience wc, new break area in units 102, 202, 302. mep under separate permit.

Outcome
Completed (city status: complete, Feb 19, 2014)
Filed
Feb 20, 2013
Permit issued
Feb 20, 2013
Final sign-off
Feb 19, 2014
Declared cost
$52,500
Building use
office
Neighborhood
Potrero Hill (how long permits take there)
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 4058, lot 009)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder
Authorized agent
David Myers (no license listed), applicant