Block 3732, lot 110
951 Howard St
- City’s use
- Commercial Office
- Built
- 1922
- Stories
- 2
- Rooms
- 3 bathrooms
- Building
- 13,050 sq ft
- Lot
- 9,748 sq ft
- Zoning
- RSD
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
37 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 8, 2025 | Completed final sign-off Sep 2025 | 951 Howard St | Metropolitan Electrical Construction | at&t - modification of an (e) unmanned wireless facility consisting: removing 6 rrus, relocate 3 rrus, install 3 new rrus, add 3 new air antennas, 3 back to back brackets, ground (1) 48v rectifier, (3) 50a air 6419 antenna dc breaker, (3) 50a 4890 rru dc breakers.Details
at&t - modification of an (e) unmanned wireless facility consisting: removing 6 rrus, relocate 3 rrus, install 3 new rrus, add 3 new air antennas, 3 back to back brackets, ground (1) 48v rectifier, (3) 50a air 6419 antenna dc breaker, (3) 50a 4890 rru dc breakers. | $35,000 |
| Nov 10, 2021 | Completed final sign-off May 2022 | 951 Howard St | Electric Tech Construction Inc | at&t modidy of (e) unmanned cell site. antenna location: remove & replace (3) antennas - painted to match. equipment: remove (16) 155 ah batteries & (4) 160ah batteries from (e) battery rack. install (1) n battery tray in (e) dcpp-(12) 190 ah batt & (8) 190ah-(1) 6648 in (e) rack; remove 2 (e) tma'Details
at&t modidy of (e) unmanned cell site. antenna location: remove & replace (3) antennas - painted to match. equipment: remove (16) 155 ah batteries & (4) 160ah batteries from (e) battery rack. install (1) n battery tray in (e) dcpp-(12) 190 ah batt & (8) 190ah-(1) 6648 in (e) rack; remove 2 (e) tma' | $80,000 |
| Oct 6, 2020 | Completed final sign-off Jan 2021 | 951 Howard St | Ericsson Inc Dba E U S Inc | remove/replace (3) panel antennas on tower. remove/replace (3) rru units on tower. add (3) dc-9 units on tower. install new power/fiber trunkDetails
remove/replace (3) panel antennas on tower. remove/replace (3) rru units on tower. add (3) dc-9 units on tower. install new power/fiber trunk | $36,525 |
| Oct 2, 2018 | Completed final sign-off Jun 2019 | 951 Howard St | Electric Tech Construction Inc | cell tower, att modification. remove and replace 6 antennas w/ 6 (n) antennas, install 6 (n) rru's, install other small equipment, no change to (e) batteriesDetails
cell tower, att modification. remove and replace 6 antennas w/ 6 (n) antennas, install 6 (n) rru's, install other small equipment, no change to (e) batteries | $33,000 |
| Oct 10, 2017 | Never finaled issued May 2018, no final | 951 Howard St | Shah & Associates Inc Dba P D C Corporat | swap 3 (e) antennas for 3 new antennas. swap 3 (e) radios for 3 new radio models. install xmu unit inside (e) rack & install 1 idl2 cable. ** maher: n/a **Details
swap 3 (e) antennas for 3 new antennas. swap 3 (e) radios for 3 new radio models. install xmu unit inside (e) rack & install 1 idl2 cable. ** maher: n/a ** | $15,000 |
| May 23, 2017 | Completed final sign-off Nov 2017 | 951 Howard St | Dryco Construction Inc - Dba - Dryco | provide and install an 8'-0" high steel security fence and gate. maher na.Details
provide and install an 8'-0" high steel security fence and gate. maher na. | $25,000 |
| Aug 31, 2015 | Completed final sign-off Feb 2016 | 951 Howard St | Triton Tower Inc | at&t: modification to (e) facility consisting of installing (n) dc-12 surge suppressor inside (e) rack; r&r (e) dul w/2(n) dus41 inside (e) rack; r&r 3(e) rrus w-01 w/3(n) rrus-32; r&r 3 (e) antennas w/3(n) antennas; remove (e) dcg surge suppressor inside (e) rack. maher naDetails
at&t: modification to (e) facility consisting of installing (n) dc-12 surge suppressor inside (e) rack; r&r (e) dul w/2(n) dus41 inside (e) rack; r&r 3(e) rrus w-01 w/3(n) rrus-32; r&r 3 (e) antennas w/3(n) antennas; remove (e) dcg surge suppressor inside (e) rack. maher na | $15,000 |
| Oct 9, 2013 | Completed final sign-off Jan 2014 | 951 Howard St | Triton Tower Inc | a modification to an extg at&t unmanned telecommunication facility consisting of adding 3 new rrus- 11's, one new surge suppressor and one new innerduct for fiber and dc power. no change to antennas. no other scope of work.Details
a modification to an extg at&t unmanned telecommunication facility consisting of adding 3 new rrus- 11's, one new surge suppressor and one new innerduct for fiber and dc power. no change to antennas. no other scope of work. | $6,000 |
| Feb 14, 2013 | Expired or cancelled cancelled Mar 2020 | 951 Howard St | a modification to an (e) unmanned telecommunication facility consisting of removing & replacing (3) (e) at&t antennas w/ (3) (n) at&t antennas.Details
a modification to an (e) unmanned telecommunication facility consisting of removing & replacing (3) (e) at&t antennas w/ (3) (n) at&t antennas. | $10,000 | |
| Feb 14, 2011 | Completed final sign-off Apr 2011 | 951 Howard St | Intelligent Technologies & Services Inc | demo ir detection from existing generator enclosure and reinstall in new enclosure. new enclosure under 201010213489Details
demo ir detection from existing generator enclosure and reinstall in new enclosure. new enclosure under 201010213489 | $3,200 |
| Dec 9, 2010 | Completed final sign-off Jul 2011 | 951 Howard St | Cba Site Services Inc. | remove and replace 3 antennas, install 6 rrus. install 19" rack w/a n 6601 equip cabinet, n surge suppressor, 1 new 3" conduit. install new gps antennaDetails
remove and replace 3 antennas, install 6 rrus. install 19" rack w/a n 6601 equip cabinet, n surge suppressor, 1 new 3" conduit. install new gps antenna | $35,000 |
| Nov 23, 2010 | Never finaled issued Nov 2010, no final | 951 Howard St | street space permitDetails
street space permit | ||
| Oct 21, 2010 | Completed final sign-off Apr 2011 | 951 Howard St | Roebbelen Contracting Inc | replace (e) 350 kw generator w/ new 500 kw gen'r. remove gen'r & enclosure. install new gen'r, stand alone, package. provide new elect'l, monitoring, alarms, controls, fuel piping. at ext'r of bldg & provide assoc'd fueling plns for perm't & temp gen'r. (connect'n to fire alarm on separate permit)Details
replace (e) 350 kw generator w/ new 500 kw gen'r. remove gen'r & enclosure. install new gen'r, stand alone, package. provide new elect'l, monitoring, alarms, controls, fuel piping. at ext'r of bldg & provide assoc'd fueling plns for perm't & temp gen'r. (connect'n to fire alarm on separate permit) | $600,000 |
| Sep 21, 2010 | Never finaled issued Sep 2010, no final | 951 Howard St | sidewalk permitDetails
sidewalk permit | ||
| May 3, 2010 | Never finaled issued May 2010, no final | 951 Howard St | street space and mta parkingDetails
street space and mta parking | ||
| Mar 31, 2010 | Completed final sign-off Apr 2011 | 951 Howard St | Roebbelen Contracting Inc | replace existing 600a service with new 800a service, including switchgear, automatic transfer switches, generator tap box, and main house service panel. this project will include a housekeeping pad for the equipment and bollards for protection.Details
replace existing 600a service with new 800a service, including switchgear, automatic transfer switches, generator tap box, and main house service panel. this project will include a housekeeping pad for the equipment and bollards for protection. | $497,097 |
| Mar 15, 2010 | Expired or cancelled withdrawn Dec 2010 | 951 Howard St | Broken Arrow Communications Inc | at&t. a modification to an (e) unmanned telecomunication facility conssisting of removing and replacing one antenna, and adding six new runs of coax, three new dtma's (dual tower mounted amplifiers) and new ret's ( remote electronic filter)Details
at&t. a modification to an (e) unmanned telecomunication facility conssisting of removing and replacing one antenna, and adding six new runs of coax, three new dtma's (dual tower mounted amplifiers) and new ret's ( remote electronic filter) | $25,000 |
| Nov 25, 2009 | Completed final sign-off May 2010 | 951 Howard St | Roebbelen Contracting Inc | revision to appl #2009.1125.2116. add sound barriers on roof screen & sound attenuation on (4) condensers. to address correction notice per d. sullivan & to address complaint #200926047 (bid).Details
revision to appl #2009.1125.2116. add sound barriers on roof screen & sound attenuation on (4) condensers. to address correction notice per d. sullivan & to address complaint #200926047 (bid). | $20,000 |
| Sep 22, 2009 | Completed final sign-off Nov 2009 | 951 Howard St | Potter Fire Protection | plug 8 and relocate 2 fire sprinklers to accomodate the new ceiling construction in an existing office area.Details
plug 8 and relocate 2 fire sprinklers to accomodate the new ceiling construction in an existing office area. | $780 |
| Sep 10, 2009 | Completed final sign-off Jan 2010 | 951 Howard St | Intelligent Technologies & Services Inc | relocate existing fm200 tank & relocate 1 detector & update graphic panel & replace 1 existing fm200 tank with bigger tank for ceiling removal in battery room. no office increaseDetails
relocate existing fm200 tank & relocate 1 detector & update graphic panel & replace 1 existing fm200 tank with bigger tank for ceiling removal in battery room. no office increase | $9,500 |
| Aug 10, 2009 | Never finaled issued Aug 2009, no final | 951 Howard St | street space & mta permit.Details
street space & mta permit. | ||
| Jun 3, 2009 | Completed final sign-off May 2010 | 951 Howard St | Roebbelen Contracting Inc | replace with identical units hvac rtu for telecommunications equipment processes. remove ceiling in power room & leave open.Details
replace with identical units hvac rtu for telecommunications equipment processes. remove ceiling in power room & leave open. | $600,000 |
| May 14, 2009 | Completed final sign-off Jun 2010 | 951 Howard St | Roebbelen Contracting Inc | reroofing and roof strengthening. ada upgrades.Details
reroofing and roof strengthening. ada upgrades. | $300,000 |
| Apr 21, 2009 | Completed final sign-off Sep 2009 | 951 Howard St | Cba Site Services Inc. | modifcation to an (e) telecom facility consisting of removing all tdma equipment, add new rets (remote electronic tilts) to (e) antennas. ret powered by low voltage signaled trough (e) coax cableDetails
modifcation to an (e) telecom facility consisting of removing all tdma equipment, add new rets (remote electronic tilts) to (e) antennas. ret powered by low voltage signaled trough (e) coax cable | $5,200 |
| Jan 7, 2009 | Completed final sign-off Feb 2009 | 951 Howard St | Intelligent Technologies & Services Inc | install detector and relay modules in new hvac room.Details
install detector and relay modules in new hvac room. | $5,500 |
| Oct 14, 2008 | Completed final sign-off Feb 2009 | 951 Howard St | Bangar Construction Corp. | addition of three cooling units in new unoccupied mechanical room.Details
addition of three cooling units in new unoccupied mechanical room. | $350,000 |
| Apr 4, 2008 | Completed final sign-off Feb 2009 | 951 Howard St | Intelligent Technologies & Services Inc | install ir detector in generator room that shall be tied into existing system.Details
install ir detector in generator room that shall be tied into existing system. | $4,500 |
| Sep 7, 2005 | Expired or cancelled cancelled Sep 2007 | 951 Howard St | electrical service & standby, emergency generator upgrade.add additional emergency light fixtures.(e.g. swapout exist fluorescewnt lighting with new self contained emergerncy light fixtures).Details
electrical service & standby, emergency generator upgrade.add additional emergency light fixtures.(e.g. swapout exist fluorescewnt lighting with new self contained emergerncy light fixtures). | $500,000 | |
| May 20, 2005 | Completed final sign-off Jun 2005 | 951 Howard St | The Lawson Roofing Co Inc. | reroofingDetails
reroofing | $88,309 |
| May 5, 2005 | Never finaled issued Jul 2005, no final | 951 Howard St | Intelligent Technologies & Services Inc | install new fire alarm, fire suppression, pre-action and air sampling systemDetails
install new fire alarm, fire suppression, pre-action and air sampling system | $50,000 |
| May 4, 2005 | Never finaled issued Dec 2005, no final | 951 Howard St | Bcci Construction Company | new interior partitions,ceiling work,mech.,elec.,structural and finishes.replace & add new rooftopDetails
new interior partitions,ceiling work,mech.,elec.,structural and finishes.replace & add new rooftop | $150,000 |
| Mar 5, 2002 | Expired or cancelled expired Jul 2002 | 951 Howard St | Transbay Fire Protection | revision: (as builts) to200203050647Details
revision: (as builts) to200203050647 | |
| Jan 22, 2002 | Expired or cancelled expired May 2002 | 951 Howard St | American Incorporated | ap#200103023373 - modify #of dwg fr 1 to 0/reduce scope of wrk can struct & arch activity modify plnDetails
ap#200103023373 - modify #of dwg fr 1 to 0/reduce scope of wrk can struct & arch activity modify pln | |
| Dec 14, 2001 | Expired or cancelled cancelled Mar 2003 | 951 Howard St | Transbay Fire Protection | modify existing preaction system per tenant improvements revisions to p.a#200107032876Details
modify existing preaction system per tenant improvements revisions to p.a#200107032876 | |
| Aug 1, 2001 | Expired or cancelled expired Feb 2002 | 951 Howard St | Sabah International Incorporated | furnish and install horns/strobes and power panelDetails
furnish and install horns/strobes and power panel | $15,400 |
| Jul 3, 2001 | Expired or cancelled expired Jul 2002 | 951 Howard St | Transbay Fire Protection | modify exist preaction system per tneant improvemnets.Details
modify exist preaction system per tneant improvemnets. | $27,025 |
| Mar 2, 2001 | Expired or cancelled expired Jul 2002 | 951 Howard St | American Incorporated | structural modification for independent truss system to support telco cable rackingDetails
structural modification for independent truss system to support telco cable racking | $160,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Intelligent Technologies & Services Inc (5), Roebbelen Contracting Inc (5), Transbay Fire Protection (3), American Incorporated (2), Cba Site Services Inc. (2), Electric Tech Construction Inc (2), Triton Tower Inc (2), Bangar Construction Corp., Bcci Construction Company, Broken Arrow Communications Inc, Dryco Construction Inc - Dba - Dryco, Ericsson Inc Dba E U S Inc, Metropolitan Electrical Construction, Potter Fire Protection, Sabah International Incorporated, Shah & Associates Inc Dba P D C Corporat, The Lawson Roofing Co Inc.
- Architects
- Brett Mccomb, Joseph Gonzalez, Mark Thieme, Nestor Popowych
- Engineers
- John Chinn (2), Daniel Connel, Eric Kumar, James A. Underwood, Kevin Sorensen, Seung Kun Oh, Stephen Bunting
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.