Block 0326, lot 011
222 Mason St
- City’s use
- Commercial Hotel
- Built
- 1988
- Stories
- 31
- Units
- 529
- Rooms
- 529 bedrooms, 541 bathrooms
- Building
- 574,080 sq ft
- Lot
- 18,906 sq ft
- Zoning
- C3G
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
76 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 14, 2025 | In progress issued Jul 2026 | 222 Mason St | Everon Llc | replace existing fire alarm system with new, replace initiating devices at existing location with new, replace notification appliances at existing locaiton with new.interface with existing smoke control function via bms system.Details
replace existing fire alarm system with new, replace initiating devices at existing location with new, replace notification appliances at existing locaiton with new.interface with existing smoke control function via bms system. | $1,600,000 |
| Sep 12, 2024 | Completed final sign-off Apr 2025 | 222 Mason St | Hp Build | temporary equipment access panel for elevator refurbishment.Details
temporary equipment access panel for elevator refurbishment. | $36,000 |
| May 31, 2024 | Completed final sign-off Jun 2024 | 222 Mason St | Pribuss Engineering Inc | remove (e) fire sprinklers form all elevator hoistways and elevator machine rooms for the modernization of (6) passenger and 5 service elevators.Details
remove (e) fire sprinklers form all elevator hoistways and elevator machine rooms for the modernization of (6) passenger and 5 service elevators. | $7,500 |
| Apr 7, 2023 | Completed final sign-off Jun 2023 | 222 Mason St | Hp Build | partial reconfiguration of an existing tenant office space @ level 5. includes selective demo & and installation of walls, ceiling and doorsDetails
partial reconfiguration of an existing tenant office space @ level 5. includes selective demo & and installation of walls, ceiling and doors | $5,000 |
| Mar 9, 2023 | Completed final sign-off Mar 2023 | 222 Mason St | Johnson Controls Inc. | fire only: sound meter test with city inspector. administrative permit to verify (e) sound levels in sleeping areas, complying with sffc section 1103.7.6.1Details
fire only: sound meter test with city inspector. administrative permit to verify (e) sound levels in sleeping areas, complying with sffc section 1103.7.6.1 | |
| Mar 3, 2021 | Expired or cancelled withdrawn Apr 2021 | 222 Mason St | Satoh Brothers International Inc | revision to pa 202007069618. updating structural attachments for slope ladder and cat walk assemblies at upper story and pool roof. not visible from the street.Details
revision to pa 202007069618. updating structural attachments for slope ladder and cat walk assemblies at upper story and pool roof. not visible from the street. | |
| Feb 10, 2021 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | revision to pa 202007069618. roof hatches were replaced with sloped ladders. vertical ladders were replaced with sloped ladders. work not visible from street.Details
revision to pa 202007069618. roof hatches were replaced with sloped ladders. vertical ladders were replaced with sloped ladders. work not visible from street. | |
| Nov 25, 2020 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | revision to pa #2020-0919-4505 & 2020-0302-5832: replace 9 concrete landings w/ 9 prefabricated landings. replace double plate guardrails with single plate guardrails at 25 & 27 floors. update details for plate detachment and stepped ladder attachments at roof.Details
revision to pa #2020-0919-4505 & 2020-0302-5832: replace 9 concrete landings w/ 9 prefabricated landings. replace double plate guardrails with single plate guardrails at 25 & 27 floors. update details for plate detachment and stepped ladder attachments at roof. | |
| Nov 17, 2020 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | revision to pa# 202009194505. reinforcing structural steel framing for exterior facade access. incorporating pre-fab steps to stepped ladders at high level roofs in lieu of concrete steps. minor guardrail changes at p1 level.Details
revision to pa# 202009194505. reinforcing structural steel framing for exterior facade access. incorporating pre-fab steps to stepped ladders at high level roofs in lieu of concrete steps. minor guardrail changes at p1 level. | |
| Sep 19, 2020 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | revision to pa 202003025832. reinforcing existing structural steel framing for installation of exterior building facade access.Details
revision to pa 202003025832. reinforcing existing structural steel framing for installation of exterior building facade access. | |
| Sep 3, 2020 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | reinforce (e) structural steel framing at locations for installation of exterior bldg facade access improvements associated w/ 5th, 20th, 21st-26th floors, including penthouse & roof levels. install exterior bldg facade access improvements. repair/replace finishes adjacent. ref pa #202003025832.Details
reinforce (e) structural steel framing at locations for installation of exterior bldg facade access improvements associated w/ 5th, 20th, 21st-26th floors, including penthouse & roof levels. install exterior bldg facade access improvements. repair/replace finishes adjacent. ref pa #202003025832. | $327,580 |
| Jul 6, 2020 | Completed final sign-off Aug 2021 | 222 Mason St | Satoh Brothers International Inc | hotel nikko is a 26-story hotel that includes scope of work: a new exterior building maintenance system and equipment to meet current osha regulations. maher naDetails
hotel nikko is a 26-story hotel that includes scope of work: a new exterior building maintenance system and equipment to meet current osha regulations. maher na | $85,000 |
| Mar 2, 2020 | Completed final sign-off Sep 2021 | 222 Mason St | Bana Construction Inc | reinforce (e) structure steel framing at locations for the installation of exterior building facade floors 5,20,21,22,23,24,25,26 and penthouse-pedestals, safety anchor, guard rail, landers and catwalk, roof access hatchesDetails
reinforce (e) structure steel framing at locations for the installation of exterior building facade floors 5,20,21,22,23,24,25,26 and penthouse-pedestals, safety anchor, guard rail, landers and catwalk, roof access hatches | $327,580 |
| Dec 11, 2019 | Completed final sign-off Apr 2021 | 222 Mason St | new electrical outlets for parking power door. exterior and interior on ground floor. interior at 5th floorDetails
new electrical outlets for parking power door. exterior and interior on ground floor. interior at 5th floor | $15,000 | |
| Dec 11, 2019 | Never finaled filed Dec 2019, never issued | 222 Mason St | window replacement (in-kind). 3 qty @ 20th floor. 3 qty @ 21st floor.Details
window replacement (in-kind). 3 qty @ 20th floor. 3 qty @ 21st floor. | ||
| Dec 11, 2019 | Completed final sign-off Jun 2021 | 222 Mason St | replace 6 window, 3 doors.Details
replace 6 window, 3 doors. | $124,780 | |
| Nov 6, 2019 | Never finaled issued Nov 2019, no final | 222 Mason St | street spaceDetails
street space | ||
| Aug 5, 2019 | Expired or cancelled cancelled Jan 2026 | 222 Mason St | provide and install new nitrogen infused coffee dispenserDetails
provide and install new nitrogen infused coffee dispenser | $8,500 | |
| Oct 4, 2018 | Never finaled issued Nov 2018, no final | 222 Mason St | Goike Construction Management | 5th flr. hotel office remodel and will incl selective demo and installation of doors, walls, ceilings, lights fixtures. no exterior work or change of occupancy. fire life safety and mep under separate permitDetails
5th flr. hotel office remodel and will incl selective demo and installation of doors, walls, ceilings, lights fixtures. no exterior work or change of occupancy. fire life safety and mep under separate permit | $4,000 |
| Sep 11, 2017 | Completed final sign-off May 2025 | 222 Mason St | Ayoob & Peery Plumbing Co Inc | 23/f- fire sprinklers t.i., add (3) and relocate (6) sprinklers to conform with new wall/ceiling layout. t.i. pa#2016-12-28-6035. n/a ordinance #155-13Details
23/f- fire sprinklers t.i., add (3) and relocate (6) sprinklers to conform with new wall/ceiling layout. t.i. pa#2016-12-28-6035. n/a ordinance #155-13 | $4,725 |
| Jun 12, 2017 | Never finaled issued Jun 2017, no final | 222 Mason St | street space permit and mta permit - 201609168047Details
street space permit and mta permit - 201609168047 | ||
| Feb 3, 2017 | Completed final sign-off Apr 2017 | 222 Mason St | Goike Construction Management | the scope of work is to rebuild the accesible curb cut from the porte cochere to the hotel lobby. create a passenger loading area and install new ada signage. no change in occupancy, use or egress. fire safety under separate permit. n/a maherDetails
the scope of work is to rebuild the accesible curb cut from the porte cochere to the hotel lobby. create a passenger loading area and install new ada signage. no change in occupancy, use or egress. fire safety under separate permit. n/a maher | $22,000 |
| Feb 3, 2017 | Completed final sign-off May 2017 | 222 Mason St | Cahill Contractors Inc | 2nd & 3rd floor - revision to pa #201610281401: reduce quantity of lighting fixture & receptacle.Details
2nd & 3rd floor - revision to pa #201610281401: reduce quantity of lighting fixture & receptacle. | |
| Jan 18, 2017 | Completed final sign-off Mar 2017 | 222 Mason St | Johnson Controls Inc. | 21/f & 24/f- install new strobes, smoke detectors with low frequency sounder bases and replace (e) speakers in the remodeled ada rooms, new remote power supply, add control module & sync module to each guest room on 21/f, 24/f will have seperate power circuits from the power supply for each unit.Details
21/f & 24/f- install new strobes, smoke detectors with low frequency sounder bases and replace (e) speakers in the remodeled ada rooms, new remote power supply, add control module & sync module to each guest room on 21/f, 24/f will have seperate power circuits from the power supply for each unit. | $24,000 |
| Dec 28, 2016 | Completed final sign-off Jan 2018 | 222 Mason St | Cahill Contractors Llc. | selective demo & refinishing of walls, floors anbd ceiling & the removal of replacement of plumbning fixtures, light fixtures, outlets & casework in 3 suites. no change in occupancy, occipany loads or egress. noe ext work. fire/life safety under sep permit maher naDetails
selective demo & refinishing of walls, floors anbd ceiling & the removal of replacement of plumbning fixtures, light fixtures, outlets & casework in 3 suites. no change in occupancy, occipany loads or egress. noe ext work. fire/life safety under sep permit maher na | $138,000 |
| Nov 4, 2016 | Expired or cancelled expired Aug 2021 | 222 Mason St | Cahill Contractors Llc. | scope of work includes remodel of e guestroom on the 7th fl and specifically the selective demo and refinishing of walls, floors, ceilings and removal and replacement of plumbing fixtures. lighting fixtures, outlets, and casework. no extr work or change in occup. (life safety deferred if reqd)Details
scope of work includes remodel of e guestroom on the 7th fl and specifically the selective demo and refinishing of walls, floors, ceilings and removal and replacement of plumbing fixtures. lighting fixtures, outlets, and casework. no extr work or change in occup. (life safety deferred if reqd) | $37,000 |
| Oct 20, 2016 | Expired or cancelled expired Aug 2021 | 222 Mason St | Sunbelt Controls Inc | level b1-5/f, phase 2- hvac controls upgrade. n/a ordinance #155-13Details
level b1-5/f, phase 2- hvac controls upgrade. n/a ordinance #155-13 | $750,000 |
| Sep 16, 2016 | Completed final sign-off Jan 2018 | 222 Mason St | Takenaka Corporation U S A | this scope is phase 3 of voluntary seismic retrofit & consist of strengthening of (e) column splices along the tower perimeter & the demolition. construction of walls in these area. no change in occupancy, occ load, or egress. no exterior work. fire life safety under separate permit.Details
this scope is phase 3 of voluntary seismic retrofit & consist of strengthening of (e) column splices along the tower perimeter & the demolition. construction of walls in these area. no change in occupancy, occ load, or egress. no exterior work. fire life safety under separate permit. | $350,000 |
| Jul 6, 2016 | Completed final sign-off Nov 2017 | 222 Mason St | Takenaka Corporation U S A | this scope is phase 2 of a voluntary structural strengthening & consists of the addition of grider catch seats under level 2 & 5 structural slabs & related demo & construction of walls, floor & ceiling on level 1 & 4 around new seismic members.no change in occupancy,occ load & egressDetails
this scope is phase 2 of a voluntary structural strengthening & consists of the addition of grider catch seats under level 2 & 5 structural slabs & related demo & construction of walls, floor & ceiling on level 1 & 4 around new seismic members.no change in occupancy,occ load & egress | $220,000 |
| Jun 13, 2016 | Completed final sign-off May 2017 | 222 Mason St | various fl:selective demo and refinishing of walls, floors, ceilings, remove and replace plumbing fixtures, lighting, outlets, casework. no change in occupancy, occ load , or egress. no exterior work, fire life safety under sep permit maher not req.Details
various fl:selective demo and refinishing of walls, floors, ceilings, remove and replace plumbing fixtures, lighting, outlets, casework. no change in occupancy, occ load , or egress. no exterior work, fire life safety under sep permit maher not req. | $720,000 | |
| Jun 9, 2016 | Completed final sign-off Mar 2017 | 222 Mason St | installation of ada accessible inclined lift at entry and new sidewalk extension to entrance. electrcal under seperate permit.Details
installation of ada accessible inclined lift at entry and new sidewalk extension to entrance. electrcal under seperate permit. | $80,000 | |
| May 13, 2016 | Completed final sign-off May 2017 | 222 Mason St | floors 6-22: barrier removal only- scope of work consists of upgrading 16 (e) accessible guestrooms to current code compliance and converting two guestrooms into an accessible suite on floor 21.Details
floors 6-22: barrier removal only- scope of work consists of upgrading 16 (e) accessible guestrooms to current code compliance and converting two guestrooms into an accessible suite on floor 21. | $165,000 | |
| Jan 20, 2016 | Completed final sign-off Nov 2016 | 222 Mason St | Johnson Controls Inc. | one new control relay to be provided to override the new door lock on double doors @ pool area,the (e)node 4,loop 1 circuit to be extended,relay adjacent to the dble doors.for new weatherproof speakers/strobes,connected (e)circuits 5avb&5bvb,5 (e)speakers to replace & 2(e)reconnected; maher n/aDetails
one new control relay to be provided to override the new door lock on double doors @ pool area,the (e)node 4,loop 1 circuit to be extended,relay adjacent to the dble doors.for new weatherproof speakers/strobes,connected (e)circuits 5avb&5bvb,5 (e)speakers to replace & 2(e)reconnected; maher n/a | $12,000 |
| Dec 18, 2015 | Completed final sign-off Jan 2016 | 222 Mason St | Johnson Controls Inc. | a new monitor module to be provided to monitor new kitchen hood system for alarm condition. the (e) node 4, loop 1 circuit to be extended to the new monitor module. replace (e) smoke detectorwith new addressable heat detector and reuse (e) device addresses. maher naDetails
a new monitor module to be provided to monitor new kitchen hood system for alarm condition. the (e) node 4, loop 1 circuit to be extended to the new monitor module. replace (e) smoke detectorwith new addressable heat detector and reuse (e) device addresses. maher na | $13,664 |
| Dec 9, 2015 | Completed final sign-off Jan 2016 | 222 Mason St | Golden Gate Fire Protection Inc | fire sprinklers: change out 30 pendent sprinklers on the 5th floor pool area. ref pa 2015-1001-8549. maher naDetails
fire sprinklers: change out 30 pendent sprinklers on the 5th floor pool area. ref pa 2015-1001-8549. maher na | $15,450 |
| Oct 8, 2015 | Completed final sign-off Nov 2015 | 222 Mason St | Johnson Controls Inc. | 5th floor: i.i. suppression monitoring. monitoring alarm action in 5th floor computer room. through bldg fire panel. n/a ordinance #155-13Details
5th floor: i.i. suppression monitoring. monitoring alarm action in 5th floor computer room. through bldg fire panel. n/a ordinance #155-13 | $6,500 |
| Oct 3, 2014 | Never finaled issued Oct 2014, no final | 222 Mason St | Goike Construction Management | revision to 201311071358 - remove accessible guest room types cqs and pk addition of accessible guest room type nd and revision to number and locations of existing accessible guest room type q with roll-in shower upgrade. n/a maher ordinanceDetails
revision to 201311071358 - remove accessible guest room types cqs and pk addition of accessible guest room type nd and revision to number and locations of existing accessible guest room type q with roll-in shower upgrade. n/a maher ordinance | |
| Jul 11, 2014 | Expired or cancelled expired Aug 2021 | 222 Mason St | Goike Construction Management | 25th fl. control upgrades to 4 air handlers. replace 25 vav terminals with new controlsDetails
25th fl. control upgrades to 4 air handlers. replace 25 vav terminals with new controls | $75,000 |
| Jul 11, 2014 | Expired or cancelled expired Aug 2021 | 222 Mason St | Goike Construction Management | gas meter room upgrade. gas monitor and new exhaust fan. maher not reqDetails
gas meter room upgrade. gas monitor and new exhaust fan. maher not req | $6,000 |
| Apr 8, 2014 | Completed final sign-off Jun 2016 | 222 Mason St | Cosco Fire Protection Inc. | 5th floor server room - novec 1230 & smoke detection system. compliance with ordinance #155-13 not required.Details
5th floor server room - novec 1230 & smoke detection system. compliance with ordinance #155-13 not required. | $29,500 |
| Jun 11, 2013 | Completed final sign-off Jun 2013 | 222 Mason St | Golden Gate Fire Protection Inc | relocate 8 pendent sprinklers on the 5th fl office areaDetails
relocate 8 pendent sprinklers on the 5th fl office area | $4,120 |
| May 14, 2013 | Completed final sign-off Aug 2013 | 222 Mason St | Goike Construction Management | 6th floor:voluntary conversion of 1 accessible guest room to 1 accessible guest room with a roll in shower, and to make other modifications necessary to enhandle accessibility.Details
6th floor:voluntary conversion of 1 accessible guest room to 1 accessible guest room with a roll in shower, and to make other modifications necessary to enhandle accessibility. | $3,000 |
| May 14, 2013 | Completed final sign-off Jan 2014 | 222 Mason St | Goike Construction Management | 5th floor:partial demolition and refurbishment of extg back of house office on the 5th floor of the hotel nikko.Details
5th floor:partial demolition and refurbishment of extg back of house office on the 5th floor of the hotel nikko. | $49,000 |
| Oct 28, 2011 | Completed final sign-off Nov 2011 | 222 Mason St | T C B Builders Inc | revision to app#201011225460. replace stair risors and windows.Details
revision to app#201011225460. replace stair risors and windows. | $2,000 |
| Sep 13, 2011 | Completed final sign-off Sep 2011 | 222 Mason St | R L H Fire Protection Inc | fire sprinkler permit. relocate 3 pendent sprinklersDetails
fire sprinkler permit. relocate 3 pendent sprinklers | $1,500 |
| May 9, 2011 | Completed final sign-off Jul 2011 | 222 Mason St | occupancy load verification . sffd assembly permit required.Details
occupancy load verification . sffd assembly permit required. | ||
| Apr 11, 2011 | Completed final sign-off Oct 2011 | 222 Mason St | Johnson Controls Inc. | renew for final: 200802195024/ a;; work completeDetails
renew for final: 200802195024/ a;; work complete | |
| Nov 22, 2010 | Completed final sign-off Nov 2011 | 222 Mason St | T C B Builders Inc | renovation of (e) starbucks, incl. repalcaing finishes, cabinetry, lighting and equipment. no exterior or struc modifications. all existing and new drywall partiotion are non bearingDetails
renovation of (e) starbucks, incl. repalcaing finishes, cabinetry, lighting and equipment. no exterior or struc modifications. all existing and new drywall partiotion are non bearing | $100,000 |
| Sep 10, 2010 | Expired or cancelled expired Aug 2021 | 222 Mason St | temporary tent for oracle world event. 9/17/10 to 9/24/10Details
temporary tent for oracle world event. 9/17/10 to 9/24/10 | $10,600 | |
| Apr 26, 2010 | Completed final sign-off Nov 2010 | 222 Mason St | occupant load calculation onlyDetails
occupant load calculation only | ||
| Nov 10, 2009 | Completed final sign-off Nov 2009 | 222 Mason St | to obtain final inspection for work approved under pa 200802255526; all work has been completedDetails
to obtain final inspection for work approved under pa 200802255526; all work has been completed | ||
| Nov 10, 2009 | Completed final sign-off Nov 2009 | 222 Mason St | to obtain final inspection for work approved under pa 200712211070 ; all work has been completedDetails
to obtain final inspection for work approved under pa 200712211070 ; all work has been completed | ||
| Feb 27, 2009 | Completed final sign-off Apr 2009 | 222 Mason St | Hathaway Dinwiddie Co. | revision to pa #200811207057, to eliminate structural beams no required at removed hot tub locations.Details
revision to pa #200811207057, to eliminate structural beams no required at removed hot tub locations. | |
| Feb 18, 2009 | Completed final sign-off Apr 2009 | 222 Mason St | installation of fire smoke dampers at 5th level spa. amendment to app #200811207057Details
installation of fire smoke dampers at 5th level spa. amendment to app #200811207057 | $20,000 | |
| Jan 21, 2009 | Completed final sign-off Apr 2009 | 222 Mason St | R L H Fire Protection Inc | 5th floor-datam s.f.llc-t.i. upgrade of (e) fire sprinkler system. relocate 27 sprinkler heads and add 6 sprinkler headsDetails
5th floor-datam s.f.llc-t.i. upgrade of (e) fire sprinkler system. relocate 27 sprinkler heads and add 6 sprinkler heads | $7,400 |
| Nov 20, 2008 | Completed final sign-off Apr 2009 | 222 Mason St | remodel of men's and women's locker rooms including costemic works at reception areaDetails
remodel of men's and women's locker rooms including costemic works at reception area | $375,000 | |
| Feb 25, 2008 | Expired or cancelled expired Nov 2009 | 222 Mason St | revision to application # 200710226120, cosmetic work for 17 junior suites, replacing tiles, shower, glass doors, counter tops.Details
revision to application # 200710226120, cosmetic work for 17 junior suites, replacing tiles, shower, glass doors, counter tops. | $137,000 | |
| Feb 21, 2008 | Completed final sign-off Mar 2008 | 222 Mason St | Johnson Controls Inc. | add 1 smoke detector, add 3 wall strobe lights, 2 ceiling strobe units, add 1 booster, panel fcps24f58, add 1 speaker only, add 1 speaker strobeDetails
add 1 smoke detector, add 3 wall strobe lights, 2 ceiling strobe units, add 1 booster, panel fcps24f58, add 1 speaker only, add 1 speaker strobe | $10,000 |
| Feb 19, 2008 | Completed final sign-off Oct 2011 | 222 Mason St | Johnson Controls Inc. | full fire life saftey system upgrade for entire building ( hotel nikko). includes ifc 3030, graphic annuciation, change out of field devices, pull station, smoke detector and others.Details
full fire life saftey system upgrade for entire building ( hotel nikko). includes ifc 3030, graphic annuciation, change out of field devices, pull station, smoke detector and others. | $700,000 |
| Dec 21, 2007 | Expired or cancelled expired Nov 2009 | 222 Mason St | revision to appl #200710226120 - ada bathrooms alternate grab bars replacement.Details
revision to appl #200710226120 - ada bathrooms alternate grab bars replacement. | $1,500 | |
| Dec 4, 2007 | Completed final sign-off Mar 2008 | 222 Mason St | interior non-structural demo on 2nd floor lounge/banquet room area in advance of t.i. no exterior work. no construction work in compliance with ab107Details
interior non-structural demo on 2nd floor lounge/banquet room area in advance of t.i. no exterior work. no construction work in compliance with ab107 | $20,000 | |
| Oct 22, 2007 | Completed final sign-off Nov 2009 | 222 Mason St | Rago Construction | cosmetic renovation of guest rooms on floors 6-24. replacing vanaity sink, wall sconces, title, title, counter top, shower enclosers, etc.Details
cosmetic renovation of guest rooms on floors 6-24. replacing vanaity sink, wall sconces, title, title, counter top, shower enclosers, etc. | $3,500,000 |
| Aug 14, 2007 | Expired or cancelled cancelled Jan 2026 | 222 Mason St | installation of conduit for hvac controlDetails
installation of conduit for hvac control | ||
| Nov 1, 2006 | Expired or cancelled withdrawn Dec 2007 | 222 Mason St | Johnson Controls Inc. | upgrading fire alarm system & bms systems.Details
upgrading fire alarm system & bms systems. | $660,000 |
| Aug 31, 2005 | Completed final sign-off Nov 2005 | 222 Mason St | Rudolph Commercial Interiors Inc, Rci | renewal of permit renewal of permit#200501253964,#200412171650.Details
renewal of permit renewal of permit#200501253964,#200412171650. | |
| Apr 30, 2001 | Expired or cancelled expired Oct 2001 | 222 Mason St | alteration to meeting room and ada restroomDetails
alteration to meeting room and ada restroom | $25,000 | |
| Jan 12, 2001 | Expired or cancelled expired Jul 2001 | 222 Mason St | fire alarm tenant improvement at 2nd floor sushi bar at hotel nikkoDetails
fire alarm tenant improvement at 2nd floor sushi bar at hotel nikko | $10,000 | |
| Dec 20, 2000 | Expired or cancelled expired Apr 2001 | 222 Mason St | Anderson, Rowe & Buckley, Inc. | provide fire protection work 25th flr phase 2 200008249729Details
provide fire protection work 25th flr phase 2 200008249729 | $2,800 |
| Dec 7, 2000 | Expired or cancelled expired Apr 2001 | 222 Mason St | replace (e) espresso machines, minor counter adjustments mechanical under seprarate permitDetails
replace (e) espresso machines, minor counter adjustments mechanical under seprarate permit | $3,500 | |
| Nov 20, 2000 | Expired or cancelled expired May 2001 | 222 Mason St | Details
| $21,000 | |
| Sep 26, 2000 | Expired or cancelled expired Mar 2001 | 222 Mason St | revision to pa#20000201763/25th floor corridorDetails
revision to pa#20000201763/25th floor corridor | ||
| Aug 24, 2000 | Expired or cancelled expired Mar 2001 | 222 Mason St | Anderson, Rowe & Buckley, Inc. | provide fire protection work 25th flr,sprinkler head relocationDetails
provide fire protection work 25th flr,sprinkler head relocation | $20,575 |
| Apr 4, 2000 | Expired or cancelled expired Aug 2000 | 222 Mason St | relocate existing lifesafety speakers within hotel restrooms - 9 speakers on 6th floorDetails
relocate existing lifesafety speakers within hotel restrooms - 9 speakers on 6th floor | $1,000 | |
| Feb 9, 2000 | Completed final sign-off Jun 2000 | 222 Mason St | convert 4 suites into 9 hotel roomsDetails
convert 4 suites into 9 hotel rooms | $125,000 | |
| Feb 4, 2000 | Completed final sign-off Jun 2000 | 222 Mason St | Anderson, Rowe & Buckley, Inc. | install fire sprinklerDetails
install fire sprinkler | $1,890 |
| Feb 1, 2000 | Expired or cancelled expired Jun 2001 | 222 Mason St | modify existing 25th floor restaurant to be a conference center/meeting roomDetails
modify existing 25th floor restaurant to be a conference center/meeting room | $300,000 |