Block 0166, lot 001
747 Front St
- City’s use
- Commercial Office
- Built
- 1909
- Stories
- 4
- Units
- 2
- Building
- 86,171 sq ft
- Lot
- 17,542 sq ft
- Zoning
- C2
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
81 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 18, 2025 | Completed final sign-off Jul 2025 | 747 Front St | Arrow Sign Company | install (1) set non illuminated letters to (e) canopy " braunhagey + borden llp "Details
install (1) set non illuminated letters to (e) canopy " braunhagey + borden llp " | $995 |
| Jun 18, 2025 | Completed final sign-off Jul 2025 | 747 Front St | Arrow Sign Company | install (2) set non illuminated d/f hanging sings to (e) canopy " a "Details
install (2) set non illuminated d/f hanging sings to (e) canopy " a " | $995 |
| May 1, 2025 | In progress filed May 2025, not yet issued | 747 Front St | install a partition and glazed al. (pair) doors to create new wellness room. also infill (e) opening on wall. m.i.p. under sep permit.Details
install a partition and glazed al. (pair) doors to create new wellness room. also infill (e) opening on wall. m.i.p. under sep permit. | $6,150 | |
| Apr 8, 2025 | Completed final sign-off May 2025 | 747 Front St | Bilcor Inc | install 1 ceiling mount horn strobe ref pa 202408057928Details
install 1 ceiling mount horn strobe ref pa 202408057928 | $666 |
| Jan 27, 2025 | Completed final sign-off May 2025 | 747 Front St | San Francisco Commercial Builders Inc | revision 202408057928- changing the pass thru window within the same openingDetails
revision 202408057928- changing the pass thru window within the same opening | $1,000 |
| Oct 2, 2024 | Completed final sign-off May 2025 | 747 Front St | San Francisco Commercial Builders Inc | revision to approved pa # 202405091825: revise scope - revision to partition type c per elevation 8/a104.1 and details 2 & 4 a/a601.1.Details
revision to approved pa # 202405091825: revise scope - revision to partition type c per elevation 8/a104.1 and details 2 & 4 a/a601.1. | |
| Aug 8, 2024 | Completed final sign-off Jul 2025 | 747 Front St | Ad Art Inc. | installation of awning/canopy structureDetails
installation of awning/canopy structure | $10,000 |
| Aug 5, 2024 | Completed final sign-off May 2025 | 747 Front St | San Francisco Commercial Builders Inc | ground fl change of use from gym to coffee shop ti to include minor electrical and plumbing. (n) pass through window.Details
ground fl change of use from gym to coffee shop ti to include minor electrical and plumbing. (n) pass through window. | $75,000 |
| Jul 26, 2024 | Completed final sign-off Nov 2024 | 747 Front St | Arrow Sign Company | install 2 sets of internally illuminated channel letters & logo mounted on a wirewayDetails
install 2 sets of internally illuminated channel letters & logo mounted on a wireway | $21,640 |
| May 9, 2024 | Completed final sign-off May 2025 | 747 Front St | San Francisco Commercial Builders Inc | g/f: demise new tenant suite. mep deferred.Details
g/f: demise new tenant suite. mep deferred. | $96,000 |
| Apr 29, 2024 | Completed final sign-off Jun 2024 | 747 Front St | Bilcor Inc | install (22) ceiling mount horn-strobe. install (10) ceiling mount strobe. ref arch ti 202401103702Details
install (22) ceiling mount horn-strobe. install (10) ceiling mount strobe. ref arch ti 202401103702 | $21,312 |
| Feb 22, 2024 | Completed final sign-off Oct 2024 | 747 Front St | C B F Inc | 4/f: deferred electrical work for bldg permit# 202401103702, 150 lights, 160 receptacles and relocation of 1 electrical panel.Details
4/f: deferred electrical work for bldg permit# 202401103702, 150 lights, 160 receptacles and relocation of 1 electrical panel. | $495,000 |
| Jan 10, 2024 | Completed final sign-off Oct 2024 | 747 Front St | San Francisco Commercial Builders Inc | 4th fl - consists of interior demo of non structural elements & ti office build out. office improvements consists of (n) offices, meeting rooms, lounge, shower (n) partitions, doors, finishes, ceilings & lighting. scope of work includes restroom ada accessibility upgrades. mep, life safety & fireDetails
4th fl - consists of interior demo of non structural elements & ti office build out. office improvements consists of (n) offices, meeting rooms, lounge, shower (n) partitions, doors, finishes, ceilings & lighting. scope of work includes restroom ada accessibility upgrades. mep, life safety & fire | $2,000,000 |
| Dec 23, 2022 | Completed final sign-off Feb 2023 | 747 Front St | Arrow Sign Company | install 2 sets internally illuminated logos on a wireway copy read "ivp" replace (e) signsDetails
install 2 sets internally illuminated logos on a wireway copy read "ivp" replace (e) signs | $6,737 |
| Dec 23, 2022 | Completed final sign-off Feb 2023 | 747 Front St | Arrow Sign Company | install 1 non-illumincated projecting sign "ivp"Details
install 1 non-illumincated projecting sign "ivp" | $3,000 |
| Mar 16, 2021 | Completed final sign-off Jun 2021 | 747 Front St | Arrow Sign Company | install (2) internally illuminated single faced letter sets wall sign: "ivp"Details
install (2) internally illuminated single faced letter sets wall sign: "ivp" | $3,300 |
| Nov 24, 2020 | Completed final sign-off Oct 2021 | 747 Front St | Golden Gate Sign Company Inc. | manufacture 1 structural steel canopy 5'-8" x 9'- 5"Details
manufacture 1 structural steel canopy 5'-8" x 9'- 5" | $25,000 |
| Nov 5, 2020 | Completed final sign-off Dec 2020 | 747 Front St | San Francisco Fire Protection | voluntary add-on installation to existing fa system. install of wall and ceiling mount horn strobes. install of ceiling strobes in the bathroom. install of monitor modules to existing duct detectors. install of manual pull station at lobby. ref fa system pa # 2014-0908-5632, pa #2020-0902-3288Details
voluntary add-on installation to existing fa system. install of wall and ceiling mount horn strobes. install of ceiling strobes in the bathroom. install of monitor modules to existing duct detectors. install of manual pull station at lobby. ref fa system pa # 2014-0908-5632, pa #2020-0902-3288 | $14,047 |
| Oct 24, 2020 | Completed final sign-off Nov 2021 | 747 Front St | Victory Electric | lobby lighting renovation. electrical titel 24. power & lighting. reference #2020-0805-1161.Details
lobby lighting renovation. electrical titel 24. power & lighting. reference #2020-0805-1161. | $88,000 |
| Sep 2, 2020 | Completed final sign-off Apr 2021 | 747 Front St | Novo Construction Inc | interior improvement on 1st fl to include demolition of non-structural patitions. revision to mep distribution. new electrical & plumbing. new lighting, ceilings, finishes, flooring & furniture.Details
interior improvement on 1st fl to include demolition of non-structural patitions. revision to mep distribution. new electrical & plumbing. new lighting, ceilings, finishes, flooring & furniture. | $1,013,000 |
| Aug 5, 2020 | Completed final sign-off Mar 2022 | 747 Front St | San Francisco Commercial Builders Inc | limited demo and new partitions, doors, power/data, finishes and lighting. new marquee and exterior address plate by others. new elevator cab upgrades. space is currently occupied. mep, life safety and sinage under seperate permit.Details
limited demo and new partitions, doors, power/data, finishes and lighting. new marquee and exterior address plate by others. new elevator cab upgrades. space is currently occupied. mep, life safety and sinage under seperate permit. | $340,000 |
| May 11, 2020 | Never finaled issued May 2020, no final | 747 Front St | The Lawson Roofing Co Inc. | street space / 202002134360Details
street space / 202002134360 | |
| Feb 13, 2020 | Completed final sign-off Jun 2020 | 747 Front St | The Lawson Roofing Co Inc. | reroofingDetails
reroofing | $401,350 |
| Aug 30, 2018 | Completed final sign-off Jan 2019 | 747 Front St | San Francisco Fire Protection | add 2 relays to (e) fire alarm system, power for new card magnetic looks to be dropped on new fire alarm activation. magnetic locks are installed and powered by others. add 2 monitor modules to (e) fire alarm system. modules are to activate existing fire alarm system when emergency exit is initiatedDetails
add 2 relays to (e) fire alarm system, power for new card magnetic looks to be dropped on new fire alarm activation. magnetic locks are installed and powered by others. add 2 monitor modules to (e) fire alarm system. modules are to activate existing fire alarm system when emergency exit is initiated | $5,000 |
| Aug 13, 2018 | Completed final sign-off Jan 2019 | 747 Front St | Constructive Solutions Inc. | 4th flr. new windows, doors and gyp board soffits at reception. maher n/aDetails
4th flr. new windows, doors and gyp board soffits at reception. maher n/a | $12,000 |
| Jan 30, 2018 | Completed final sign-off May 2018 | 747 Front St | Arrow Sign Company | install (2) sets of illuminated letters & logos, single-faced, wall sign. sign "a"Details
install (2) sets of illuminated letters & logos, single-faced, wall sign. sign "a" | $5,000 |
| Jan 30, 2018 | Completed final sign-off Apr 2018 | 747 Front St | Arrow Sign Company | install (1) 1/8" aluminum panel onto existing fixture. single-faced, non-illuminated, sign "b"Details
install (1) 1/8" aluminum panel onto existing fixture. single-faced, non-illuminated, sign "b" | $300 |
| Apr 15, 2015 | Completed final sign-off May 2015 | 747 Front St | Bilcor Inc | 2nd floor: fire alarm tenant improvement. install 1 booster panel, install 8 ceiling mount strobes, install 22 ceiling mount horn-strobes, install 5 smoke detectors with bases, install 6 duct detectors, install 6 control relay modules. ref app#201503049910 n/a for maherDetails
2nd floor: fire alarm tenant improvement. install 1 booster panel, install 8 ceiling mount strobes, install 22 ceiling mount horn-strobes, install 5 smoke detectors with bases, install 6 duct detectors, install 6 control relay modules. ref app#201503049910 n/a for maher | $19,200 |
| Apr 13, 2015 | Expired or cancelled cancelled Jan 2026 | 747 Front St | fire alarm t.i. install 1 booster panel, install 8 ceiling mount strobes, install 22 ceiling mount horn-strokes, install 5 smoke detector with bases, install 6 duct detectors, and 7 control relay modules.Details
fire alarm t.i. install 1 booster panel, install 8 ceiling mount strobes, install 22 ceiling mount horn-strokes, install 5 smoke detector with bases, install 6 duct detectors, and 7 control relay modules. | $19,600 | |
| Mar 30, 2015 | Never finaled issued Mar 2015, no final | 747 Front St | street spaceDetails
street space | ||
| Mar 4, 2015 | Completed final sign-off Jul 2015 | 747 Front St | Dettaglio Construction Inc Dba Dci Const | revision to pa# 2014 0627 9711 - changes to partition plan, power & signal rlp, electrical, hvac, plumb, submitting structural drawings. maher - not req'dDetails
revision to pa# 2014 0627 9711 - changes to partition plan, power & signal rlp, electrical, hvac, plumb, submitting structural drawings. maher - not req'd | |
| Feb 27, 2015 | Never finaled issued Feb 2015, no final | 747 Front St | Chris' Plumbing Inc | 2nd floor - class ii standpipe relocation move 5' and rotate 90 degrees maher - not req'dDetails
2nd floor - class ii standpipe relocation move 5' and rotate 90 degrees maher - not req'd | $1,500 |
| Feb 9, 2015 | Completed final sign-off Aug 2015 | 747 Front St | Arrow Sign Company | erect (2) illuminated letter sets single faced wall sign. n/a maher ordinanceDetails
erect (2) illuminated letter sets single faced wall sign. n/a maher ordinance | $4,500 |
| Feb 9, 2015 | Completed final sign-off Aug 2015 | 747 Front St | Arrow Sign Company | erect (4) illuminated letter sets single faced wall sign. n/a maher ordinanceDetails
erect (4) illuminated letter sets single faced wall sign. n/a maher ordinance | $9,000 |
| Feb 9, 2015 | Completed final sign-off Aug 2015 | 747 Front St | Arrow Sign Company | erect (2) illuminated letter sets single faced wall sign. n/a maher ordinanceDetails
erect (2) illuminated letter sets single faced wall sign. n/a maher ordinance | $3,500 |
| Feb 9, 2015 | Completed final sign-off Aug 2015 | 747 Front St | Arrow Sign Company | erect (1) non-illuminated single faced wall sign directory plaque. n/a maher ordinanceDetails
erect (1) non-illuminated single faced wall sign directory plaque. n/a maher ordinance | $1,500 |
| Dec 4, 2014 | Never finaled issued Dec 2014, no final | 747 Front St | Priority Architectural Graphics Dba Prio | 6 evacuation maps to be reviewed by sffd only. n/a for the maher ordinance.Details
6 evacuation maps to be reviewed by sffd only. n/a for the maher ordinance. | $1,500 |
| Oct 28, 2014 | Expired or cancelled cancelled Jan 2026 | 747 Front St | electrical work for tenant improvement on the 4/f., t.i. pa#201408143781. n/a ordinance #155-13.Details
electrical work for tenant improvement on the 4/f., t.i. pa#201408143781. n/a ordinance #155-13. | $25,000 | |
| Oct 8, 2014 | Completed final sign-off Feb 2015 | 747 Front St | Bilcor Inc | 4th floor - install 1 booster panel, 3 ceiling mount strobes, 24 ceiling mount horn strobes, 3 smoke detector, 8 duct detectors and 9 control relay modules. ref. t.i. appl. 201408143781. maher n/a.Details
4th floor - install 1 booster panel, 3 ceiling mount strobes, 24 ceiling mount horn strobes, 3 smoke detector, 8 duct detectors and 9 control relay modules. ref. t.i. appl. 201408143781. maher n/a. | $16,000 |
| Oct 2, 2014 | Completed final sign-off Sep 2015 | 747 Front St | Dettaglio Construction Inc Dba Dci Const | 4th floor: mechanical and electrical work for t.i. ref arch app#201408143781. n/a for the maherDetails
4th floor: mechanical and electrical work for t.i. ref arch app#201408143781. n/a for the maher | $10,000 |
| Oct 1, 2014 | Never finaled issued Oct 2014, no final | 747 Front St | Bilcor Inc | 3rd flr: as built revision to pa 201409116120. fire alarm ti 3rd floor-duct detector relocated and elimante 1 duct detector.Details
3rd flr: as built revision to pa 201409116120. fire alarm ti 3rd floor-duct detector relocated and elimante 1 duct detector. | |
| Sep 11, 2014 | Never finaled issued Sep 2014, no final | 747 Front St | Bilcor Inc | on 3rd floor, install 1 booster panel, 5 ceiling mount strobes, 23 ceiling mount speaker strobes, 8 smoke detectors, 8 duct detectors with smoke detector heads, install 8 control relay modules. pa#201406143781.Details
on 3rd floor, install 1 booster panel, 5 ceiling mount strobes, 23 ceiling mount speaker strobes, 8 smoke detectors, 8 duct detectors with smoke detector heads, install 8 control relay modules. pa#201406143781. | $21,200 |
| Sep 8, 2014 | Completed final sign-off Jun 2015 | 747 Front St | San Francisco Fire Protection | like for like voluntary system replacement. replace exist 7 smokes, 2 pull stations w/new at the same location. install modules to connect exist waterflow & tamper switch & elev. recall to new panel to be monitored; maher n/aDetails
like for like voluntary system replacement. replace exist 7 smokes, 2 pull stations w/new at the same location. install modules to connect exist waterflow & tamper switch & elev. recall to new panel to be monitored; maher n/a | $3,500 |
| Aug 14, 2014 | Completed final sign-off Jun 2015 | 747 Front St | Dettaglio Construction Inc Dba Dci Const | office t.i. includes:partial non-structural demo of partitions, finishes, light fixtures. accessible upgrades to extg restrooms. addition of restrooms (2 unisex) install new partitions lights, finishes, doors, accoustical ceilings, ceilings and glazing. n/a maher.Details
office t.i. includes:partial non-structural demo of partitions, finishes, light fixtures. accessible upgrades to extg restrooms. addition of restrooms (2 unisex) install new partitions lights, finishes, doors, accoustical ceilings, ceilings and glazing. n/a maher. | $1,000,000 |
| Jun 27, 2014 | Completed final sign-off Apr 2015 | 747 Front St | Dettaglio Construction Inc Dba Dci Const | demo & construction of non-structural interior partitions, doors, frames, hardware, millwork, drywall & accoustic ceiling finishes, mech, electrical & plumbing. deferred submittal fire/life safety, atrium openings & guardrails. n/a ordinance #155-13.Details
demo & construction of non-structural interior partitions, doors, frames, hardware, millwork, drywall & accoustic ceiling finishes, mech, electrical & plumbing. deferred submittal fire/life safety, atrium openings & guardrails. n/a ordinance #155-13. | $536,235 |
| Jun 27, 2014 | Completed final sign-off Jul 2015 | 747 Front St | Dettaglio Construction Inc Dba Dci Const | 2nd fl:demo & construction of non-structural interior partitions, doors, frames, hardware, millwork, drywall & accoustic ceiling finishes, mech, electrical & plumbing. deferred submittal fire/life safety, atrium openings & guardrails. n/a ordinance #155-13.Details
2nd fl:demo & construction of non-structural interior partitions, doors, frames, hardware, millwork, drywall & accoustic ceiling finishes, mech, electrical & plumbing. deferred submittal fire/life safety, atrium openings & guardrails. n/a ordinance #155-13. | $536,235 |
| Jun 26, 2014 | Never finaled issued Jun 2014, no final | 747 Front St | street space permitDetails
street space permit | ||
| May 12, 2014 | Completed final sign-off Jun 2015 | 747 Front St | Constructive Solutions Inc. | interior improvement of entrance lobby work includes relocation of one interior non-load bearing partitoin, removal of existing dropped ceiling, new lighting & finishes, replacement of storefront. compliance with ordinance #155-13 not requiredDetails
interior improvement of entrance lobby work includes relocation of one interior non-load bearing partitoin, removal of existing dropped ceiling, new lighting & finishes, replacement of storefront. compliance with ordinance #155-13 not required | $75,000 |
| Jul 9, 2013 | Expired or cancelled withdrawn Jun 2014 | 747 Front St | 2nd floor-tenant improvement to include removal of (e) dropped ceilings & partitions. new lighting, enlarged bathrooms & formation of new window at rear, not visible from the streetDetails
2nd floor-tenant improvement to include removal of (e) dropped ceilings & partitions. new lighting, enlarged bathrooms & formation of new window at rear, not visible from the street | $375,000 | |
| Dec 12, 2012 | Never finaled issued Dec 2012, no final | 747 Front St | Jeff King And Company Inc | 2nd floor:removal of (e) ceiling, erection of new partitions (non-load bearing) to form into a conference room & re-hanging of lights & hvac ducts.mep under seperate permit.Details
2nd floor:removal of (e) ceiling, erection of new partitions (non-load bearing) to form into a conference room & re-hanging of lights & hvac ducts.mep under seperate permit. | $60,000 |
| Dec 5, 2012 | Completed final sign-off Mar 2013 | 747 Front St | Weidner Architectural Signage | wall mounted, non illuminated signage.Details
wall mounted, non illuminated signage. | $5,800 |
| Sep 17, 2012 | Never finaled issued Oct 2012, no final | 747 Front St | Jeff King And Company Inc | renovation of existing ketchette in existing tenancy with replacement of doors and partitions previously removed.Details
renovation of existing ketchette in existing tenancy with replacement of doors and partitions previously removed. | $45,000 |
| Jan 25, 2012 | Completed final sign-off Apr 2012 | 747 Front St | B-Side Inc. | demolition of 3 office spaces & a partition wall (non-bearing wall) per ab-017.Details
demolition of 3 office spaces & a partition wall (non-bearing wall) per ab-017. | $7,000 |
| Apr 29, 2011 | Never finaled issued Apr 2011, no final | 747 Front St | street space permitDetails
street space permit | ||
| Apr 29, 2011 | Never finaled issued Apr 2011, no final | 747 Front St | street space permitDetails
street space permit | ||
| Jun 17, 2008 | Completed final sign-off Jun 2008 | 747 Front St | ground fl. renew pa#200612210362 & #200706214702 for final inspection.Details
ground fl. renew pa#200612210362 & #200706214702 for final inspection. | ||
| May 9, 2008 | Never finaled issued Jun 2008, no final | 747 Front St | 1st floor north: new t.i. of existing shell condition space of approx. 7866 sf. new accesible restroom and general office improvements of walls,celing, electric , mech & plumbing. this is a mep permit, building permit under appl. 200805071536.Details
1st floor north: new t.i. of existing shell condition space of approx. 7866 sf. new accesible restroom and general office improvements of walls,celing, electric , mech & plumbing. this is a mep permit, building permit under appl. 200805071536. | $220,000 | |
| May 7, 2008 | Completed final sign-off Jun 2008 | 747 Front St | 1st floor - revision to application 200612210362, 200706214702. revision to drawings per inspector's notes- revised da checklist, add fire proof @ rated walls in lieu of repair shaft to dumb waiter, remove & infill. see structural drawings included.Details
1st floor - revision to application 200612210362, 200706214702. revision to drawings per inspector's notes- revised da checklist, add fire proof @ rated walls in lieu of repair shaft to dumb waiter, remove & infill. see structural drawings included. | $4,000 | |
| May 7, 2008 | Completed final sign-off Apr 2009 | 747 Front St | new tenant improvements to include new recessed store front entry off of front street, new accesible restroom and general office. improvements including walls, doors,ceiling,electrical,plumbing. mep separate permitDetails
new tenant improvements to include new recessed store front entry off of front street, new accesible restroom and general office. improvements including walls, doors,ceiling,electrical,plumbing. mep separate permit | $250,000 | |
| Jul 10, 2007 | Expired or cancelled expired Jul 2009 | 747 Front St | Overnet Dba: Blue Pond Signs | to erect non electrical sign.install one new projected non-illuminated sign.Details
to erect non electrical sign.install one new projected non-illuminated sign. | |
| Jul 3, 2007 | Completed final sign-off Jul 2007 | 747 Front St | Dpr Construction Inc | revidion to pa 2006122204229 checklist as requested by assidngd bilding inspector. p[olan revised to show path of egress on crrently exist ot building (this work was preformed ownerDetails
revidion to pa 2006122204229 checklist as requested by assidngd bilding inspector. p[olan revised to show path of egress on crrently exist ot building (this work was preformed owner | |
| Jun 27, 2007 | Completed final sign-off Sep 2007 | 747 Front St | Acco Engineered Systems Inc. Dba Acco En | added split heat pump units for boardroom(434) and conference room(412); added exhaust fans for break room(425), electrical room(416) pantry room(405) & copy/mail room(403). relocate existing heat pump. demolition of existing ductwork and install new ductwork to accomdate new ti planDetails
added split heat pump units for boardroom(434) and conference room(412); added exhaust fans for break room(425), electrical room(416) pantry room(405) & copy/mail room(403). relocate existing heat pump. demolition of existing ductwork and install new ductwork to accomdate new ti plan | $70,000 |
| Jun 27, 2007 | Completed final sign-off Sep 2007 | 747 Front St | Skyline Construction | lighting and electrical work only.Details
lighting and electrical work only. | $45,000 |
| Jun 21, 2007 | Expired or cancelled expired Jun 2008 | 747 Front St | ref. appl#200612210362 revisionto permitted drawings, add new utility door (interior) remove (n) tenant entry door, existing walls to remain and not demolished @ ground floor.Details
ref. appl#200612210362 revisionto permitted drawings, add new utility door (interior) remove (n) tenant entry door, existing walls to remain and not demolished @ ground floor. | ||
| Jun 6, 2007 | Completed final sign-off Sep 2007 | 747 Front St | Skyline Construction | oti-4 4th fl el,me,lsDetails
oti-4 4th fl el,me,ls | $450,000 |
| May 15, 2007 | Completed final sign-off Jul 2007 | 747 Front St | minor revision to store front and bathrooms (as-built submittal) per appl#200612220429Details
minor revision to store front and bathrooms (as-built submittal) per appl#200612220429 | $100 | |
| Apr 5, 2007 | Never finaled issued Apr 2007, no final | 747 Front St | street space permitDetails
street space permit | ||
| Dec 22, 2006 | Completed final sign-off Jul 2007 | 747 Front St | Dpr Construction Inc | tenant improvements to + - 7,000 sqft. including partitions, finishes, electrical, plumbing & hvac two toilet rooms, offices and storage space.Details
tenant improvements to + - 7,000 sqft. including partitions, finishes, electrical, plumbing & hvac two toilet rooms, offices and storage space. | $500,000 |
| Dec 21, 2006 | Expired or cancelled expired Jun 2008 | 747 Front St | provide new demising wall in grey shell space + comdor (1 hr). provide new tenant entry doors.Details
provide new demising wall in grey shell space + comdor (1 hr). provide new tenant entry doors. | $35,000 | |
| Nov 19, 2004 | Completed final sign-off Jan 2005 | 747 Front St | demo walls, partitions and doors, partition/door infill & replace doors.Details
demo walls, partitions and doors, partition/door infill & replace doors. | $25,000 | |
| Jun 18, 2004 | Never finaled issued Jun 2004, no final | 101 Broadway | Golden Gate Sign Company Inc. | to erect single faced electric signDetails
to erect single faced electric sign | |
| Jun 4, 2004 | Completed final sign-off Sep 2004 | 747 Front St | replace studs sizing on permit #2004/02/24/7063r1 with new sizing for manufacturers specificationDetails
replace studs sizing on permit #2004/02/24/7063r1 with new sizing for manufacturers specification | ||
| Feb 24, 2004 | Completed final sign-off Sep 2004 | 747 Front St | oti-1 3rd fl-el,meDetails
oti-1 3rd fl-el,me | $206,000 | |
| Feb 24, 2004 | Completed final sign-off Sep 2004 | 747 Front St | oti-2 3rd fl-el,meDetails
oti-2 3rd fl-el,me | $200,175 | |
| Aug 6, 2003 | Expired or cancelled expired Mar 2004 | 747 Front St | Signs America Inc Dba Sign A Rama | erect sign for non electric, wall ,single facedDetails
erect sign for non electric, wall ,single faced | |
| Apr 16, 2002 | Never finaled issued Apr 2002, no final | 747 Front St | street space permitDetails
street space permit | ||
| Nov 27, 2001 | Completed final sign-off Jan 2002 | 747 Front St | oti-2 4th floor ltg onlyDetails
oti-2 4th floor ltg only | $39,109 | |
| Nov 27, 2001 | Expired or cancelled expired Mar 2004 | 747 Front St | elevator replacement to comply with adaDetails
elevator replacement to comply with ada | $104,000 | |
| Nov 2, 2001 | Completed final sign-off Jan 2002 | 747 Front St | oti-1 4/f elDetails
oti-1 4/f el | $42,368 | |
| Oct 16, 2000 | Expired or cancelled expired Apr 2001 | 747 Front St | interior demoDetails
interior demo | ||
| Jul 6, 2000 | Expired or cancelled expired Aug 2001 | 747 Front St | install store-front windows, disabled access for sidewalk and street repairDetails
install store-front windows, disabled access for sidewalk and street repair | $155,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.