Block 0136, lot 001
55 Green St
- City’s use
- Commercial Office
- Built
- 1984
- Stories
- 5
- Units
- 1
- Rooms
- 3 bathrooms
- Building
- 51,025 sq ft
- Lot
- 8,962 sq ft
- Zoning
- C2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
36 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 9, 2026 | In progress issued Sep 2026 | 55 Green St | Corish Commercial Electric Inc | 5th floor: office t.i. office outlets, lighting, controls, data, fire alarm. ref#: 202602236322Details
5th floor: office t.i. office outlets, lighting, controls, data, fire alarm. ref#: 202602236322 | $70,000 |
| May 19, 2026 | Completed final sign-off Sep 2026 | 55 Green St | 3d Signs Llc | install 2 signs: (twelve labs) backlit matel led signs will try to install between bricksDetails
install 2 signs: (twelve labs) backlit matel led signs will try to install between bricks | $2,550 |
| May 11, 2026 | In progress filed May 2026, not yet issued | 55 Green St | 3d Signs Llc | install 12 channel letters illunimated facing street for twelve labs called sign aDetails
install 12 channel letters illunimated facing street for twelve labs called sign a | $5,500 |
| Feb 23, 2026 | In progress issued Apr 2026 | 55 Green St | Rowdy Red Construction Llc | interior only 5th floor t.i. remodel existing restrooms. new all gender restroom. renovate entire floor with new offices, open work area, break room and reception area. mep deffered.Details
interior only 5th floor t.i. remodel existing restrooms. new all gender restroom. renovate entire floor with new offices, open work area, break room and reception area. mep deffered. | $1,000,000 |
| Feb 24, 2025 | Completed final sign-off Mar 2025 | 55 Green St | Everon Llc | 2nd fl - fire alarm add 1 control relay t0 interface with access control. release at exist side of stairwell door.Details
2nd fl - fire alarm add 1 control relay t0 interface with access control. release at exist side of stairwell door. | $800 |
| Jan 30, 2025 | Completed final sign-off Feb 2025 | 55 Green St | Everon Llc | fire alarm ti on 1st fl. add 1 wall mount horn/strobe in conference room ref pa 202412166865Details
fire alarm ti on 1st fl. add 1 wall mount horn/strobe in conference room ref pa 202412166865 | $800 |
| Dec 16, 2024 | Completed final sign-off Feb 2025 | 55 Green St | Rowdy Red Construction Llc | level 1 - area of the (e) open office will be converted into an enclosed conference. total area of alteration is 258 sq ft which is 2.69% of the gross building area. mep deferred.Details
level 1 - area of the (e) open office will be converted into an enclosed conference. total area of alteration is 258 sq ft which is 2.69% of the gross building area. mep deferred. | $113,300 |
| Dec 12, 2024 | Completed final sign-off Dec 2024 | 55 Green St | Rowdy Red Construction Llc | remove mep scope for pa# 202406104034Details
remove mep scope for pa# 202406104034 | |
| Sep 9, 2024 | Completed final sign-off Oct 2024 | 55 Green St | Everon Llc | fire alarm ti: add 1-control relay to interface with access control. ref pa# 202406104034.Details
fire alarm ti: add 1-control relay to interface with access control. ref pa# 202406104034. | $800 |
| Jun 10, 2024 | Completed final sign-off Dec 2024 | 55 Green St | elevator vestiblles for floor 2, 3, and 4. small drop soffits, new doors, relocate exist signs.Details
elevator vestiblles for floor 2, 3, and 4. small drop soffits, new doors, relocate exist signs. | $43,500 | |
| Jun 10, 2024 | Completed final sign-off Jun 2024 | 55 Green St | Golden Gate Fire Protection Inc | floors 2,3,4: fire sprinklers, relocate 3 uprights & 1 pendent on the 2/f, relocate 3 uprights and 4 pendents on 3/f, and relocate 3 uprights & 4 pendents on the 4/f.Details
floors 2,3,4: fire sprinklers, relocate 3 uprights & 1 pendent on the 2/f, relocate 3 uprights and 4 pendents on 3/f, and relocate 3 uprights & 4 pendents on the 4/f. | $45,400 |
| Nov 25, 2019 | Never finaled issued Dec 2019, no final | 55 Green St | Dome Construction Corp | ti of level 5 office space. improvement include non-structural partitions, doors, ceilings, lighting & finishes. electrical & mechicanl system are withing the socpe of work. maher naDetails
ti of level 5 office space. improvement include non-structural partitions, doors, ceilings, lighting & finishes. electrical & mechicanl system are withing the socpe of work. maher na | $2,700,000 |
| Oct 17, 2019 | Completed final sign-off Nov 2019 | 55 Green St | Bilcor Inc | ground floor: fire alarm: install 1 wall mount strobe. install 2 wall mount horn strobes. install 4 ceiling mount strobe. install 8 ceiling mount horn strobes. install 2 weater proof ceiling mount strobes. install 1 smoke detector with base. install 1 control relay. ref app#201907226512.Details
ground floor: fire alarm: install 1 wall mount strobe. install 2 wall mount horn strobes. install 4 ceiling mount strobe. install 8 ceiling mount horn strobes. install 2 weater proof ceiling mount strobes. install 1 smoke detector with base. install 1 control relay. ref app#201907226512. | $12,540 |
| Sep 16, 2019 | Never finaled issued Oct 2019, no final | 55 Green St | Dome Construction Corp | for public health review only of pantry support and catered lunches for employees. see ref pa#2019-0722-6512 for scope of work.Details
for public health review only of pantry support and catered lunches for employees. see ref pa#2019-0722-6512 for scope of work. | |
| Aug 14, 2019 | Never finaled issued Aug 2019, no final | 55 Green St | Pribuss Engineering Inc | 1st fl - fire sprinkler, ref pa 2019-0722-6512. add 95 sprinklersDetails
1st fl - fire sprinkler, ref pa 2019-0722-6512. add 95 sprinklers | $48,830 |
| Jul 22, 2019 | Never finaled issued Aug 2019, no final | 55 Green St | Dome Construction Corp | ti - ground floor office space. improvements include non structural partitions, doors, lighting and arch finished. new ele & mech systems, new plmDetails
ti - ground floor office space. improvements include non structural partitions, doors, lighting and arch finished. new ele & mech systems, new plm | $2,730,000 |
| Jun 20, 2019 | Never finaled issued Jun 2019, no final | 55 Green St | Bilcor Inc | 2nd fl - fire alarm ti install 8 ceiling strobes, install 16 ceiling strobes. ref pa 2019-0603-2309Details
2nd fl - fire alarm ti install 8 ceiling strobes, install 16 ceiling strobes. ref pa 2019-0603-2309 | $15,840 |
| Jun 6, 2019 | Completed final sign-off Aug 2019 | 55 Green St | Pribuss Engineering Inc | 2nd fl - fire sprinkler ti on - relocated 25, added 58. ref pa 2019-0603-2309Details
2nd fl - fire sprinkler ti on - relocated 25, added 58. ref pa 2019-0603-2309 | $42,662 |
| Jun 3, 2019 | Never finaled issued Jun 2019, no final | 55 Green St | Dome Construction Corp | tenant improvement of level 2 office space. improvements include non structural partitions, doors, ceilings, lighting, arch finishes. elec, mechDetails
tenant improvement of level 2 office space. improvements include non structural partitions, doors, ceilings, lighting, arch finishes. elec, mech | $1,329,100 |
| Apr 23, 2019 | Completed final sign-off May 2019 | 55 Green St | Bilcor Inc | 3/f & 4/f: t.i. install (30) ceiling mount horn strobes, install (13) ceiling mount strobes. maher n/a.Details
3/f & 4/f: t.i. install (30) ceiling mount horn strobes, install (13) ceiling mount strobes. maher n/a. | $21,500 |
| Mar 21, 2019 | Completed final sign-off Jul 2019 | 55 Green St | Pribuss Engineering Inc | fire sprinkler t.i. on 3rd & 4th fl. extend sprinkler system to provide complete coverage on 3 & 4th floors. (ref #201903064555) total added 175 n/a maherDetails
fire sprinkler t.i. on 3rd & 4th fl. extend sprinkler system to provide complete coverage on 3 & 4th floors. (ref #201903064555) total added 175 n/a maher | $89,950 |
| Mar 6, 2019 | Never finaled issued Mar 2019, no final | 55 Green St | Dome Construction Corp | t.i. building out of level 03 and 04 office space. improvements inlclude non structural partitions, doors, ceilings, lighting, architectural finishes, electrical and mechanical.Details
t.i. building out of level 03 and 04 office space. improvements inlclude non structural partitions, doors, ceilings, lighting, architectural finishes, electrical and mechanical. | $2,300,000 |
| Jan 8, 2019 | Never finaled issued Jan 2019, no final | 55 Green St | street spaceDetails
street space | ||
| Dec 7, 2018 | Completed final sign-off Mar 2019 | 55 Green St | Dome Construction Corp | removal of non structural partitions vceiling, arch finishes, ele and mech distribution on floors 1 to 5 to prepare floors for future tiDetails
removal of non structural partitions vceiling, arch finishes, ele and mech distribution on floors 1 to 5 to prepare floors for future ti | $227,635 |
| Sep 6, 2018 | Expired or cancelled withdrawn Nov 2018 | 55 Green St | interior non structural demo of 1st-5th floors. to include partitions, flooring, ceilings, finishes & furnishing. no change to egress no ext work. all other work under sep paDetails
interior non structural demo of 1st-5th floors. to include partitions, flooring, ceilings, finishes & furnishing. no change to egress no ext work. all other work under sep pa | $175,000 | |
| May 28, 2014 | Never finaled issued May 2014, no final | 55 Green St | street space & mta parking meterDetails
street space & mta parking meter | ||
| Nov 10, 2010 | Completed final sign-off Mar 2011 | 55 Green St | Meylan Construction | 2nd floor-new partitions, doors, frames & painting. minor changes to lighting & electrical. relocation of hvac diffusersDetails
2nd floor-new partitions, doors, frames & painting. minor changes to lighting & electrical. relocation of hvac diffusers | $21,317 |
| Jul 9, 2009 | Completed final sign-off Jul 2009 | 55 Green St | E. J. Weber Elect.Co Inc | renew pa# 2007/02/27/4961 to obtain final inspection. all work has been completed.Details
renew pa# 2007/02/27/4961 to obtain final inspection. all work has been completed. | |
| Nov 27, 2007 | Never finaled issued Nov 2007, no final | 55 Green St | Diversified Fire Products | 4th floor - t.i. fm200 interface to existing to fa system. (2) address mod, (1) control relay, (4) smoke, (1) strobe, (1) h/s, (1) pull, (1) releasing mod, (2) releasing relays, (2)svc disconnect, (1) abort switch, (2) solenoids, (1) discharge switch.Details
4th floor - t.i. fm200 interface to existing to fa system. (2) address mod, (1) control relay, (4) smoke, (1) strobe, (1) h/s, (1) pull, (1) releasing mod, (2) releasing relays, (2)svc disconnect, (1) abort switch, (2) solenoids, (1) discharge switch. | $37,000 |
| Feb 27, 2007 | Expired or cancelled expired Mar 2009 | 55 Green St | E. J. Weber Elect.Co Inc | provide a new addreessable fire alarm system to include devices, control modules & notification appliances for all 5 floors, basement and roof.Details
provide a new addreessable fire alarm system to include devices, control modules & notification appliances for all 5 floors, basement and roof. | $38,000 |
| Sep 2, 2004 | Never finaled issued Sep 2004, no final | 55 Green St | street space permitDetails
street space permit | ||
| Sep 8, 2003 | Expired or cancelled expired Dec 2005 | 55 Green St | Simplex Grinnell | replace 22 each (e) central omega sprinklers w/gem model "a" quick response heads 1/2" npt w/k-factoDetails
replace 22 each (e) central omega sprinklers w/gem model "a" quick response heads 1/2" npt w/k-facto | $1,590 |
| Aug 7, 2001 | Completed final sign-off Mar 2002 | 55 Green St | E. J. Weber Elect.Co Inc | life safety device relocated and additioning devices added to existing systems, on 2nd flrDetails
life safety device relocated and additioning devices added to existing systems, on 2nd flr | $5,000 |
| Jul 17, 2001 | Completed final sign-off Mar 2002 | 55 Green St | Bcci Construction Company | oti-2 2nd floor, el onlyDetails
oti-2 2nd floor, el only | $20,000 |
| Jul 3, 2001 | Expired or cancelled expired Dec 2002 | 55 Green St | Bcci Construction Company | oti-1, 2nd fl, lt, ls.Details
oti-1, 2nd fl, lt, ls. | $35,000 |
| May 17, 2001 | Completed final sign-off Jun 2001 | 55 Green St | Bcci Construction Company | interior demolition of non-bearing partition on 2/fl. letter of exemption certify full ada compliancDetails
interior demolition of non-bearing partition on 2/fl. letter of exemption certify full ada complianc | $8,500 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.