Block 0135, lot 003
901 Battery St
51 permits filed for this property since 2000.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 11, 2025 | Completed | 901 Battery St | Richlen Construction | 1 floor - suite 100: interior ti. including new non-structural partitions, millwork, light fixtures and plumbing fixtures and finishes. | $1,000,000 |
| Aug 8, 2024 | In progress | 901 Battery St | Richlen Construction | abe ord 51-16 accessible building entry upgrades, relocate door actuator to front facade, exterior sidewalk upgrades. abe 20200492108 | $147,000 |
| Nov 8, 2023 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | 3rd flr. as built to show (2) added ceiling horn strobes and monitor modules for water flow and tamper switch. ref#: 202308013470 | |
| Aug 1, 2023 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | 3/f: fire alarm. 28 horn strobes, 18 ceiling strobes and 1 relay module to be added for proper coverage. ref pa 202306270898 | $10,000 |
| Jul 10, 2023 | Completed | 901 Battery St | Gci, Inc | 3/f: mep add branch ductwork and required vavs to new hvac zones, ddc system to be added to the floor, providfe new lighting & power to existing circuit. ref pa# 202305177916. | $1,200,000 |
| Jun 27, 2023 | Completed | 901 Battery St | R L H Fire Protection Inc | 3/f: installation of new fire sprinkler system; rlh scope of work starts at the existing top of riser located in stair 1 (st1-3) ref pa 2023-0517-7916 | $64,000 |
| May 17, 2023 | Completed | 901 Battery St | Gci, Inc | 3/f: t.i. includes demo of non-structural partitions and bldg new non-stru partitions. all new or revised mep's, sprinklers & alarm life safety work will be designed build and submitted separately (bldg is fully sprinklered) as part of scope. | $600,000 |
| Mar 28, 2023 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | this is an addition to the existing fire alarm system. 6 duct detectors and 6 relay modules to be added to provide proper coverage. ref pa# 202109017560 | $3,000 |
| Dec 14, 2022 | Completed | 901 Battery St | Richlen Construction | to obtain final inspection for 2017-03201863: all work is complete. 2nd floor | |
| Oct 27, 2022 | Completed | 901 Battery St | Richlen Construction | to obtain final inspection for work approved under pa #201803234407. all work is complete. | |
| Sep 1, 2021 | Completed | 901 Battery St | Richlen Construction | suite 100: interior t.i.: new millwork, finishes, non-structural partitions, light fixtures. mech and elect included. fire/life safety and sprinkler under sep permit. maher n/a. | $750,000 |
| Aug 31, 2021 | Never finaled | 901 Battery St | Pyro-Comm Systems, Inc. | fire alarm mod to (e) system: add 1 smoke detector, 5 ceiling strobes, 15 ceiling horn strobes. 1 wall horn strobe and 2 wall weater proof horn strobe to be added to (e) facu. ref pa 202006088251. | $4,000 |
| Feb 25, 2021 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | this is an addition to the existing facu. ilcd annunciator, 3 duct detector, 1 smoke detector, 6 relay modules, 1 dual monitor module, 1 ceiling strobe, 6 wall strobes, 17 ceiling horn strobes, and 8 wall horn strobes to be added to provide proper coverage. | $10,000 |
| Jan 22, 2021 | Completed | 901 Battery St | 4/f: mechanical & plmbing for t.i. on 4/f. ref t.i. pa 202006088251. maher n/a. | $120,000 | |
| Jan 6, 2021 | Never finaled | 901 Battery St | Novo Construction Inc | 4th floor - electrical work for ti. ref pa 2020-0608-8251 | $20,000 |
| Sep 26, 2020 | Completed | 901 Battery St | Ayoob & Peery Plumbing Co Inc | 4/f: t.i., add (247) sprinklers & main lines and fittings to conform to new wall/ceiling layout of the t.i. ref bpa#202006088251 | $130,000 |
| Jun 8, 2020 | Completed | 901 Battery St | Novo Construction Inc | interior tenant improvement including new non-structural partitions, lighting, plumbing, finishes, and millwork. voluntary addition of new sprinklers to 4th floor. no change in occupancy, use, or area. | $1,327,955 |
| May 15, 2019 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | ref pa 201904107556: 2 manual pull station, 3 relay module, 1 multi-voltage relay, 2 ceiling strobe, 3 wall/horn strobe minimal coverge for unoccupied fl. maher n/a. | $5,000 |
| May 15, 2019 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | ref pa 201903266262; 2 manual pull station, 3 relay module, 1 multi voltage relay, 2 ceiling strobe, 3 wall horn/strobe, minimal coverage for unoccupied floor | $5,000 |
| Apr 10, 2019 | Completed | 901 Battery St | revision to permit #201808106985, change restroom orientation to reuse (e) plumbing chase plus add, full mep engineering. 2nd fl. | $553,321 | |
| Mar 26, 2019 | Completed | 901 Battery St | Richlen Construction | build back accessible restroomsincluding non structural partitions, ceiling assemblies, doors, frames, hardware, lighting, elec, plumbing finishes in empty tenant space. no structural work and no change in use, area or occupancy. mep included | $460,351 |
| Sep 24, 2018 | Completed | 901 Battery St | Richlen Construction | 4th fl - per ab-17 selective demo on vacant, unoccupied 4th fl of (e) non-sstructural partitions, doors/frames, ceiling grid/tile, lighting, power & finishes. there is no new construction under demo permit application. mep and life safety will be under separate permit | $97,980 |
| Sep 19, 2018 | Never finaled | 901 Battery St | street space | ||
| Aug 10, 2018 | Completed | 901 Battery St | Richlen Construction | demo of non structural partitions, ceiling assembles, doors, frams, hardware, lighting, electrical, millwork, plumbing and finishes. build back of accessible restrooms including non structural paritions ceiling assemblies, doors, frames and hardware. no increase in area, change of use. mep/life sep. | $215,706 |
| Aug 9, 2018 | Never finaled | 901 Battery St | street space with meters | ||
| Mar 23, 2018 | Completed | 901 Battery St | Richlen Construction | structural slab infill where (e) stair has been removed. no change in occupancy, use, or area. revision to 201702031863 | $75,000 |
| Apr 7, 2017 | Never finaled | 901 Battery St | street space & sidewalk | ||
| Mar 20, 2017 | Expired or cancelled | 901 Battery St | Novo Construction Inc | 2/f- infill of a single stair opening in existing concrete building, raised floor over structural framing. | $30,000 |
| Nov 3, 2016 | Completed | 901 Battery St | Novo Construction Inc | demo of (e) full height partitions. new wood frame glazing, finishes and associated disable access upgrades. | $102,000 |
| Sep 20, 2016 | Never finaled | 901 Battery St | H & M Fire Protection, Inc. | install new voluntary fire sprinkler syst with new 4-inch riser that feeds sprinkler risers at each floor.install 6-inch fire service off of 8-inch main on 16-inch main on battery.install floor sprinkler systems under separate appl. | |
| Sep 1, 2016 | Completed | 901 Battery St | Pyro-Comm Systems, Inc. | like for like replacement of (e) fa system and field devices with new. (e) fa system being replace due to obsolete panel. (e) device to be replaced with new and connect to new fire alarm panel. | $33,000 |
| Aug 23, 2016 | Never finaled | 901 Battery St | The Brock Company | to renew pa#201212035285 and complete work. | $2,000 |
| Aug 8, 2016 | Never finaled | 901 Battery St | street space permit | ||
| May 14, 2014 | Completed | 901 Battery St | C C I Commercial Construction & Improv | mep for 201312194576 | $50,000 |
| May 13, 2014 | Expired or cancelled | 901 Battery St | erect non electric, wall, 1 single faced sign. | $500 | |
| May 13, 2014 | Never finaled | 901 Battery St | Martinelli Environmental Graph | erect non electric, non-illuminated, wall, 1 single-faced new sign. | $500 |
| Apr 18, 2014 | Never finaled | 901 Battery St | street space permit & mta permit; (m458087 - 1314703) | ||
| Jan 17, 2014 | Never finaled | 901 Battery St | street space and mta parking | ||
| Dec 19, 2013 | Completed | 901 Battery St | C C I Commercial Construction & Improv | non structural t.i. walls for office and conference rooms, add unisex bathrooms, open office improvements. | $850,000 |
| Dec 4, 2013 | Never finaled | 901 Battery St | street space | ||
| Sep 17, 2013 | Never finaled | 901 Battery St | street space meters only- street space under m425987 | ||
| Sep 12, 2013 | Never finaled | 901 Battery St | streetspace | ||
| Aug 5, 2013 | Completed | 901 Battery St | Plant Construction Co, Lp | voluntary structural strengthening. construction of foundation for one interior steel braced frame and one interior shear wall | $175,000 |
| Jun 21, 2013 | Completed | 901 Battery St | Plant Construction Company Lp | voluntary seismic upgrade. accessibility upgrade of (e) common restrooms. improvements of two bldg entry lobbies. teixant spaces maintenance upgrades | $1,300,000 |
| Mar 13, 2013 | Never finaled | 901 Battery St | street space permit | ||
| Dec 3, 2012 | Never finaled | 901 Battery St | The Brock Company | 4th floor-demolition of non bearing partitions & addition of non bearing partitions, relocation of doors & replacement of acoustic ceiling. work is restricted to 4th fl only | $10,817 |
| Oct 24, 2011 | Completed | 909 Battery St | American Construction | insert new glass & frames into (e) partitions relocate (e) glazing unit. reface counters with new millwork @ 1st. flr. | $28,500 |
| Apr 7, 2009 | Completed | 901 Battery St | San Francisco Fire Protection | elevator recall only - install 1 fire panel, 6 smoke detectors, & 2 relays. | $1,500 |
| Sep 28, 2006 | Completed | 901 Battery St | Acco Engineered Systems Inc. Dba Acco En | remove/replace (e) mechanical rooftop equip . install new chiller, pumps & storage tank. supply fan & rooftop ductwork under separate permit. | $150,000 |
| Aug 14, 2006 | Completed | 901 Battery St | Acco Engineered Systems Inc. Dba Acco En | remove and replace supply fan and ductwork on roof only. chiller and storage tank under separate permit | $150,000 |
| May 2, 2001 | Expired or cancelled | 901 Battery St | add emergency generator to roof area | $100,000 |