Block 0056, lot 006
55 Francisco St
The city’s assessor roll has no record for this parcel.
Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
146 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 3, 2013 | Expired or cancelled cancelled Jan 2026 | 55 Francisco St | t.i. to layout of offices per client program and ada requirment. move partition wall in conference room and 2 offices. replace countertop in kitchen.Details
t.i. to layout of offices per client program and ada requirment. move partition wall in conference room and 2 offices. replace countertop in kitchen. | $18,000 | |
| Oct 18, 2012 | Completed final sign-off Dec 2012 | 55 Francisco St | Pioneer Fire Inc. | remove sprinkler piping & all fire sprinklers from elevator machine roomsDetails
remove sprinkler piping & all fire sprinklers from elevator machine rooms | |
| Oct 2, 2012 | Completed final sign-off Feb 2013 | 55 Francisco St | H C I Systems Inc | revision to 201206293755. change contractor for fire alarm system replacement for 8 floors. original pa# 201204259050 scope" fa system replacement, complete replacement of entire system with no phases.Details
revision to 201206293755. change contractor for fire alarm system replacement for 8 floors. original pa# 201204259050 scope" fa system replacement, complete replacement of entire system with no phases. | |
| Jun 29, 2012 | Never finaled issued Jun 2012, no final | 55 Francisco St | Carter Brothers Fire & Life Safety | revision to 201204259050 for fire alarm systemDetails
revision to 201204259050 for fire alarm system | |
| Jun 7, 2012 | Completed final sign-off Sep 2012 | 55 Francisco St | Pioneer Fire Inc. | fire sprinklers : 19 relocated pendents, 2 added pendents, 3 removed pendentsDetails
fire sprinklers : 19 relocated pendents, 2 added pendents, 3 removed pendents | $4,000 |
| May 31, 2012 | Completed final sign-off Jul 2012 | 55 Francisco St | Carter Brothers Fire & Life Safety | add new fire alarm devices to existing fire alarm system in new ti space. includes 4 horn strobes and 1 strobeDetails
add new fire alarm devices to existing fire alarm system in new ti space. includes 4 horn strobes and 1 strobe | $6,250 |
| May 30, 2012 | Completed final sign-off Jul 2012 | 55 Francisco St | Aegis Enterprises Inc | 4th floor/suite #430-fire sprinklers added due to new walls in t.i, 5 added & 1 relocatedDetails
4th floor/suite #430-fire sprinklers added due to new walls in t.i, 5 added & 1 relocated | $2,500 |
| May 23, 2012 | Completed final sign-off Sep 2012 | 55 Francisco St | Cannon Constructors North Inc | revision to 201205089990: 8th fl, delete plan check requirement note to install new guardrails along existing roof top. walkway to exterior fire escapeDetails
revision to 201205089990: 8th fl, delete plan check requirement note to install new guardrails along existing roof top. walkway to exterior fire escape | |
| May 8, 2012 | Completed final sign-off Feb 2013 | 55 Francisco St | Cannon Constructors North Inc | 8th floor:t.i. includes the demolishing of non structural partitions and building new non structural partitions. all new or revised hvac, electrical, plmg and life safety work will be design build and submitted for permit seperately. bldg is fully sprinklered.Details
8th floor:t.i. includes the demolishing of non structural partitions and building new non structural partitions. all new or revised hvac, electrical, plmg and life safety work will be design build and submitted for permit seperately. bldg is fully sprinklered. | $101,000 |
| Apr 27, 2012 | Completed final sign-off Jun 2012 | 55 Francisco St | D A Pope Inc | suite #430: change of use from office to medical office. t.i.: new non load bearing wall, new suspsended ceiling,new casework, new lighting, new restroom.Details
suite #430: change of use from office to medical office. t.i.: new non load bearing wall, new suspsended ceiling,new casework, new lighting, new restroom. | $58,500 |
| Apr 25, 2012 | Never finaled issued May 2012, no final | 55 Francisco St | Carter Brothers Fire & Life Safety | replace existing fire alarm system with a new est3. this is phase 1 of sffd approved capDetails
replace existing fire alarm system with a new est3. this is phase 1 of sffd approved cap | $74,600 |
| Jan 10, 2012 | Completed final sign-off Mar 2012 | 55 Francisco St | Aeco Systems, Inc | suite #710 - modifications to extg fire alarm system consisting of 3 horn/strobe and 6 strobes. 9 devices total. dr kim office.Details
suite #710 - modifications to extg fire alarm system consisting of 3 horn/strobe and 6 strobes. 9 devices total. dr kim office. | $6,000 |
| Dec 16, 2011 | Completed final sign-off Mar 2012 | 55 Francisco St | Aquamatic Fire Protection | suite 705: add 19 fire sprinklers and four seismic laterals for tenant improvement.Details
suite 705: add 19 fire sprinklers and four seismic laterals for tenant improvement. | $5,700 |
| Oct 27, 2011 | Completed final sign-off Mar 2012 | 55 Francisco St | Peacock Construction Inc | demo extg office inerior, build new offices and exam rooms. mep and fire sprinkler under seperate permitDetails
demo extg office inerior, build new offices and exam rooms. mep and fire sprinkler under seperate permit | $50,000 |
| Apr 26, 2011 | Completed final sign-off Jul 2011 | 55 Francisco St | Allcom Electric Inc. | remove and relocate 7 extg horn strobes. ref. to pa#201103081588Details
remove and relocate 7 extg horn strobes. ref. to pa#201103081588 | $6,000 |
| Apr 13, 2011 | Completed final sign-off Jun 2011 | 55 Francisco St | Pioneer Fire Inc. | relocate 13 fire sprinklers, add 1 fire sprinklerDetails
relocate 13 fire sprinklers, add 1 fire sprinkler | $4,800 |
| Mar 8, 2011 | Completed final sign-off Jun 2011 | 55 Francisco St | 7th fl: t.i. includes demo of non structural partitions, new non structural partitions. new or revised hvac,ele, plumb, life safety design build & submitted on separate permit. building is fully sprinkleredDetails
7th fl: t.i. includes demo of non structural partitions, new non structural partitions. new or revised hvac,ele, plumb, life safety design build & submitted on separate permit. building is fully sprinklered | $70,000 | |
| Dec 14, 2010 | Completed final sign-off Jan 2012 | 55 Francisco St | Pinnacle Wireless Usa Inc. | remove & replace 6 antennas, add gps antenna, add 6 rru's, add new 6601 rbs cabinet & add new pull box & innerductsDetails
remove & replace 6 antennas, add gps antenna, add 6 rru's, add new 6601 rbs cabinet & add new pull box & innerducts | $35,000 |
| Aug 13, 2010 | Completed final sign-off Oct 2010 | 55 Francisco St | Aeco Systems, Inc | expansion of (e) fire alarm to accomodate improvements to suite 790. work will include the installation of new ceiling horn/strobe (1) and strobes (3)Details
expansion of (e) fire alarm to accomodate improvements to suite 790. work will include the installation of new ceiling horn/strobe (1) and strobes (3) | $5,000 |
| Aug 13, 2010 | Expired or cancelled cancelled Mar 2011 | 55 Francisco St | Aeco Systems, Inc | expansion of extg fire alarm system to occomodate building improvement to suite 760 and corridors. work will include removal of extg 10" bells. 13 devicesDetails
expansion of extg fire alarm system to occomodate building improvement to suite 760 and corridors. work will include removal of extg 10" bells. 13 devices | $7,000 |
| Jul 19, 2010 | Completed final sign-off Oct 2010 | 55 Francisco St | Peacock Construction Inc | office ti onthe 7th floor. new full height and ceiling height. non struc. partitions. new elec. and lighting. new millwork, all new modified hvac. elec, plbg and life saftey under separate permit. bldg is fully sprinkleredDetails
office ti onthe 7th floor. new full height and ceiling height. non struc. partitions. new elec. and lighting. new millwork, all new modified hvac. elec, plbg and life saftey under separate permit. bldg is fully sprinklered | $60,817 |
| Jun 29, 2010 | Completed final sign-off Jul 2010 | 55 Francisco St | Cannon Constructors North Inc | reconfiguer hvac for new tenant wall lay out. deferred submittal to pa# 2010.05.05.1738. new exhaust fan, 2 new vav boxes. reduct (e) zone.Details
reconfiguer hvac for new tenant wall lay out. deferred submittal to pa# 2010.05.05.1738. new exhaust fan, 2 new vav boxes. reduct (e) zone. | $18,000 |
| Jun 9, 2010 | Completed final sign-off Jul 2010 | 55 Francisco St | Aeco Systems, Inc | 7th floor ste 700 modifications to existing fire alarm system consisting of (6) horn/strobes, (14) storbes, (20) devices total. field verify that power booster battery tests at required 7 ah.Details
7th floor ste 700 modifications to existing fire alarm system consisting of (6) horn/strobes, (14) storbes, (20) devices total. field verify that power booster battery tests at required 7 ah. | $9,000 |
| Jun 1, 2010 | Never finaled issued Jun 2010, no final | 55 Francisco St | R L H Fire Protection Inc | ti upgradde to e fire sprinkler system for stanford m cipinko 4th fl. relocate 3 heads.Details
ti upgradde to e fire sprinkler system for stanford m cipinko 4th fl. relocate 3 heads. | $900 |
| Jun 1, 2010 | Completed final sign-off Sep 2010 | 55 Francisco St | R L H Fire Protection Inc | ti upgrade of e fire sprinker system for 7th floor sio. relocate 37 heads, add 10 heads and delete 9 headsDetails
ti upgrade of e fire sprinker system for 7th floor sio. relocate 37 heads, add 10 heads and delete 9 heads | $14,100 |
| May 5, 2010 | Completed final sign-off Sep 2010 | 55 Francisco St | Cannon Constructors North Inc | 7th floor t.i. including new full height & ceiling height non-structural partitions, new electrical & lighting to accomodate new construction & new millwork. all new or modified hvac, plbg & life safety work will be designed build & submitted under separate permit.Details
7th floor t.i. including new full height & ceiling height non-structural partitions, new electrical & lighting to accomodate new construction & new millwork. all new or modified hvac, plbg & life safety work will be designed build & submitted under separate permit. | $250,000 |
| May 4, 2010 | Completed final sign-off Aug 2010 | 55 Francisco St | Peacock Construction Inc | 4th. flr. t.i. incl demo of non-struct part & build back of (n) non-struct part. all (n) or mep and l/s work will be design-build & subm for sep permit. bldg. fully sprink. field verify that outdoor deck area is for bldg use only and has signage that 'keep door locked-no tenant access'.Details
4th. flr. t.i. incl demo of non-struct part & build back of (n) non-struct part. all (n) or mep and l/s work will be design-build & subm for sep permit. bldg. fully sprink. field verify that outdoor deck area is for bldg use only and has signage that 'keep door locked-no tenant access'. | $30,000 |
| Jan 22, 2010 | Completed final sign-off May 2010 | 55 Francisco St | Mc Millan Electric | relocate (1) existing horn strobe on first floor.Details
relocate (1) existing horn strobe on first floor. | $3,000 |
| Jan 5, 2010 | Completed final sign-off May 2010 | 1777 Montgomery St | Pioneer Fire Inc. | 1st floor. relocate one pendent sprinkler.Details
1st floor. relocate one pendent sprinkler. | $2,200 |
| Dec 9, 2009 | Completed final sign-off May 2010 | 1777 Montgomery St | Novo Construction Inc | 1st floor-mechanical work for tenant improvement, architectural pa# 2009-1013-8837Details
1st floor-mechanical work for tenant improvement, architectural pa# 2009-1013-8837 | $50,000 |
| Nov 6, 2009 | Expired or cancelled expired Dec 2010 | 55 Francisco St | Pioneer Fire Inc. | 3rd floor-5 relocated pendent sprinklers, 1 removed & 1 add sprinklers. also replace 1/2" outlets in t.i. area with new 1" outletsDetails
3rd floor-5 relocated pendent sprinklers, 1 removed & 1 add sprinklers. also replace 1/2" outlets in t.i. area with new 1" outlets | $6,000 |
| Oct 13, 2009 | Completed final sign-off May 2010 | 1777 Montgomery St | Novo Construction Inc | dg fastchannel - ground floor. ti to include new tape storage room, video room, break room. no exterior work. mechanical and life safety under separate permit. electrical included.Details
dg fastchannel - ground floor. ti to include new tape storage room, video room, break room. no exterior work. mechanical and life safety under separate permit. electrical included. | $450,000 |
| Oct 9, 2009 | Completed final sign-off Jan 2010 | 55 Francisco St | Novo Construction Inc | ti on 3rd fl. new full height and clg height non struc partitions. new elect and lights to accomodate new constr., new millwork. all new or modified hvac. elec/lighting, plumbing and life safety under separate permit. building fully sprinklered.Details
ti on 3rd fl. new full height and clg height non struc partitions. new elect and lights to accomodate new constr., new millwork. all new or modified hvac. elec/lighting, plumbing and life safety under separate permit. building fully sprinklered. | $137,000 |
| Aug 3, 2009 | Never finaled issued Aug 2009, no final | 55 Francisco St | street space permit only.Details
street space permit only. | ||
| Jan 21, 2009 | Completed final sign-off Mar 2009 | 55 Francisco St | Western Allied Mechanical Inc. | (work on 55 francisco only)replace (e) water cooling tower with new cooling tower of like capacity on 1st floor. install new concrete foundation, steel support frameDetails
(work on 55 francisco only)replace (e) water cooling tower with new cooling tower of like capacity on 1st floor. install new concrete foundation, steel support frame | $50,000 |
| Jan 12, 2009 | Completed final sign-off Feb 2010 | 55 Francisco St | Transceive Communications Inc. | at&t wireless proposes to modify an (e) telecom facility. will consist of -installation of (6) rru's at (e) panel antennas & replacement of 1 (e) panel antenna located at penhouse level. removal of 1 (e) cabinet & replacement of (1) equip cabinet within (e) equip shelter, no water or sewer reqd.Details
at&t wireless proposes to modify an (e) telecom facility. will consist of -installation of (6) rru's at (e) panel antennas & replacement of 1 (e) panel antenna located at penhouse level. removal of 1 (e) cabinet & replacement of (1) equip cabinet within (e) equip shelter, no water or sewer reqd. | $5,000 |
| Sep 23, 2008 | Completed final sign-off Dec 2008 | 55 Francisco St | Corish Electric Corporation | 5th floor-expand (e) fire alarm system to tenant improvement. new work to include monitoring new 120v duct detectors (fbo) & installation of new strobe, horn strobe devices which shall be powered by an (e) fcps-24fs6 booster power supply. battery calculation, wattage drop's are included onDetails
5th floor-expand (e) fire alarm system to tenant improvement. new work to include monitoring new 120v duct detectors (fbo) & installation of new strobe, horn strobe devices which shall be powered by an (e) fcps-24fs6 booster power supply. battery calculation, wattage drop's are included on | $7,500 |
| Sep 5, 2008 | Completed final sign-off Dec 2008 | 55 Francisco St | Cannon Constructors North Inc | mechanical modifications per new tenant improvement- appl. 200807247530. add 10 ton unit for lab & heppa filters- re-configure ductwork for room wall changes.Details
mechanical modifications per new tenant improvement- appl. 200807247530. add 10 ton unit for lab & heppa filters- re-configure ductwork for room wall changes. | $123,000 |
| Aug 29, 2008 | Completed final sign-off Dec 2008 | 55 Francisco St | Cannon Constructors North Inc | 5th floor tenant improvement 200807247530. title 24 lightingDetails
5th floor tenant improvement 200807247530. title 24 lighting | $8,000 |
| Aug 25, 2008 | Completed final sign-off Dec 2008 | 55 Francisco St | R L H Fire Protection Inc | 5th fl pacific fertility: ti upgrade on the e fire sprinkler system. relocate 55 pendents, add 4 pendents.Details
5th fl pacific fertility: ti upgrade on the e fire sprinkler system. relocate 55 pendents, add 4 pendents. | $12,000 |
| Jul 24, 2008 | Completed final sign-off Dec 2008 | 55 Francisco St | 5th floor: tenant improvement including newfull height and ceiling. height-nonstructural partitions(electrical, mechanical, lifesafty and sprinklers under seperate permit) building is fully sprinkleredDetails
5th floor: tenant improvement including newfull height and ceiling. height-nonstructural partitions(electrical, mechanical, lifesafty and sprinklers under seperate permit) building is fully sprinklered | $109,758 | |
| Mar 20, 2008 | Completed final sign-off Apr 2008 | 55 Francisco St | R L H Fire Protection Inc | 3rd floor: t/i. upgrade on existing fire sprinkler system for suite 300. relocate 2 pendent heads.Details
3rd floor: t/i. upgrade on existing fire sprinkler system for suite 300. relocate 2 pendent heads. | $400 |
| Mar 14, 2008 | Completed final sign-off Apr 2008 | 55 Francisco St | Allcom Electric Inc. | 3rd floor suite 300 - tenant improvement, life safety, provide and install 3 horn/strobes & 4 strobes to existing power supply on same floor.Details
3rd floor suite 300 - tenant improvement, life safety, provide and install 3 horn/strobes & 4 strobes to existing power supply on same floor. | $4,500 |
| Jan 31, 2008 | Completed final sign-off Apr 2008 | 55 Francisco St | 3rd floor t.i. remodel existing offices- add private toilet room and utility sinks. life safety and sprinkler work under separate permits.Details
3rd floor t.i. remodel existing offices- add private toilet room and utility sinks. life safety and sprinkler work under separate permits. | $89,000 | |
| Jan 23, 2008 | Completed final sign-off Feb 2008 | 55 Francisco St | Allcom Electric Inc. | 5th floor suite 550: tenant improvement - life safety - add horn/strobes & strobes to existing power supply.Details
5th floor suite 550: tenant improvement - life safety - add horn/strobes & strobes to existing power supply. | $5,000 |
| Jan 16, 2008 | Completed final sign-off Apr 2008 | 55 Francisco St | 5th floor - remove 1-existing door frame & wing walls in the multi-tenant corridor. no increase in office space.Details
5th floor - remove 1-existing door frame & wing walls in the multi-tenant corridor. no increase in office space. | $1,200 | |
| Jan 11, 2008 | Completed final sign-off May 2008 | 55 Francisco St | R L H Fire Protection Inc | 5th floor t.i. upgrade on (e) fire sprinkler system. relocate 7 heads & add 2 heads. for pacific fertility exp. 5th floor phase ii.Details
5th floor t.i. upgrade on (e) fire sprinkler system. relocate 7 heads & add 2 heads. for pacific fertility exp. 5th floor phase ii. | $1,800 |
| Dec 21, 2007 | Completed final sign-off Feb 2008 | 55 Francisco St | office tenant improvement at the 5th floor, suite 550. mechanical and electrical work under separate permit.Details
office tenant improvement at the 5th floor, suite 550. mechanical and electrical work under separate permit. | $53,700 | |
| Dec 19, 2007 | Expired or cancelled cancelled Nov 2009 | 55 Francisco St | 7th floor-convert (e) coffee station into a new shower room. no increase in office space. fire alarm work under seperate permit.Details
7th floor-convert (e) coffee station into a new shower room. no increase in office space. fire alarm work under seperate permit. | $4,500 | |
| Nov 29, 2007 | Completed final sign-off Apr 2008 | 55 Francisco St | ground floor: install new door & door frame at the building domestic pump room.Details
ground floor: install new door & door frame at the building domestic pump room. | $1,200 | |
| Nov 15, 2007 | Completed final sign-off Aug 2008 | 55 Francisco St | Anderson, Rowe & Buckley, Inc. | 1st floor - t.i. to existing fire sprinkler system. (7) removed, (7) new.Details
1st floor - t.i. to existing fire sprinkler system. (7) removed, (7) new. | $1,400 |
| Oct 30, 2007 | Completed final sign-off Nov 2007 | 55 Francisco St | Aeco Systems, Inc | installation of new notification device(s) on 1st floor to be powered by an existing fcds-24fs6 (1 device). power supply, battery calculations and voltage drops are included on this drawings. suite 100Details
installation of new notification device(s) on 1st floor to be powered by an existing fcds-24fs6 (1 device). power supply, battery calculations and voltage drops are included on this drawings. suite 100 | $4,000 |
| Oct 17, 2007 | Completed final sign-off Nov 2007 | 55 Francisco St | Allied Heating & Air Conditioning | install mechanical system on 1st floor.Details
install mechanical system on 1st floor. | $15,000 |
| Oct 4, 2007 | Never finaled issued Oct 2007, no final | 55 Francisco St | street space permit only.Details
street space permit only. | ||
| Aug 31, 2007 | Completed final sign-off Nov 2007 | 55 Francisco St | Turner Construction Co | tenant improvement: minor demolition of interior walls new interior walls and electrical and lighting modification per new layout mechinical and lighting cal./title 24 will be on a separate permit, as well as life safety.Details
tenant improvement: minor demolition of interior walls new interior walls and electrical and lighting modification per new layout mechinical and lighting cal./title 24 will be on a separate permit, as well as life safety. | $150,000 |
| Aug 23, 2007 | Completed final sign-off Aug 2007 | 55 Francisco St | Allcom Electric Inc. | 5/f- fire alarm, remove & relocate 2 demcot, add 3 new devices.Details
5/f- fire alarm, remove & relocate 2 demcot, add 3 new devices. | $6,000 |
| Aug 8, 2007 | Completed final sign-off Aug 2007 | 55 Francisco St | Cannon Constructors North Inc | lighting for tenant improvement for new officesDetails
lighting for tenant improvement for new offices | $18,895 |
| Aug 3, 2007 | Completed final sign-off Aug 2007 | 55 Francisco St | R L H Fire Protection Inc | t.i. upgrade on (e) fire sprinkler system, for pacific fertility expansion at 5/f, relocate 17 heads & add 1 head totak 18 heads.Details
t.i. upgrade on (e) fire sprinkler system, for pacific fertility expansion at 5/f, relocate 17 heads & add 1 head totak 18 heads. | $3,600 |
| Jul 23, 2007 | Completed final sign-off Aug 2007 | 55 Francisco St | 5th floor t.i. sprinkler, life safety, mechanical, and electrical under seperate permit.Details
5th floor t.i. sprinkler, life safety, mechanical, and electrical under seperate permit. | $106,000 | |
| Aug 23, 2006 | Completed final sign-off Sep 2006 | 55 Francisco St | renew expired appl#200508150249 for final inspection.Details
renew expired appl#200508150249 for final inspection. | ||
| Aug 8, 2006 | Completed final sign-off Aug 2006 | 55 Francisco St | Aeco Systems, Inc | renew application #200408202101 for final inspection.Details
renew application #200408202101 for final inspection. | |
| Oct 27, 2005 | Expired or cancelled withdrawn May 2015 | 55 Francisco St | horizontal addition. new construction of 51 residential units on 3 stories over (e) 3 story parking garage, for a total of 6 stories. no work at the (e) office building.Details
horizontal addition. new construction of 51 residential units on 3 stories over (e) 3 story parking garage, for a total of 6 stories. no work at the (e) office building. | $2,000,000 | |
| Sep 26, 2005 | Completed final sign-off Jun 2006 | 55 Francisco St | Cannon Constructors North Inc | oti-2, 2nd fl - el,me, ls.Details
oti-2, 2nd fl - el,me, ls. | $120,000 |
| Sep 22, 2005 | Completed final sign-off Oct 2005 | 55 Francisco St | Cannon Constructors North Inc | renew expired permit for final inspection. pa# 2003/03/10/9196 & pa# 2002/12/13/3489.Details
renew expired permit for final inspection. pa# 2003/03/10/9196 & pa# 2002/12/13/3489. | |
| Sep 14, 2005 | Completed final sign-off Oct 2005 | 55 Francisco St | Cannon Constructors North Inc | renew pa 200308121816-200212134084-200212133492Details
renew pa 200308121816-200212134084-200212133492 | |
| Sep 14, 2005 | Completed final sign-off Nov 2005 | 55 Francisco St | Dpw Inc. | modify extg sprinkler system for new walls and new tiban ceiiling on 2nd floor onlyDetails
modify extg sprinkler system for new walls and new tiban ceiiling on 2nd floor only | $20,000 |
| Sep 9, 2005 | Completed final sign-off Oct 2005 | 55 Francisco St | Cannon Constructors North Inc | renew 200302278417,200303129440,200210179207Details
renew 200302278417,200303129440,200210179207 | |
| Aug 25, 2005 | Completed final sign-off Aug 2005 | 55 Francisco St | Cannon Constructors North Inc | renew for final only 200209207079Details
renew for final only 200209207079 | |
| Aug 24, 2005 | Completed final sign-off Sep 2005 | 55 Francisco St | Cannon Constructors North Inc | for final 200209207075Details
for final 200209207075 | |
| Aug 24, 2005 | Completed final sign-off Sep 2005 | 55 Francisco St | Cannon Constructors North Inc | for final inspection 200308121813Details
for final inspection 200308121813 | |
| Aug 24, 2005 | Completed final sign-off Aug 2005 | 55 Francisco St | Cannon Constructors North Inc | renew expired permit 200207252296 for final inspectionDetails
renew expired permit 200207252296 for final inspection | |
| Aug 15, 2005 | Expired or cancelled expired Sep 2006 | 55 Francisco St | 2nd floor tenant improvements- revision to apprvd plans -ref 200506296341- existing ramp at west lobby at bldg column to remain at 3-8 clr.Details
2nd floor tenant improvements- revision to apprvd plans -ref 200506296341- existing ramp at west lobby at bldg column to remain at 3-8 clr. | ||
| Aug 12, 2005 | Completed final sign-off Nov 2005 | 55 Francisco St | oti-1, 2nd floor, el, me, ls, spDetails
oti-1, 2nd floor, el, me, ls, sp | $108,203 | |
| Aug 10, 2005 | Completed final sign-off Aug 2005 | 55 Francisco St | Cannon Constructors North Inc | revision to pa# 2002/09/20/7079. delete (2) five smoke dampos @ grid line 5. sheet sky.Details
revision to pa# 2002/09/20/7079. delete (2) five smoke dampos @ grid line 5. sheet sky. | |
| Aug 8, 2005 | Completed final sign-off Nov 2005 | 55 Francisco St | Dpw Inc. | modify (e)sprinkler system for new walls and (e)t-bar ceiling removalDetails
modify (e)sprinkler system for new walls and (e)t-bar ceiling removal | $5,000 |
| Aug 2, 2005 | Completed final sign-off Nov 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-2, 2nd floor, el, me, ls.Details
oti-2, 2nd floor, el, me, ls. | $19,000 |
| Jun 29, 2005 | Completed final sign-off Nov 2005 | 55 Francisco St | oti-1 2/f el,me,ls,spDetails
oti-1 2/f el,me,ls,sp | $50,000 | |
| May 23, 2005 | Completed final sign-off Jun 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-2 3rd fl l/sDetails
oti-2 3rd fl l/s | $9,800 |
| May 13, 2005 | Completed final sign-off Jun 2005 | 55 Francisco St | Dpw Inc. | modify existing sprinkler system for new walls and ceiling also upgrade e standard response head toDetails
modify existing sprinkler system for new walls and ceiling also upgrade e standard response head to | $5,000 |
| Mar 31, 2005 | Completed final sign-off Jun 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-1,3rd/fl-me, ls,sp.Details
oti-1,3rd/fl-me, ls,sp. | $45,000 |
| Mar 25, 2005 | Expired or cancelled cancelled Dec 2006 | 55 Francisco St | construction approx 9 ft of ceiling ht. partition wall will be relocated with door. sprinklersDetails
construction approx 9 ft of ceiling ht. partition wall will be relocated with door. sprinklers | $3,000 | |
| Nov 22, 2004 | Completed final sign-off Mar 2005 | 55 Francisco St | Aeco Systems, Inc | expand (e) fire alarm system to include - 4 strobes, 4 horn strobes to accomodate tenant improvementDetails
expand (e) fire alarm system to include - 4 strobes, 4 horn strobes to accomodate tenant improvement | $6,800 |
| Nov 5, 2004 | Completed final sign-off Mar 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-2, 3rd floor, meDetails
oti-2, 3rd floor, me | $8,100 |
| Oct 27, 2004 | Completed final sign-off May 2005 | 55 Francisco St | Dpw Inc. | relocae 8 sprinkler heads and plug off 7 and add 1 new for new 3rd fl t.i. work only.Details
relocae 8 sprinkler heads and plug off 7 and add 1 new for new 3rd fl t.i. work only. | $3,800 |
| Oct 7, 2004 | Completed final sign-off Mar 2005 | 55 Francisco St | oti-1,3rd /fl-me,ls, sp.Details
oti-1,3rd /fl-me,ls, sp. | $22,500 | |
| Aug 20, 2004 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Aeco Systems, Inc | modifications to extg fire alarm system due to tenant improvementDetails
modifications to extg fire alarm system due to tenant improvement | $10,000 |
| Jul 20, 2004 | Completed final sign-off Aug 2004 | 55 Francisco St | Cannon Constructors North Inc | oti 2 , 3rd floor; l/sDetails
oti 2 , 3rd floor; l/s | $13,000 |
| Jul 20, 2004 | Completed final sign-off Aug 2004 | 55 Francisco St | Cannon Constructors North Inc | tenant improvement- rev to appd plns ref app 200406095928-relocate demising partition, no increase iDetails
tenant improvement- rev to appd plns ref app 200406095928-relocate demising partition, no increase i | $1,000 |
| Jul 15, 2004 | Completed final sign-off Aug 2004 | 55 Francisco St | Dpw Inc. | add and relocate sprinkler heads for new walls and ceilings on 3rd fl only no increase in office spaDetails
add and relocate sprinkler heads for new walls and ceilings on 3rd fl only no increase in office spa | $5,000 |
| Jun 9, 2004 | Completed final sign-off Aug 2004 | 55 Francisco St | Cannon Constructors North Inc | oti-1, 3rd fl. - el, sp, me, lsDetails
oti-1, 3rd fl. - el, sp, me, ls | $36,500 |
| Jun 3, 2004 | Completed final sign-off Oct 2004 | 55 Francisco St | renew expired pemit applic. #2003/08/12/1815 - work not startedDetails
renew expired pemit applic. #2003/08/12/1815 - work not started | $12,000 | |
| Aug 12, 2003 | Expired or cancelled expired Oct 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-1 ,4th flrDetails
oti-1 ,4th flr | $9,500 |
| Aug 12, 2003 | Expired or cancelled expired Oct 2004 | 55 Francisco St | Cannon Constructors North Inc | oti-1, 3rd flrDetails
oti-1, 3rd flr | $12,000 |
| Aug 12, 2003 | Expired or cancelled expired Oct 2005 | 55 Francisco St | Cannon Constructors North Inc | oti-1 3rd flrDetails
oti-1 3rd flr | $14,000 |
| Mar 12, 2003 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | mechanical work on 4th fl. no increase in office space per 200210179207.Details
mechanical work on 4th fl. no increase in office space per 200210179207. | $8,800 |
| Mar 10, 2003 | Expired or cancelled expired Jan 2005 | 55 Francisco St | construct partition to split existing full floor space into sublease space- 2 total (no increase inDetails
construct partition to split existing full floor space into sublease space- 2 total (no increase in | $12,500 | |
| Feb 27, 2003 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti -2 4th fl le, spDetails
oti -2 4th fl le, sp | $5,180 |
| Feb 27, 2003 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti -3= 4th fl. el, l/s, spDetails
oti -3= 4th fl. el, l/s, sp | $3,500 |
| Dec 23, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti-1 5/f elDetails
oti-1 5/f el | $22,500 |
| Dec 13, 2002 | Expired or cancelled expired Jan 2005 | 55 Francisco St | oti-1 5th floorDetails
oti-1 5th floor | $12,000 | |
| Dec 13, 2002 | Expired or cancelled expired Jan 2005 | 55 Francisco St | oti-1 4th floor- no increase in office spaceDetails
oti-1 4th floor- no increase in office space | $4,500 | |
| Dec 11, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Ayoob & Peery Plumbing Co Inc | relocate 10 fire sprinkler and remove 4 per tenant improvement on 4th fl.Details
relocate 10 fire sprinkler and remove 4 per tenant improvement on 4th fl. | $1,850 |
| Oct 17, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | oti-1, 4th flr,el,me,ls,spDetails
oti-1, 4th flr,el,me,ls,sp | $17,500 | |
| Sep 20, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti-2 4th floor elDetails
oti-2 4th floor el | $4,900 |
| Sep 20, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti-2 4th floor el,me,sp suite 430Details
oti-2 4th floor el,me,sp suite 430 | $11,500 |
| Aug 19, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | oti-1 4th floor, el, lsDetails
oti-1 4th floor, el, ls | $22,000 | |
| Jul 25, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | oti-1 4/f el me ls spDetails
oti-1 4/f el me ls sp | $40,000 | |
| Jul 3, 2002 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | oti-1,4th flr elDetails
oti-1,4th flr el | $40,000 |
| Feb 15, 2002 | Expired or cancelled expired Jan 2003 | 55 Francisco St | Aeco Systems, Inc | new booster panel, add 19 horn/strobes and 13 strobesDetails
new booster panel, add 19 horn/strobes and 13 strobes | $20,000 |
| Jan 30, 2002 | Expired or cancelled expired Jan 2003 | 55 Francisco St | Dpw Inc. | t.i. work on 6th floor per approved sprinkler plans 14 new/ 15 plug and 57 relocate 6th floorDetails
t.i. work on 6th floor per approved sprinkler plans 14 new/ 15 plug and 57 relocate 6th floor | $10,000 |
| Jan 4, 2002 | Completed final sign-off Sep 2002 | 55 Francisco St | 5/fl.- demo partition wall, build new partition as shown, lower kitchen sink to comply with adaDetails
5/fl.- demo partition wall, build new partition as shown, lower kitchen sink to comply with ada | $10,000 | |
| Jan 4, 2002 | Completed final sign-off Sep 2002 | 55 Francisco St | 6/fl.- demo partition wall, construct new partition wall, change kitchen cabinet/counter topDetails
6/fl.- demo partition wall, construct new partition wall, change kitchen cabinet/counter top | $200,000 | |
| Sep 25, 2001 | Completed final sign-off Nov 2001 | 55 Francisco St | replace exist suspend ceiling with new 2x2 ceiling. build 1-hr rated partition.Details
replace exist suspend ceiling with new 2x2 ceiling. build 1-hr rated partition. | $2,500 | |
| Aug 29, 2001 | Expired or cancelled expired Oct 2001 | 55 Francisco St | renewal app#200010304356 for final inspection onlyDetails
renewal app#200010304356 for final inspection only | ||
| Jul 30, 2001 | Completed final sign-off Nov 2001 | 55 Francisco St | construct new ceiling at the building entry from parking garageDetails
construct new ceiling at the building entry from parking garage | $1,700 | |
| Jun 29, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | renewal of pa#200005038906Details
renewal of pa#200005038906 | ||
| Jun 29, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | renewal of pa#200003285536Details
renewal of pa#200003285536 | ||
| Jun 29, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | renewal of pa#200005119745Details
renewal of pa#200005119745 | ||
| Jun 29, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | renewal of pa#200006011531Details
renewal of pa#200006011531 | ||
| Jun 29, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | renewal of pa#200003245360Details
renewal of pa#200003245360 | ||
| Jun 4, 2001 | Completed final sign-off Aug 2001 | 55 Francisco St | demolition of int partitions only, work does not affect life safety or structure of bldgnDetails
demolition of int partitions only, work does not affect life safety or structure of bldgn | $12,000 | |
| Jun 4, 2001 | Completed final sign-off Aug 2001 | 55 Francisco St | barrier removal-install accessible hi-low drinking fountain, rework stall door in womens toilet roomDetails
barrier removal-install accessible hi-low drinking fountain, rework stall door in womens toilet room | $3,000 | |
| Mar 22, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | Geo M Robinson & Co | as built 200101260698 minor revisn to sprklr system actual pipe sizes now shown relocat heads rm 114Details
as built 200101260698 minor revisn to sprklr system actual pipe sizes now shown relocat heads rm 114 | |
| Mar 22, 2001 | Completed final sign-off Mar 2002 | 55 Francisco St | Park Place Contractors | one-stop:m.tjoe:install antennas on the roof of the telecom bldg.Details
one-stop:m.tjoe:install antennas on the roof of the telecom bldg. | $70,000 |
| Mar 20, 2001 | Expired or cancelled expired Jan 2003 | 55 Francisco St | Gregory Michael Brazil | add microwave dish to exist penthouse.Details
add microwave dish to exist penthouse. | $12,000 |
| Mar 16, 2001 | Expired or cancelled expired Oct 2006 | 55 Francisco St | Cannon Constructors North Inc | renew expired pa#9917365 for final sign off-all work has been completedDetails
renew expired pa#9917365 for final sign off-all work has been completed | |
| Feb 20, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | Decker Electric Co Inc Electrical Contra | add 2 smoke detectors, 1 dull station, 8 storage & 2 horo/storbes to the (e) f/a system on 1/flDetails
add 2 smoke detectors, 1 dull station, 8 storage & 2 horo/storbes to the (e) f/a system on 1/fl | $5,000 |
| Feb 15, 2001 | Expired or cancelled expired Jun 2001 | 55 Francisco St | rev. to approved pa#2000/12/11/7650-fill holes in (e) concrete floorDetails
rev. to approved pa#2000/12/11/7650-fill holes in (e) concrete floor | $1,000 | |
| Jan 26, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | Geo M Robinson & Co | alteration to existing springler system tenant improvements at 1st floor locationDetails
alteration to existing springler system tenant improvements at 1st floor location | $9,307 |
| Jan 25, 2001 | Completed final sign-off Jul 2001 | 55 Francisco St | oti-2 ground floor lighting, mechDetails
oti-2 ground floor lighting, mech | $105,000 | |
| Jan 25, 2001 | Expired or cancelled withdrawn Apr 2001 | 55 Francisco St | oti-1 7th floor ltg, l/s, sprklerDetails
oti-1 7th floor ltg, l/s, sprkler | $65,000 | |
| Jan 12, 2001 | Completed final sign-off May 2001 | 55 Francisco St | install handicap accssble drinking fntn;relocate (e)door to provide clearanceDetails
install handicap accssble drinking fntn;relocate (e)door to provide clearance | $1,700 | |
| Dec 21, 2000 | Expired or cancelled expired Apr 2001 | 55 Francisco St | Dpr Construction Inc | demolition only: floor covering, abandoned conduit, walls, abanooned ductworkDetails
demolition only: floor covering, abandoned conduit, walls, abanooned ductwork | $1,000 |
| Dec 11, 2000 | Completed final sign-off Jul 2001 | 55 Francisco St | oti-1 1st floor el me spr lsDetails
oti-1 1st floor el me spr ls | $250,000 | |
| Nov 15, 2000 | Completed final sign-off Mar 2001 | 55 Francisco St | Cannon Constructors North Inc | oti-2, ground floor, sp onlyDetails
oti-2, ground floor, sp only | $3,500 |
| Oct 30, 2000 | Expired or cancelled expired Oct 2001 | 55 Francisco St | construct 3 offices no elec/mech relocate elec fix only sprnkler plans under sep permitDetails
construct 3 offices no elec/mech relocate elec fix only sprnkler plans under sep permit | $20,000 | |
| Oct 30, 2000 | Completed final sign-off Feb 2001 | 55 Francisco St | remove (e) driveway (n) curb to match existingDetails
remove (e) driveway (n) curb to match existing | $2,000 | |
| Jun 20, 2000 | Completed final sign-off Feb 2001 | 55 Francisco St | revision to #20000118242 &200003245360 close off (e) stairwell from ground lel to 5th fl.Details
revision to #20000118242 &200003245360 close off (e) stairwell from ground lel to 5th fl. | $17,500 | |
| Jun 7, 2000 | Expired or cancelled expired Oct 2000 | 1777 Montgomery St | address assignmentDetails
address assignment | ||
| Jun 1, 2000 | Expired or cancelled expired Mar 2001 | 55 Francisco St | revision to app #200003245360Details
revision to app #200003245360 | $3,000 | |
| May 11, 2000 | Expired or cancelled expired Sep 2000 | 55 Francisco St | light hazard pipe scheduleDetails
light hazard pipe schedule | ||
| May 3, 2000 | Expired or cancelled expired Mar 2001 | 55 Francisco St | Decker Electric Co Inc Electrical Contra | t.i. /new intiiation devisesDetails
t.i. /new intiiation devises | $24,000 |
| Mar 28, 2000 | Completed final sign-off Jul 2001 | 55 Francisco St | oti-2, 1st floor, el, meDetails
oti-2, 1st floor, el, me | $175,000 | |
| Mar 24, 2000 | Expired or cancelled expired Apr 2001 | 55 Francisco St | oti-1, el, me, ls, sp, ground floorDetails
oti-1, el, me, ls, sp, ground floor | $250,000 | |
| Jan 31, 2000 | Expired or cancelled cancelled Jan 2000 | 55 Francisco St | revision to plan 9917365Details
revision to plan 9917365 | $40,000 | |
| Jan 18, 2000 | Completed final sign-off Mar 2001 | 55 Francisco St | seismic accessibility upgradesDetails
seismic accessibility upgrades | $70,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Cannon Constructors North Inc (35), Aeco Systems, Inc (9), Dpw Inc. (6), R L H Fire Protection Inc (6), Pioneer Fire Inc. (5), Allcom Electric Inc. (4), Carter Brothers Fire & Life Safety (3), Novo Construction Inc (3), Peacock Construction Inc (3), Decker Electric Co Inc Electrical Contra (2), Geo M Robinson & Co (2), Aegis Enterprises Inc, Allied Heating & Air Conditioning, Anderson, Rowe & Buckley, Inc., Aquamatic Fire Protection, Ayoob & Peery Plumbing Co Inc, Corish Electric Corporation, D A Pope Inc, Dpr Construction Inc, Gregory Michael Brazil, H C I Systems Inc, Mc Millan Electric, Park Place Contractors, Pinnacle Wireless Usa Inc., Transceive Communications Inc., Turner Construction Co, Western Allied Mechanical Inc.
- Architects
- Ken Eng (5), Hooksasd Hooks Asd (2), Ken Eng (2), Bjorn Steuete, Ken Eng, Robert Hayes, Robin Mcdonald, Sternberg Benjamin Architects
- Engineers
- Aston Pereira
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.