Block 0019, lot 001
151 Beach St
- City’s use
- Commercial Misc
- Built
- 1900
- Stories
- 1
- Units
- 1
- Rooms
- 4 bathrooms
- Building
- 11,640 sq ft
- Lot
- 113,430 sq ft
- Zoning
- P
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
16 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 13, 2022 | Never finaled issued Oct 2022, no final | 151 Beach St | Pacific Auxiliary Fire Alarm | fire alarm ti: adding (1) cellular communicator to existing notifier nfs-320 fire alary system.Details
fire alarm ti: adding (1) cellular communicator to existing notifier nfs-320 fire alary system. | |
| Jan 3, 2019 | Never finaled issued Jan 2019, no final | 151 Beach St | street space/mta metersDetails
street space/mta meters | ||
| Nov 27, 2018 | Never finaled issued Nov 2018, no final | 151 Beach St | street spaceDetails
street space | ||
| Sep 11, 2018 | Completed final sign-off May 2019 | 151 Beach St | Pilot Construction Management Inc | installation of electrical system for veeder root, communication and fueling dispensers. reference p.a. # 2017 0213 9309Details
installation of electrical system for veeder root, communication and fueling dispensers. reference p.a. # 2017 0213 9309 | $25,000 |
| Apr 17, 2018 | Completed final sign-off May 2019 | 151 Beach St | Pilot Construction Management Inc | revision to 201702139309. install dual piping fueling system instead of single piping fueling system. maher naDetails
revision to 201702139309. install dual piping fueling system instead of single piping fueling system. maher na | $400,000 |
| Apr 12, 2018 | Never finaled issued Apr 2018, no final | 151 Beach St | street spaceDetails
street space | ||
| Oct 18, 2017 | Never finaled issued Oct 2017, no final | 151 Beach St | street space w/mtaDetails
street space w/mta | ||
| May 18, 2017 | Completed final sign-off May 2019 | 151 Beach St | Balch Petroleum Contractors & Builders, Pilot Construction Management Inc | temporary shoring and excavation. ref 2017-0213-9309, construction 24" concrete hydrocap. maher applicable > 50 yrdsDetails
temporary shoring and excavation. ref 2017-0213-9309, construction 24" concrete hydrocap. maher applicable > 50 yrds | $300,000 |
| Apr 7, 2017 | Completed final sign-off May 2017 | 151 Beach St | Ces Controlled Environmental Services | relocation of one (1) existing diesel fuel dispenser #6 from under canopy to outside in tank enclosed area due prep for future tank and dispenser upgrade work in 2018, associated plumbing/wiring. n/a ordinance #155-13Details
relocation of one (1) existing diesel fuel dispenser #6 from under canopy to outside in tank enclosed area due prep for future tank and dispenser upgrade work in 2018, associated plumbing/wiring. n/a ordinance #155-13 | $25,000 |
| Apr 5, 2017 | Never finaled issued Apr 2017, no final | 151 Beach St | street space prmitDetails
street space prmit | ||
| Feb 13, 2017 | Completed final sign-off May 2019 | 151 Beach St | Pilot Construction Management Inc | remove 2 (e) 20,000 gal single wall ust and (e) fuel dispensers #4-#6. instlal 2 (n) 20,000 gal double wall ust (diesel fuel supply) with new dispensers #7-#9, and new tank monitoring system/leak detection. ** maher: disturbance of at least 50 cu.yd. of soil; route to dph **Details
remove 2 (e) 20,000 gal single wall ust and (e) fuel dispensers #4-#6. instlal 2 (n) 20,000 gal double wall ust (diesel fuel supply) with new dispensers #7-#9, and new tank monitoring system/leak detection. ** maher: disturbance of at least 50 cu.yd. of soil; route to dph ** | $2,681,498 |
| Feb 8, 2017 | Expired or cancelled cancelled Sep 2023 | 2301 Stockton St | Ces Controlled Environmental Services | relocate (e) 8,000 gal. ast empty & disconnect (e) 8,000 gallon above ground diesel storage tank. construct new concrete foundation tank pad with crash bollards. extend (e) fuel piping to new ast location. reinstall 8,000 gallon ast on new concrete foundation pad in new location.Details
relocate (e) 8,000 gal. ast empty & disconnect (e) 8,000 gallon above ground diesel storage tank. construct new concrete foundation tank pad with crash bollards. extend (e) fuel piping to new ast location. reinstall 8,000 gallon ast on new concrete foundation pad in new location. | $60,000 |
| Dec 28, 2016 | Completed final sign-off Mar 2020 | 151 Beach St | Intrepid Electronic Systems Inc | demolish (e) fire alarm control units, devices and fire alarm cabling. provide new fire alarm control units, devices and fire alarm cabling per nfpa 72.Details
demolish (e) fire alarm control units, devices and fire alarm cabling. provide new fire alarm control units, devices and fire alarm cabling per nfpa 72. | $95,074 |
| Jul 21, 2015 | Completed final sign-off Apr 2016 | 151 Beach St | Champion Telecom Inc | add breaker to extg electrical panel. run electrical lines in conduit to dis server. install small antennas on bldg and ballast mount on roof. run fiber optic, coaxal dc cable with sleepers on rooftop. n/a for maher.Details
add breaker to extg electrical panel. run electrical lines in conduit to dis server. install small antennas on bldg and ballast mount on roof. run fiber optic, coaxal dc cable with sleepers on rooftop. n/a for maher. | $20,000 |
| Sep 9, 2011 | Completed final sign-off Dec 2011 | 151 Beach St | Ces Controlled Environmental Services | remove and replace 5 gallon deisel fuel spill buckets on two - 20,000 gallon tanks, concrete and rebar.Details
remove and replace 5 gallon deisel fuel spill buckets on two - 20,000 gallon tanks, concrete and rebar. | $25,396 |
| Apr 21, 2004 | Expired or cancelled cancelled Mar 2007 | 151 Beach St | Ces Controlled Environmental Services | alterrations to (e) diesel fuel piping from underground storage tanks to dispensers, install new 3"Details
alterrations to (e) diesel fuel piping from underground storage tanks to dispensers, install new 3" | $18,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Ces Controlled Environmental Services (4), Pilot Construction Management Inc (4), Balch Petroleum Contractors & Builders, Champion Telecom Inc, Intrepid Electronic Systems Inc, Pacific Auxiliary Fire Alarm
- Engineers
- John Matthew Becker (2), Christopher Richard, Farokh Pirrmand, Julian White, Lang Huey
Find contractors for work like this