Farokh Pirrmand
- Listed as
- engineer
- Firm
- Sf - Dpw
- On San Francisco permits
- Jan 2016 to Mar 2021
6 permits since 2000 (engineer on 6 permits): 5 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 31, 2021 | Never finaled issued Apr 2022, no final | 1095 Indiana St | demolition and replacement of the existing bus wash equipment and its reclamation system, including the trench drains and the concrete floor in the bus wash building.Details
demolition and replacement of the existing bus wash equipment and its reclamation system, including the trench drains and the concrete floor in the bus wash building. | $3,800,000 | |
| Feb 13, 2017 | Completed final sign-off May 2021 | 1849 Harrison St | Mitchell Engineering, Pilot Construction Management Inc | remove 2 waste tank system located on underground concrete valut, remove fuel 1,000 gallon above ground tanks in mechanical room, 5 (n) aboveground tanks ul 142, new hose reels, pumps, equipment & piping installed in mechanical room. n/a ordinance #155-13Details
remove 2 waste tank system located on underground concrete valut, remove fuel 1,000 gallon above ground tanks in mechanical room, 5 (n) aboveground tanks ul 142, new hose reels, pumps, equipment & piping installed in mechanical room. n/a ordinance #155-13 | $1,742,974 |
| Feb 13, 2017 | Completed final sign-off May 2019 | 151 Beach St | Pilot Construction Management Inc | remove 2 (e) 20,000 gal single wall ust and (e) fuel dispensers #4-#6. instlal 2 (n) 20,000 gal double wall ust (diesel fuel supply) with new dispensers #7-#9, and new tank monitoring system/leak detection. ** maher: disturbance of at least 50 cu.yd. of soil; route to dph **Details
remove 2 (e) 20,000 gal single wall ust and (e) fuel dispensers #4-#6. instlal 2 (n) 20,000 gal double wall ust (diesel fuel supply) with new dispensers #7-#9, and new tank monitoring system/leak detection. ** maher: disturbance of at least 50 cu.yd. of soil; route to dph ** | $2,681,498 |
| Feb 13, 2017 | Completed final sign-off May 2019 | 1940 Harrison St | Pilot Construction Management Inc | remove 2 waste tank system located in an underground concrete vault wall, replace with two new double walled above ground tank system and new tank monitoring system. ul142 n/a ordinance #155-13Details
remove 2 waste tank system located in an underground concrete vault wall, replace with two new double walled above ground tank system and new tank monitoring system. ul142 n/a ordinance #155-13 | $958,524 |
| Jan 25, 2016 | Completed final sign-off Jul 2020 | 4 Guy Pl | Azul Works, Inc. | erect a type-3, vine columns in public park.Details
erect a type-3, vine columns in public park. | $150,000 |
| Jan 25, 2016 | Completed final sign-off Jul 2020 | 4 Guy Pl | Azul Works, Inc. | grading permit. 232 lf of retaining wal on all sides of site. max height of retaining wall is 11'6". site to made level with engineered fill.Details
grading permit. 232 lf of retaining wal on all sides of site. max height of retaining wall is 11'6". site to made level with engineered fill. | $300,000 |