Michael Hennessey
- Listed as
- architect, authorized agent-others
- Firm
- Michael Hennessey Architecture
- Based in
- San Francisco
- On San Francisco permits
- Dec 2008 to Sep 2026
44 permits since 2000 (architect on 44 permits, authorized agent-others on 1 permit): 31 completed, 5 in progress, 2 never finaled, 6 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 28, 2026 | In progress filed Sep 2026, not yet issued | 67 Everson St | A L Martin Construction | renovate (e) 2 story house. provide veritcal addition above (e) residence. convert part of (e) basement into new adu. new windows & finishes throughout. new deck at rear yard. new open fence at front yard. seismic upgrade & new fire sprinkler system throughout.Details
renovate (e) 2 story house. provide veritcal addition above (e) residence. convert part of (e) basement into new adu. new windows & finishes throughout. new deck at rear yard. new open fence at front yard. seismic upgrade & new fire sprinkler system throughout. | $1,194,404 |
| Sep 3, 2025 | Completed final sign-off Aug 2026 | 1409 20th St | Mueller Nicholls Inc | existing kitchen and bathrooms to be renovated. provide cathedral ceiling at living room and kitchen space, within the existing building envelope. provide new windows and doors at rear elevation. existing deck and ext stair to be repaired, less than 50%.Details
existing kitchen and bathrooms to be renovated. provide cathedral ceiling at living room and kitchen space, within the existing building envelope. provide new windows and doors at rear elevation. existing deck and ext stair to be repaired, less than 50%. | $298,290 |
| Apr 28, 2025 | Completed final sign-off May 2025 | 1336 Chestnut St | revision to addendum of 202007290911: remove property line window & private elevator from plansDetails
revision to addendum of 202007290911: remove property line window & private elevator from plans | ||
| Oct 31, 2024 | In progress issued Aug 2025 | 110 Alpine Tr | A L Martin Construction | project provides a renovation, vertical & horizontal addition to an (e) single family. new detached garage will be provided.Details
project provides a renovation, vertical & horizontal addition to an (e) single family. new detached garage will be provided. | $505,050 |
| Oct 31, 2024 | In progress issued Aug 2025 | 110 Alpine Tr | A L Martin Construction | to erect 1 story, type v-b, detach garage.Details
to erect 1 story, type v-b, detach garage. | $126,262 |
| Aug 8, 2024 | In progress issued Oct 2024 | 2500 Steiner St | D V Rasmussen & Son Inc. | an existing roof patio space is to be renovated to include a shared patio & garden (590 sqft) & a private patio(160 s.f.) at the podium level of a multi-family residential bldg. work at the renovated patios is to include steel trellis structures with wood lattice infill, percelain pavers,Details
an existing roof patio space is to be renovated to include a shared patio & garden (590 sqft) & a private patio(160 s.f.) at the podium level of a multi-family residential bldg. work at the renovated patios is to include steel trellis structures with wood lattice infill, percelain pavers, | $150,000 |
| May 13, 2024 | Completed final sign-off Apr 2025 | 2500 Steiner St | Mueller Nicholls Inc | renovation to single apartment high rise res building. new powder room, existing baths to be remodeled, kitchen to be remodeled, laundry room to be remodled, new lighting througout, e windows to be refurbished for proper function. new windows and new door with transomo at north wall, not visibleDetails
renovation to single apartment high rise res building. new powder room, existing baths to be remodeled, kitchen to be remodeled, laundry room to be remodled, new lighting througout, e windows to be refurbished for proper function. new windows and new door with transomo at north wall, not visible | $300,000 |
| Jul 21, 2023 | In progress issued Apr 2024 | 377 Santa Ana Av | Ventana 76, A L Martin Construction | renovation of detached, single-family residence to include: - raising the second floor level to accommodate a new roof deck; - new primary closet, work area and laundry addition at second floor; - new raised patio at first floor; - new partition walls for new bathroom and kitchen.Details
renovation of detached, single-family residence to include: - raising the second floor level to accommodate a new roof deck; - new primary closet, work area and laundry addition at second floor; - new raised patio at first floor; - new partition walls for new bathroom and kitchen. | $574,719 |
| Aug 12, 2022 | Expired or cancelled cancelled Jan 2026 | 82 Cameo Wy | A L Martin Construction | renovation of existing kid's bathroom. replacement of exterior wood siding in kind. provide new front gate, fence and courtyard paving. replacement of front facing windows in existing opening. new paint at existing flashing, vents, and flues. new front facing sconce.Details
renovation of existing kid's bathroom. replacement of exterior wood siding in kind. provide new front gate, fence and courtyard paving. replacement of front facing windows in existing opening. new paint at existing flashing, vents, and flues. new front facing sconce. | $53,868 |
| Jun 1, 2022 | Expired or cancelled expired Jul 2024 | 225 Amber Dr | A L Martin Construction | revision to pa# 201703131293 s1. structural drawing for concrete landscape planters. retaining wall at hot tub. new garden shed. main stair revisions, and new footing at existing retaining wall.Details
revision to pa# 201703131293 s1. structural drawing for concrete landscape planters. retaining wall at hot tub. new garden shed. main stair revisions, and new footing at existing retaining wall. | $25,000 |
| Aug 24, 2020 | Expired or cancelled withdrawn Apr 2021 | 1500 Mission St | single-story bottle shop fit-out of an existing retail space. existing building is a recently complete multi-family residential project. the bottle shop is located on g/f in the north corner of existing building for occasional wine/drink tasting in this spacee.Details
single-story bottle shop fit-out of an existing retail space. existing building is a recently complete multi-family residential project. the bottle shop is located on g/f in the north corner of existing building for occasional wine/drink tasting in this spacee. | $37,389 | |
| Aug 21, 2020 | Never finaled issued Sep 2021, no final | 1434 Dolores St | A L Martin Construction | vertical addition containing new master suite at 3rd flr. horizontal addition at rear of 1st flr. provide new stair at front of building and new deck at rear of building. provide seismic upgrade and new fire sprinkler system throughout (sprinkler on separate submittal).Details
vertical addition containing new master suite at 3rd flr. horizontal addition at rear of 1st flr. provide new stair at front of building and new deck at rear of building. provide seismic upgrade and new fire sprinkler system throughout (sprinkler on separate submittal). | $483,836 |
| Aug 20, 2020 | Completed final sign-off Jul 2022 | 350 Winfield St | relocate power room, provide (2) rear new alum windows. provide (n) shearwalls at rear elevation. revision to pa# 202001313304Details
relocate power room, provide (2) rear new alum windows. provide (n) shearwalls at rear elevation. revision to pa# 202001313304 | $5,000 | |
| Jul 29, 2020 | Completed final sign-off May 2025 | 1336 Chestnut St | to erect 4 stories, no basement, type v-a, 3 units apartments.Details
to erect 4 stories, no basement, type v-a, 3 units apartments. | $1,696,689 | |
| Jul 18, 2020 | Completed final sign-off Nov 2023 | 1336 Chestnut St | to demolish a type v-b, 2-story single family residence with no basements.Details
to demolish a type v-b, 2-story single family residence with no basements. | $17,262 | |
| Jun 17, 2019 | Completed final sign-off Aug 2021 | 2500 Steiner St | Dowbuilt Inc. | apt #5: renovation of an extg apartment within the highrise residential bldg. nw interior partition walls to be provided for nw bathrooms, 2 additional bedrooms, a study, and louge area. nw finishes and fixtures throughout. new window to match (e) wood double hung windows.Details
apt #5: renovation of an extg apartment within the highrise residential bldg. nw interior partition walls to be provided for nw bathrooms, 2 additional bedrooms, a study, and louge area. nw finishes and fixtures throughout. new window to match (e) wood double hung windows. | $837,002 |
| Mar 4, 2019 | Completed final sign-off Oct 2020 | 2835 Vallejo St | The Fine European Construction/Uwb Dober | erect a 1-story, type 5b, detached garage bldg.Details
erect a 1-story, type 5b, detached garage bldg. | $101,704 |
| Mar 4, 2019 | Never finaled issued Nov 2019, no final | 2835 Vallejo St | The Fine European Construction/Uwb Dober | demolish (e) 1-story, type 5b, detached garage bldg.Details
demolish (e) 1-story, type 5b, detached garage bldg. | $10,000 |
| Sep 10, 2018 | Completed final sign-off Dec 2018 | 51 Federal St | The Fine European Construction/Uwb Dober | renovate (e) suite including new finishes, conference rooms and lighting. ,modifications to (e) mech/ele systems to be design build. modifications to (e) fire system to be design build maher naDetails
renovate (e) suite including new finishes, conference rooms and lighting. ,modifications to (e) mech/ele systems to be design build. modifications to (e) fire system to be design build maher na | $125,000 |
| Feb 12, 2018 | Expired or cancelled withdrawn Jun 2019 | 2835 Vallejo St | The Fine European Construction/Uwb Dober | (garage) horizontal expansion to the rear side of an existing detached garage. a new living roof at the garage to be provided. mep system to be design build.Details
(garage) horizontal expansion to the rear side of an existing detached garage. a new living roof at the garage to be provided. mep system to be design build. | $101,704 |
| Mar 13, 2017 | Expired or cancelled expired Jul 2024 | 225 Amber Dr | provide a vertical/horizontal addition to (e)single fam residence. new finishes at the interior & exterior. new hardscape & landscaping at front & rear yards. provide a full seismic upgrade to (e) structure. provide fire sprinkler system throughoutDetails
provide a vertical/horizontal addition to (e)single fam residence. new finishes at the interior & exterior. new hardscape & landscaping at front & rear yards. provide a full seismic upgrade to (e) structure. provide fire sprinkler system throughout | $515,353 | |
| Oct 3, 2016 | Completed final sign-off Nov 2017 | 322 Richland Av | provide (n) balcony and exterior door at rear elevation.Details
provide (n) balcony and exterior door at rear elevation. | $5,000 | |
| Sep 21, 2016 | Completed final sign-off Aug 2018 | 3239 Steiner St | new elevator. ref app#201404304599 sDetails
new elevator. ref app#201404304599 s | $25,000 | |
| May 3, 2016 | Completed final sign-off Dec 2020 | 711 Corbett Av | The Fine European Construction/Uwb Dober | vertical & horizontal additions to the (e) 1 unit residence, transforming it into a 3-unit building, roof decks to be provided. fire sprinklers system and seismic upgrade to be provided.Details
vertical & horizontal additions to the (e) 1 unit residence, transforming it into a 3-unit building, roof decks to be provided. fire sprinklers system and seismic upgrade to be provided. | $921,931 |
| Oct 29, 2015 | Completed final sign-off Aug 2018 | 3239 Steiner St | provide (n) finishes & windows @ the front elevations. provide (n) motorized skylight @ top of stair leading to (e) roof deck.Details
provide (n) finishes & windows @ the front elevations. provide (n) motorized skylight @ top of stair leading to (e) roof deck. | $40,000 | |
| Jul 29, 2015 | Expired or cancelled withdrawn Jul 2016 | 151 Laidley St | Design Line Construction | vertical addition. renovation to an (e) one story single family residence. one story above & two stories belows the (e) residence are to be added. provide 3.5 bathrooms & 4 bedrooms total.Details
vertical addition. renovation to an (e) one story single family residence. one story above & two stories belows the (e) residence are to be added. provide 3.5 bathrooms & 4 bedrooms total. | $600,000 |
| Mar 20, 2015 | Completed final sign-off Oct 2018 | 2920 Franklin St | Design Line Construction | demolish 2-story, type 5b, single family dwelling.Details
demolish 2-story, type 5b, single family dwelling. | $20,000 |
| Mar 20, 2015 | Completed final sign-off Oct 2018 | 2920 Franklin St | Design Line Construction | erect 4-story, no basement, type 5b, 2 dwelling units building. exempted for maher ordinance.Details
erect 4-story, no basement, type 5b, 2 dwelling units building. exempted for maher ordinance. | $800,000 |
| Jul 29, 2014 | Completed final sign-off Jul 2017 | 51 Federal St | The Fine European Construction/Uwb Dober | renovate extg lobby including new canopy, finishes, storefront entry, lighting, elevator cab finishes, and modifications to extg exit corridor. n/a for the maher ordinance #155-13Details
renovate extg lobby including new canopy, finishes, storefront entry, lighting, elevator cab finishes, and modifications to extg exit corridor. n/a for the maher ordinance #155-13 | $80,000 |
| Jan 17, 2014 | Completed final sign-off Dec 2014 | 233 Laidley St | Design Line Construction | rev; to pa#201208107050 foundation revision, lower grade beam at property line, provide shotcrete at retaining walls, provide lagging at property line.Details
rev; to pa#201208107050 foundation revision, lower grade beam at property line, provide shotcrete at retaining walls, provide lagging at property line. | $5,000 |
| Oct 15, 2013 | Completed final sign-off Apr 2014 | 196 Avila St | revision to 201307313242: installation of new bath, plumbing, including shower/water closet, lavatory sink. comply with nov # 199706808Details
revision to 201307313242: installation of new bath, plumbing, including shower/water closet, lavatory sink. comply with nov # 199706808 | $5,000 | |
| Jul 31, 2013 | Completed final sign-off Apr 2014 | 196 Avila St | Payesko Constructioin Inc | renovation of bathroom; reconfiguring of extg lower level to include 2 bedrooms, one bathroom, and living room. revised stair layout configuration and light well, new skylight.Details
renovation of bathroom; reconfiguring of extg lower level to include 2 bedrooms, one bathroom, and living room. revised stair layout configuration and light well, new skylight. | $150,000 |
| Dec 5, 2012 | Completed final sign-off Nov 2014 | 82 Cameo Wy | Brendan Waters Construction Inc | renovation of (e) 2 story residence-update interior finishes, windows & roofing. re-configure (e) kitchen & (e) master bathroom, replace (e) decks in kind. no new square footage added. m.e.p systems to be design build. (e) window opening at front to be modified.Details
renovation of (e) 2 story residence-update interior finishes, windows & roofing. re-configure (e) kitchen & (e) master bathroom, replace (e) decks in kind. no new square footage added. m.e.p systems to be design build. (e) window opening at front to be modified. | $90,000 |
| Aug 10, 2012 | Completed final sign-off Dec 2014 | 233 Laidley St | Design Line Construction | demolish 1 story, type 5, single family resident building.Details
demolish 1 story, type 5, single family resident building. | $500 |
| Aug 10, 2012 | Completed final sign-off Dec 2014 | 233 Laidley St | Design Line Construction | erect 4 stories, type 5, single family residence building.Details
erect 4 stories, type 5, single family residence building. | $300,000 |
| May 30, 2012 | Completed final sign-off May 2013 | 30 Prescott Ct | Thorpe Design Inc | installing 47 fire sprinklers. nfpa 13 system required for 4 story bldg per cbc. underground under separate permit.Details
installing 47 fire sprinklers. nfpa 13 system required for 4 story bldg per cbc. underground under separate permit. | $9,000 |
| Apr 27, 2011 | Completed final sign-off Dec 2011 | 2440 Broadway | Ggd Inc. | modifications to the rear yard of an (e) 3 unit residential building to include a new deck, patios, retaining walls & landscaping irrigation & landscape lighting to be design/buildDetails
modifications to the rear yard of an (e) 3 unit residential building to include a new deck, patios, retaining walls & landscaping irrigation & landscape lighting to be design/build | $50,000 |
| Feb 7, 2011 | Completed final sign-off Dec 2011 | 2440 Broadway | Ggd Inc. | modification to the rear yard of an (e) 3 unit residential building to include new deck & convenient rear stairway (not for means of egress).Details
modification to the rear yard of an (e) 3 unit residential building to include new deck & convenient rear stairway (not for means of egress). | $150,000 |
| Aug 27, 2010 | Completed final sign-off Mar 2011 | 2440 Broadway | Design Line Construction | modifications to rear elevation at first floor and interior renovations to first floor of (e)residential building. structural modifications in garage, new stair connecting first floor storage space to lower unit, conversion of 1st floor storage to family room, home office and bathroom.Details
modifications to rear elevation at first floor and interior renovations to first floor of (e)residential building. structural modifications in garage, new stair connecting first floor storage space to lower unit, conversion of 1st floor storage to family room, home office and bathroom. | $50,000 |
| Jun 22, 2010 | Completed final sign-off Mar 2011 | 2440 Broadway | Design Line Construction | interior renovation to the basement, garage, lower unit, and middle unit. work to include new storage spaces at basement, new acoustical ceiling assemblies and modifications to lower unit bathroom, powder room and kitchen.Details
interior renovation to the basement, garage, lower unit, and middle unit. work to include new storage spaces at basement, new acoustical ceiling assemblies and modifications to lower unit bathroom, powder room and kitchen. | $40,000 |
| Dec 17, 2009 | Completed final sign-off Mar 2011 | 2440 Broadway | interior renovation to the upper unit including kitchen & bthrooms, replace rear windows "in-kind", new 1.5 bathrooms, new skylights.Details
interior renovation to the upper unit including kitchen & bthrooms, replace rear windows "in-kind", new 1.5 bathrooms, new skylights. | $100,000 | |
| Nov 10, 2009 | Completed final sign-off May 2013 | 30 Prescott Ct | Ggd Inc. | renovate (e) 2 unit, 3 story residence. add 4th floor & add a horizontal addition ar rear. provide full seismic upgrade & fire sprinkler throughoutDetails
renovate (e) 2 unit, 3 story residence. add 4th floor & add a horizontal addition ar rear. provide full seismic upgrade & fire sprinkler throughout | $500,000 |
| Dec 8, 2008 | Completed final sign-off Feb 2013 | 2919 Laguna St | Grover Custom Builders Inc | demolish a 3 stories single family dwelling.Details
demolish a 3 stories single family dwelling. | $10,000 |
| Dec 8, 2008 | Completed final sign-off May 2014 | 2919 Laguna St | Grover Custom Builders Inc | erect 4 stories 2 family dwellings.Details
erect 4 stories 2 family dwellings. | $600,000 |