Mathew Ian Bertics
- Listed as
- engineer
- Firm
- Mba Structural Engineers Inc.
- Based in
- Walnut Creek
- On San Francisco permits
- Oct 2005 to Oct 2025
21 permits since 2000 (engineer on 21 permits): 16 completed, 2 in progress, 1 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 22, 2025 | In progress issued Oct 2025 | 1518 07th Av | Saturn Construction Co | this includes a revision to page s2.1 and s4.1 as rev4. pa#: 202212279169. this includes new retaining wall and foundation from grid line 4 eastwards. also underpinning detail inside the garage at the north wall.Details
this includes a revision to page s2.1 and s4.1 as rev4. pa#: 202212279169. this includes new retaining wall and foundation from grid line 4 eastwards. also underpinning detail inside the garage at the north wall. | $1,000 |
| Oct 1, 2024 | Completed final sign-off Nov 2025 | 272 Anderson St | Hammerhouse Construction | rev to pa202403278673, structural details to s.4.1, changes in construction sequencing (separate footing and slab pours).Details
rev to pa202403278673, structural details to s.4.1, changes in construction sequencing (separate footing and slab pours). | |
| Mar 27, 2024 | Completed final sign-off Nov 2025 | 272 Anderson St | Hammerhouse Construction | basement concrete slab removed and excavation at n conditioned spaces & e crawl, struc framing and foundation improvements,n laundry/bath, hall, family rm, stair to 1st fl 1 hr fire sep btwn garage/hab spaces.1st fl replace 1 dbl hung front sash, replace 3 rear windows at vedroom/bath. mep new gasDetails
basement concrete slab removed and excavation at n conditioned spaces & e crawl, struc framing and foundation improvements,n laundry/bath, hall, family rm, stair to 1st fl 1 hr fire sep btwn garage/hab spaces.1st fl replace 1 dbl hung front sash, replace 3 rear windows at vedroom/bath. mep new gas | $166,196 |
| Nov 14, 2023 | Completed final sign-off Mar 2025 | 165 Edgewood Av | Brian Mac Namara Construction | new roof dormer at upper level,within the height maximum for this property.no additional building square footage added.Details
new roof dormer at upper level,within the height maximum for this property.no additional building square footage added. | $50,000 |
| Mar 17, 2023 | Completed final sign-off Mar 2025 | 165 Edgewood Av | Brian Mac Namara Construction | add 2 new skylights at lowslope roof. revisions to some interior partitions. upgrade hvac and dormers to be under separate permit.Details
add 2 new skylights at lowslope roof. revisions to some interior partitions. upgrade hvac and dormers to be under separate permit. | $80,000 |
| Dec 27, 2022 | In progress issued Jul 2025 | 1518 07th Av | Saturn Construction Co | horizontal rear addition on 2/f & 3/f. new windows and doors at addition. new half-bath/laundy and kitchen expansion on 2/f. new primarty suite at 3/f with new skylight at (e) roof. add new adu on 1st floor.Details
horizontal rear addition on 2/f & 3/f. new windows and doors at addition. new half-bath/laundy and kitchen expansion on 2/f. new primarty suite at 3/f with new skylight at (e) roof. add new adu on 1st floor. | $300,000 |
| Sep 1, 2022 | Completed final sign-off Dec 2022 | 387 Arguello Bl | Bg Builders Inc | revision to previously approves pa 202205134184.Details
revision to previously approves pa 202205134184. | |
| Jul 29, 2022 | Completed final sign-off Feb 2024 | 243 West Portal Av | Hasz Construction Inc | remodel of (e) 2 tenant space into a new restaurant & small office. work to include construction of new restrooms, new kitchen equipment, new interior finishes, new structural system to support new roof top equipment & new secord floor level.Details
remodel of (e) 2 tenant space into a new restaurant & small office. work to include construction of new restrooms, new kitchen equipment, new interior finishes, new structural system to support new roof top equipment & new secord floor level. | $900,000 |
| Jun 21, 2022 | Completed final sign-off Jul 2024 | 2301 Chestnut St | Terra Nova Industries | tenant improvement of an (e) vacant space to support a (n) restaurant. scope to include mechanical, electrical, plumbing, and minor structural to support rooftop mechanical equipment and construction of stall storage mezzanine.Details
tenant improvement of an (e) vacant space to support a (n) restaurant. scope to include mechanical, electrical, plumbing, and minor structural to support rooftop mechanical equipment and construction of stall storage mezzanine. | $850,000 |
| Jun 7, 2022 | Completed final sign-off Oct 2023 | 599 Skyline Bl | Terra Nova Industries | rev to pa202203079322: updated structural sheets as per original bldg comments: new patio, outdoor dining bar (golfers). all work not visible to adjacent properties. no interior under this permitDetails
rev to pa202203079322: updated structural sheets as per original bldg comments: new patio, outdoor dining bar (golfers). all work not visible to adjacent properties. no interior under this permit | |
| May 13, 2022 | Completed final sign-off Dec 2022 | 387 Arguello Bl | Bg Builders Inc | expansion of (e) general grocery and restaurant (387 arguello blvd) into the adjacent existing retail tanant space (2 clement st). scope limited to 2 clement st. (n) kitchen equipment, millwork, floor/ wall/ ceiling finishes and associated mep work. expansion to cua granted per motion no. m-20190.Details
expansion of (e) general grocery and restaurant (387 arguello blvd) into the adjacent existing retail tanant space (2 clement st). scope limited to 2 clement st. (n) kitchen equipment, millwork, floor/ wall/ ceiling finishes and associated mep work. expansion to cua granted per motion no. m-20190. | $74,650 |
| Mar 29, 2022 | Never finaled issued Apr 2022, no final | 494 Seacliff Av | Buildergirl Design And Construction | revision to pa 2020-1007-6049 to replace (e) water damaged front landing w/(n) landing & entry stairDetails
revision to pa 2020-1007-6049 to replace (e) water damaged front landing w/(n) landing & entry stair | $5,000 |
| Mar 7, 2022 | Completed final sign-off Oct 2023 | 599 Skyline Bl | Terra Nova Industries | interior work for demo. (n) golfers bar & (e) dining area. (n) enclosed patio dining area to (e) exterior patio. (n) egress stairs, (n)mens/womens toilet rooms. interior finishes & paint. ref demo 202201035256.Details
interior work for demo. (n) golfers bar & (e) dining area. (n) enclosed patio dining area to (e) exterior patio. (n) egress stairs, (n)mens/womens toilet rooms. interior finishes & paint. ref demo 202201035256. | $250,000 |
| Jan 13, 2022 | Completed final sign-off Sep 2026 | 361 Upper Tr | Sage Construction Services, Jeff King And Company Inc | demo: remove rear wall,roof,levl 1 floor/balcony/stair,select demo of interior walls(less than 25%)remove levels 2 and 3 balconies.garage and party walls to remain. floor framing at levels 2, 3, and loft to remain. replace entry stair 1st fl,new deck, stair,and deck/hot tub at grade, new smallerDetails
demo: remove rear wall,roof,levl 1 floor/balcony/stair,select demo of interior walls(less than 25%)remove levels 2 and 3 balconies.garage and party walls to remain. floor framing at levels 2, 3, and loft to remain. replace entry stair 1st fl,new deck, stair,and deck/hot tub at grade, new smaller | $750,000 |
| Sep 7, 2021 | Expired or cancelled withdrawn Dec 2021 | 808 Douglass St | 1st floor: remodel (e) bedroom. excavation & new foundations @ new rear addition. new primary bedroom, bathroom, laundry room. new windows & exterior door. 2nd floor: kitchen remodel. rear addition. remodel (e) bath. remove (e) tar & gravel roof finish & install new ingle ply membrance roof materialDetails
1st floor: remodel (e) bedroom. excavation & new foundations @ new rear addition. new primary bedroom, bathroom, laundry room. new windows & exterior door. 2nd floor: kitchen remodel. rear addition. remodel (e) bath. remove (e) tar & gravel roof finish & install new ingle ply membrance roof material | $433,503 | |
| Jul 8, 2021 | Completed final sign-off Mar 2026 | 3738 20th St | Maib Construction Company Inc | (n) decks off rear wall at 1st, 2nd & 3rd flrs. rebuild (e) exit stair from 3rd flr to rear yard. (n) site work for lower lvl infill, modifications & (n) finishes for (n) decks, (n) trash enclosure at front of house. 63 sq ft of (n) unconditioned infill on lower lvl under (e) 2nd flr.Details
(n) decks off rear wall at 1st, 2nd & 3rd flrs. rebuild (e) exit stair from 3rd flr to rear yard. (n) site work for lower lvl infill, modifications & (n) finishes for (n) decks, (n) trash enclosure at front of house. 63 sq ft of (n) unconditioned infill on lower lvl under (e) 2nd flr. | $100,000 |
| Oct 1, 2019 | Completed final sign-off Mar 2021 | 300 16th St | Dome Construction Corp | interior ti space 3: restaurant "gotts" in e shell core and baths. exterior entry door to promenade, furn installDetails
interior ti space 3: restaurant "gotts" in e shell core and baths. exterior entry door to promenade, furn install | $400,000 |
| Nov 18, 2016 | Completed final sign-off Jul 2021 | 308 Andover St | Lenzi Incorporated | rev. pa#201506027795, revised foundation details to accommodate existing conditions.Details
rev. pa#201506027795, revised foundation details to accommodate existing conditions. | $100 |
| Jun 2, 2015 | Completed final sign-off Jul 2021 | 308 Andover St | Lenzi Incorporated | 2nd story partial roof removal & replace. 2nd story will repair, alignment & new windows in rear. extension of (e) deck to alignment, new rear door to deck for exiting.Details
2nd story partial roof removal & replace. 2nd story will repair, alignment & new windows in rear. extension of (e) deck to alignment, new rear door to deck for exiting. | $7,500 |
| Apr 14, 2015 | Completed final sign-off Dec 2015 | 850 La Playa | Eric F Anderson Incorporated | interior t-i. replace interior decor, enclose produce prep area, replace select sections grocery shelving replace select floral, deli, bakery, service meat, produce & customer service fixtures. disabled access improvements to site & store interior, misc. clean up & repair.Details
interior t-i. replace interior decor, enclose produce prep area, replace select sections grocery shelving replace select floral, deli, bakery, service meat, produce & customer service fixtures. disabled access improvements to site & store interior, misc. clean up & repair. | $260,000 |
| Oct 13, 2005 | Expired or cancelled expired May 2008 | 1330 Sanchez St | Edward Everett Patten Jr | residential renovation of 2 story house,civil & structural of underground work.Details
residential renovation of 2 story house,civil & structural of underground work. | $10,000 |