Permit GraphShortlistSan Francisco building permits since 2000

John Bachoua

License
19677
State contractor license record
Listed as
architect, engineer
Firm
Nazarene Engineering
Based in
El Cajon
On San Francisco permits
Dec 2019 to Jul 2025

12 permits since 2000 (engineer on 11 permits, architect on 1 permit): 9 completed, 3 in progress.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jul 16, 2025In progress
issued Jul 2025
718 Long Bridge StRogers Electricinstall 31 ev charging station in and around parking garage. assigned owner, not avaiable to general public.
Details
Permit
202507160930
Status
issued
Filed
Jul 16, 2025
Permit issued
Jul 16, 2025
Declared cost
$50,000
Address
718 Long Bridge St

install 31 ev charging station in and around parking garage. assigned owner, not avaiable to general public.

Open the permit page

$50,000
Sep 17, 2024Completed
final sign-off Feb 2025
4131 Geary BlBooth Electric Increvision to pa#: 202312062020. change of electrical feed and panel location.
Details
Permit
202409170939
Status
complete
Filed
Sep 17, 2024
Permit issued
Sep 26, 2024
Final sign-off
Feb 11, 2025
Declared cost
$5,000
Address
4131 Geary Bl

revision to pa#: 202312062020. change of electrical feed and panel location.

Open the permit page

$5,000
Dec 28, 2023In progress
issued Dec 2023
2190 Ofarrell StBooth Electric Incinstalling 4 level 3 fast chargers, dual stall delivery in indoor parking garage, installing power feeds from existing switchgear in parking garage.
Details
Permit
202312283184
Status
issued
Filed
Dec 28, 2023
Permit issued
Dec 28, 2023
Declared cost
$100,000
Address
2190 Ofarrell St

installing 4 level 3 fast chargers, dual stall delivery in indoor parking garage, installing power feeds from existing switchgear in parking garage.

Open the permit page

$100,000
Dec 7, 2023Completed
final sign-off Feb 2025
2238 Geary BlBooth Electric Incinstalling (2) level 3 fast charger in indoor parking garage. installing power feeds from existing switchgear in parking garage.
Details
Permit
202312072110
Status
complete
Filed
Dec 7, 2023
Permit issued
Dec 28, 2023
Final sign-off
Feb 27, 2025
Declared cost
$50,000
Address
2238 Geary Bl

installing (2) level 3 fast charger in indoor parking garage. installing power feeds from existing switchgear in parking garage.

Open the permit page

$50,000
Dec 6, 2023Completed
final sign-off Feb 2025
4131 Geary BlBooth Electric Incparking area - installing (4) level 2 ev chargers and (1) level 3 fast charger in outdoor parking lot. installing power feeds from (e) switchgear in the basement under outdoor, uncovered parking area.
Details
Permit
202312062020
Status
complete
Filed
Dec 6, 2023
Permit issued
Jan 23, 2024
Final sign-off
Feb 10, 2025
Declared cost
$100,000
Address
4131 Geary Bl

parking area - installing (4) level 2 ev chargers and (1) level 3 fast charger in outdoor parking lot. installing power feeds from (e) switchgear in the basement under outdoor, uncovered parking area.

Open the permit page

$100,000
Nov 7, 2023In progress
filed Nov 2023, not yet issued
50 Quint Stthis project consists of (20) ev charging stations with dual stall delivery serving (40) parking stalls within (e) commercial parking lot that will be restriped.
Details
Permit
202311070300
Status
filed
Filed
Nov 7, 2023
Declared cost
$400,000
Address
50 Quint St

this project consists of (20) ev charging stations with dual stall delivery serving (40) parking stalls within (e) commercial parking lot that will be restriped.

Open the permit page

$400,000
Apr 6, 2021Completed
final sign-off Dec 2021
1185 Market StCupertino Electric Inc.install 800a switchboard to feed (1) all-in-one 50kw ev charger & (4) all-in-one 100kw ev chargers. install associated conduit & conductors. (5) total evcs being installed as part of approved (12) future ev chargers approved for whole foods market renovation under pa# 202007200503.
Details
Permit
202104067981
Status
complete
Filed
Apr 6, 2021
Permit issued
Oct 8, 2021
Final sign-off
Dec 3, 2021
Declared cost
$350,000
Address
1185 Market St

install 800a switchboard to feed (1) all-in-one 50kw ev charger & (4) all-in-one 100kw ev chargers. install associated conduit & conductors. (5) total evcs being installed as part of approved (12) future ev chargers approved for whole foods market renovation under pa# 202007200503.

Open the permit page

$350,000
Feb 16, 2021Completed
final sign-off Mar 2022
735 07th AvCupertino Electric Inc.revision to app#202011048170 to the ada portion only. install 400 a meter main at extg parking lot. install 4 50kw ev chargers. install utility transformer pad and conduit. install associated conduit and conductors. install ev ada van stall & ramp.
Details
Permit
202102164688
Status
complete
Filed
Feb 16, 2021
Permit issued
Aug 3, 2021
Final sign-off
Mar 2, 2022
Declared cost
$117,900
Address
735 07th Av

revision to app#202011048170 to the ada portion only. install 400 a meter main at extg parking lot. install 4 50kw ev chargers. install utility transformer pad and conduit. install associated conduit and conductors. install ev ada van stall & ramp.

Open the permit page

$117,900
Jul 23, 2020Completed
final sign-off Dec 2020
1750 Fulton StCampbell Family Electric Incinstall (2) ev chargers in existing parking structure
Details
Permit
202007230737
Status
complete
Filed
Jul 23, 2020
Permit issued
Oct 28, 2020
Final sign-off
Dec 3, 2020
Declared cost
$162,000
Address
1750 Fulton St

install (2) ev chargers in existing parking structure

Open the permit page

$162,000
Mar 5, 2020Completed
final sign-off Aug 2020
1000 Van Ness AvCampbell Family Electric Incinstall (9) level 3 evs e chargers and (1) level 2 charger & require electrical equipment.
Details
Permit
202003056279
Status
complete
Filed
Mar 5, 2020
Permit issued
Mar 16, 2020
Final sign-off
Aug 18, 2020
Declared cost
$150,000
Address
1000 Van Ness Av

install (9) level 3 evs e chargers and (1) level 2 charger & require electrical equipment.

Open the permit page

$150,000
Mar 5, 2020Completed
final sign-off Jul 2020
1150 Ocean AvCampbell Family Electric Increplace (2) level 2 ev chargers w/(2) level (3) ev chargers.
Details
Permit
202003056282
Status
complete
Filed
Mar 5, 2020
Permit issued
Mar 16, 2020
Final sign-off
Jul 14, 2020
Declared cost
$20,000
Address
1150 Ocean Av

replace (2) level 2 ev chargers w/(2) level (3) ev chargers.

Open the permit page

$20,000
Dec 17, 2019Completed
final sign-off Jun 2020
1160 Mission StCampbell Family Electric Incinstall (2) l3 vehicle charging stations
Details
Permit
201912179802
Status
complete
Filed
Dec 17, 2019
Permit issued
Jan 2, 2020
Final sign-off
Jun 23, 2020
Declared cost
$48,000
Address
1160 Mission St

install (2) l3 vehicle charging stations

Open the permit page

$48,000