4 permits since 2000 (architect on 3 permits, engineer on 1 permit): 3 completed, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 3, 2023 | Completed final sign-off Jan 2025 | 982 Mission St | The Whiting-Turner Contracting Company | remodel of bldg & voluntary lateral force-resisting system alteration. accessibility upgrades.new ada ramp railing w/ relocating (e) stair exit door at lev 1.add rail at mezz.adding (n) wall out-of-plane & diaphram load transfer from diaphragm to braced frames. strengthen (e) collector connectn.Details
remodel of bldg & voluntary lateral force-resisting system alteration. accessibility upgrades.new ada ramp railing w/ relocating (e) stair exit door at lev 1.add rail at mezz.adding (n) wall out-of-plane & diaphram load transfer from diaphragm to braced frames. strengthen (e) collector connectn. | $1,792,526 |
| Jan 29, 2021 | Expired or cancelled cancelled Jan 2026 | 16 Jessie St | all work performed on the roof level. install new flashing and parapet coping at northeast elevation. install new steel parapet bracing along northeast elevation.Details
all work performed on the roof level. install new flashing and parapet coping at northeast elevation. install new steel parapet bracing along northeast elevation. | $150,000 | |
| Apr 27, 2018 | Completed final sign-off Apr 2020 | 316 Juanita Wy | Baytown Construction | to comply with nov #201842114 & 201841841, alteration to (e) home, including removing walls, finishes, doors, replacing windows, in - kind, new plumbing, remodel the three floors and update the layout of the house, structural reinforcement, demolish stairs in basement & reframing,Details
to comply with nov #201842114 & 201841841, alteration to (e) home, including removing walls, finishes, doors, replacing windows, in - kind, new plumbing, remodel the three floors and update the layout of the house, structural reinforcement, demolish stairs in basement & reframing, | $150,000 |
| Oct 24, 2013 | Completed final sign-off Dec 2013 | 177 Post St | Olive Construction Corp | #650- interior tenant improvement includes new non bearing partition, mechanical & electrical under seperate permit.Details
#650- interior tenant improvement includes new non bearing partition, mechanical & electrical under seperate permit. | $90,000 |