E.S. Lindquist
- Listed as
- architect, engineer
- Firm
- Brierley Associates
- On San Francisco permits
- Sep 2013 to May 2019
11 permits since 2000 (engineer on 9 permits, architect on 2 permits): 11 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 21, 2019 | Completed final sign-off Dec 2021 | 82 Mary St | Swinerton Builders | tie back extending under 82 mary street. documentation of tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281.Details
tie back extending under 82 mary street. documentation of tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281. | $18,000 |
| May 21, 2019 | Completed final sign-off Dec 2021 | 110 05th St | Swinerton Builders | tie backs extending under 110 5th street. documentation of tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281.Details
tie backs extending under 110 5th street. documentation of tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281. | |
| May 21, 2019 | Completed final sign-off Dec 2021 | 198 05th St | Swinerton Builders | tie backs extending under 198 5th street. documentation for tieback encroachment agreement only. n/a for maher. ref. permit #2019-0521-1281.Details
tie backs extending under 198 5th street. documentation for tieback encroachment agreement only. n/a for maher. ref. permit #2019-0521-1281. | |
| May 21, 2019 | Completed final sign-off Dec 2021 | 934 Howard St | Swinerton Builders | tie back extending under 934 howard. documentation for tieback encroachment only. n/a for maher. ref. main permit #2019-0521-1281.Details
tie back extending under 934 howard. documentation for tieback encroachment only. n/a for maher. ref. main permit #2019-0521-1281. | |
| May 21, 2019 | Completed final sign-off Dec 2021 | 430 Natoma St | tie backs extending under 430 natoma street. documentation for tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281.Details
tie backs extending under 430 natoma street. documentation for tieback encroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281. | ||
| May 21, 2019 | Completed final sign-off Dec 2021 | 409 Natoma St | Swinerton Builders | temporary support of excavation system consisting of deep soil mix shorings/cut off walls with tie backs. n/a for maherDetails
temporary support of excavation system consisting of deep soil mix shorings/cut off walls with tie backs. n/a for maher | $1,200,000 |
| May 21, 2019 | Completed final sign-off Dec 2021 | 433 Natoma St | Swinerton Builders | tie backs extending under 433 natoma street. documentation of tieback enchroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281.Details
tie backs extending under 433 natoma street. documentation of tieback enchroachment agreement only. n/a for maher. ref. main permit #2019-0521-1281. | |
| Nov 22, 2016 | Completed final sign-off Aug 2018 | 526 Mission St | Swinerton/Webcor Jv, Swinerton/Webcor Jv, Malcolm Drilling Co Inc | cutter soil mix csm shoring/cut off wall for tower 2 temporary support of excavation system. bracing design to be submitted under separate application ref#2015 1030 1302Details
cutter soil mix csm shoring/cut off wall for tower 2 temporary support of excavation system. bracing design to be submitted under separate application ref#2015 1030 1302 | $3,000,000 |
| Nov 6, 2015 | Completed final sign-off Aug 2017 | 510 Townsend St | Dpr Construction | shoring for temporary support of excavation. n/a for maher. tie back removal under pa#201511062016.Details
shoring for temporary support of excavation. n/a for maher. tie back removal under pa#201511062016. | $1,200,000 |
| Sep 11, 2013 | Completed final sign-off May 2018 | 181 Fremont St | Level 10 Construction Lp | temporary support for excavation. site permit under pa#2013-05-01-5894s. under maher ordiance and is excavate more than 50 cubic yard of soil.Details
temporary support for excavation. site permit under pa#2013-05-01-5894s. under maher ordiance and is excavate more than 50 cubic yard of soil. | $3,200,000 |
| Sep 11, 2013 | Completed final sign-off May 2018 | 199 Fremont St | temporary support for excavation for 181 fremont st adjacant property. site permit for 181 fremont st pa#2013-05-01-5894s. under maher ordiance and is excavate more than 50 cubic yard of soil.Details
temporary support for excavation for 181 fremont st adjacant property. site permit for 181 fremont st pa#2013-05-01-5894s. under maher ordiance and is excavate more than 50 cubic yard of soil. | $700,000 |