Permit GraphShortlistSan Francisco building permits since 2000

Permit 201302069569

153 Townsend St

8th & 9th floor - existing communicating stair between floors 8 & 9 to have existing finishes removed to stair. demo of non-structural wall partitions around communicating stairs. ab-17 for t.i. under separate permit.

Outcome
Completed (city status: complete, Jul 17, 2013)
Filed
Feb 6, 2013
Permit issued
Feb 7, 2013
Final sign-off
Jul 17, 2013
Declared cost
$5,000
Building use
office
Neighborhood
Mission Bay
Contractor
Skyline Construction (license 727637)
Project type
Stairs
Property
All permits at this address (block 3794, lot 025)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Skyline Construction (license 727637)
Architect
Sam H. Alkhatib (license E20259)
Pmt consultant/expediter
Cyndi Batson Lori Thompson (no license listed)