Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Japantown neighborhood?

In the Japantown neighborhood of San Francisco, only 4 bathroom remodel permits filed from October 2025 through September 2026 have been issued, too few for a reliable figure. Of the 5 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 165 days of being issued, up from 100 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sJapantown neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/japantown/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20264 issuedunder 513 issued15
Permit issued to final sign-offOctober 2023 through September 20245 finished1657 finished100

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q31100too recent
2026-Q22220too recent
2026-Q11100too recent
2025-Q33320too recent
2025-Q25320too recent
2025-Q14420too recent
2024-Q43320too recent
2024-Q23320yes
2024-Q13320yes
2023-Q42210yes
2023-Q32102yes
2023-Q22210yes
2023-Q13330yes
2022-Q45430yes
2022-Q31001yes
2022-Q266005521381yes
2022-Q14440yes
2021-Q42220yes
2021-Q31101yes
2021-Q23330yes
2021-Q11110yes
2020-Q42211yes
2020-Q3551211652002570yes
2020-Q13330yes
2019-Q41101yes
2019-Q35330yes
2019-Q13330yes
2018-Q42220yes
2018-Q31110yes
2018-Q22101yes
2018-Q12211yes
2017-Q42110yes
2017-Q34440yes
2017-Q23210yes
2017-Q12220yes
2016-Q44440yes
2016-Q32220yes
2016-Q24440yes
2016-Q13321yes
2015-Q41110yes
2015-Q33330yes
2015-Q22211yes
2015-Q13321yes
2014-Q43321yes
2014-Q3660041yes
2014-Q24440yes
2014-Q13330yes
2013-Q4550523yes
2013-Q33312yes
2013-Q2550132yes
2012-Q41110yes
2012-Q355203640yes
2012-Q21100yes
2011-Q43330yes
2011-Q32220yes
2011-Q21110yes
2011-Q11110yes
2010-Q32200yes
2010-Q24400yes
2010-Q12220yes
2009-Q41101yes
2009-Q31110yes
2009-Q21110yes
2009-Q14422yes
2008-Q42210yes
2008-Q34440yes
2008-Q23330yes
2008-Q11110yes
2007-Q45440yes
2007-Q34440yes
2007-Q23312yes
2006-Q41110yes
2006-Q21100yes
2005-Q21110yes
2005-Q11110yes
2004-Q31110yes
2004-Q12210yes
2003-Q21110yes
2002-Q42220yes
2001-Q31110yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

26 of the 207 bathroom remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Japantown neighborhood

Shown apart, with their own page here: kitchen remodel (288 filed, 205 finished; contractors); bathroom remodel (207 filed, 147 finished; contractors); stairs (79 filed, 44 finished; contractors). Other types: 2,244 permits. All permits in San Francisco's Japantown neighborhood

Nearby neighborhoods

Western Addition, Pacific Heights, Hayes Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.