Rab Com Limited
- Based in
- San Francisco
- On San Francisco permits
- Oct 2022 to Sep 2026
- Last 24 months
- 9 permits filed
11 permits since 2000: 8 completed, 3 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 2, 2026 | In progress issued Sep 2026 | 555 California St | elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by paganini electic. rab-com limited to program, test and commision additional intercoms to exiting system. ref 2026.0504.0579Details
elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by paganini electic. rab-com limited to program, test and commision additional intercoms to exiting system. ref 2026.0504.0579 | $23,263 |
| Aug 6, 2026 | In progress issued Aug 2026 | 345 California St | 10th fl - to program 2 way comm intercom stations for passenger and freight elevator lobbies limited to the 10 floor. intercom is being installed to provide communication abilities during times that elevator lobby doors are locked or stairswells blocked. conduit, back boxes, cabling and installationDetails
10th fl - to program 2 way comm intercom stations for passenger and freight elevator lobbies limited to the 10 floor. intercom is being installed to provide communication abilities during times that elevator lobby doors are locked or stairswells blocked. conduit, back boxes, cabling and installation | $19,626 |
| Aug 6, 2026 | Completed final sign-off Aug 2026 | 345 California St | 23rd fl - to program 2 way comm intercom stations for passenger and freight elevator lobbies limited to the 23rd floor. intercom is being installed to provide communication abilites during time the elvator lobby doors are locked or stairwells blocked. conduit, back boxes, calling and installation toDetails
23rd fl - to program 2 way comm intercom stations for passenger and freight elevator lobbies limited to the 23rd floor. intercom is being installed to provide communication abilites during time the elvator lobby doors are locked or stairwells blocked. conduit, back boxes, calling and installation to | $16,127 |
| Jul 24, 2026 | Completed final sign-off Aug 2026 | 345 California St | program 2-way communications intercom stations for passenger and freight elevator lobbies and stair #1 stair 2 aor limited to 5/f. program, test and commision system.Details
program 2-way communications intercom stations for passenger and freight elevator lobbies and stair #1 stair 2 aor limited to 5/f. program, test and commision system. | $20,500 |
| Jun 17, 2026 | Completed final sign-off Aug 2026 | 345 California St | 27/f: to program 2-way communications intercom stations for passenger and freight elevator lobbies limited to the 27th floor. intercom is being installed to provide communications abilities during times that the elevator lobby doors are locked. conduit, back boxes, cabling and installation to be...Details
27/f: to program 2-way communications intercom stations for passenger and freight elevator lobbies limited to the 27th floor. intercom is being installed to provide communications abilities during times that the elevator lobby doors are locked. conduit, back boxes, cabling and installation to be... | $4,794 |
| Dec 23, 2025 | Completed final sign-off Jul 2026 | 555 California St | 46th flr. to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electric...Details
46th flr. to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electric... | $19,443 |
| Dec 23, 2025 | Completed final sign-off Jul 2026 | 555 California St | 45th fl: to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electricref#202512222446Details
45th fl: to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electricref#202512222446 | $19,443 |
| Dec 23, 2025 | In progress issued Dec 2025 | 555 California St | 52nd fl: to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electricDetails
52nd fl: to furnish 2 way communications intercom stations for freight elevator lobby. intercoms are being installed to provide communication abilities during times that elevator lobby doors are locked. conduit, back boxes, cabling and installation to be completed by cbf electric | $19,443 |
| May 7, 2025 | Completed final sign-off Sep 2025 | 555 California St | 25th & 26/f:furnish 2-way communications intercom stations for passenger elevator lobbies.intercoms installed to provide comm. abilities during times that elevator lobby doors are locked. conduit,back boxes,cabling & installation by paganini elec.Details
25th & 26/f:furnish 2-way communications intercom stations for passenger elevator lobbies.intercoms installed to provide comm. abilities during times that elevator lobby doors are locked. conduit,back boxes,cabling & installation by paganini elec. | $24,500 |
| Jul 27, 2023 | Completed final sign-off Jun 2024 | 555 California St | upgrade existing stentofon main control board. this involves powering down stentofon exchange, removing original board, replacing with new main control board and powering exchange back up rcl will then log into system via stentofon softwareDetails
upgrade existing stentofon main control board. this involves powering down stentofon exchange, removing original board, replacing with new main control board and powering exchange back up rcl will then log into system via stentofon software | $31,600 |
| Oct 14, 2022 | Completed final sign-off May 2024 | 555 California St | 27/f:furnish 2-way communications intercom stations for passenger & freight elevator lobbies.intercoms installed to provide comm. abilities during times that elevator lobby doors are locked. conduit,back boxes,cabling & installation by mcmillan elec. rab-com limited to program,test & comm. systemDetails
27/f:furnish 2-way communications intercom stations for passenger & freight elevator lobbies.intercoms installed to provide comm. abilities during times that elevator lobby doors are locked. conduit,back boxes,cabling & installation by mcmillan elec. rab-com limited to program,test & comm. system | $24,500 |