- 8 permits filed
24 permits since 2000: 11 completed, 6 in progress, 5 never finaled, 2 expired or cancelled.
Of the 5 never-finaled permits, 2 are 3 to 5 years old, 3 are 5 to 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Kitchen remodel permits
4 kitchen remodel permits: 1 completed, 3 in progress. Typically 42 days from filing to permit and 95 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 21, 2025 | Completed final sign-off Oct 2025 | 1646 42nd Av | kitchen remodel in kind: replace (e) cabinets, appliances, & fixtures- like for like. bathroom remodel in kind: replace (e) floor tile, shower tile, & fixtures- like for like. all work in-kind to match (e) location. no change to floor layout. no change to wall layout. no structural work.Details
kitchen remodel in kind: replace (e) cabinets, appliances, & fixtures- like for like. bathroom remodel in kind: replace (e) floor tile, shower tile, & fixtures- like for like. all work in-kind to match (e) location. no change to floor layout. no change to wall layout. no structural work. | $30,000 |
| Feb 26, 2025 | In progress issued Mar 2025 | 347 Justin Dr | repair in kind, restore due to water damage, repair and re-install drywall in upper floor. reinstall cabinets in kitchen and repair floors. repair after re-roof, ref bpa 202412146851Details
repair in kind, restore due to water damage, repair and re-install drywall in upper floor. reinstall cabinets in kitchen and repair floors. repair after re-roof, ref bpa 202412146851 | $45,000 |
| Jan 9, 2025 | In progress issued May 2025 | 158 Flood Av | ground fl - add 2 bedrms, add 1 bathrm, media/gym room & laundry @ ground fl; 2nd fl - (e) kitchen to be renovated, relocate interior stairs to other side of house; improve the rear deck increasing 885 sf of conditioned spaceDetails
ground fl - add 2 bedrms, add 1 bathrm, media/gym room & laundry @ ground fl; 2nd fl - (e) kitchen to be renovated, relocate interior stairs to other side of house; improve the rear deck increasing 885 sf of conditioned space | $150,000 |
| May 3, 2024 | In progress issued Jul 2024 | 51 Ramona Av | remodel 2 kitchens, and 1 bathroom and 3 skylights.Details
remodel 2 kitchens, and 1 bathroom and 3 skylights. | $60,000 |