54 permits since 2000: 45 completed, 7 never finaled, 2 expired or cancelled.
Of the 7 never-finaled permits, 2 are 5 to 10 years old, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Kitchen remodel permits
18 kitchen remodel permits: 18 completed. Typically 0 days from filing to permit and 200 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 23, 2019 | Completed final sign-off Dec 2020 | 1486 26th Av | 1/f: add 2 bedrooms, 1 family area, 2 bathrooms, add laundry and sink, 2/f: remodel (e) kitchen & 2 bathrooms and living room. new roof deck on 1st floor lightwell infill and new roofdeck at highest level. infill under room on posts at rear. no work at front.Details
1/f: add 2 bedrooms, 1 family area, 2 bathrooms, add laundry and sink, 2/f: remodel (e) kitchen & 2 bathrooms and living room. new roof deck on 1st floor lightwell infill and new roofdeck at highest level. infill under room on posts at rear. no work at front. | $40,000 |
| Jun 6, 2018 | Completed final sign-off Apr 2019 | 953 Union St | rev pa# 201405307166, keep 3rd & 4th fl. kitchen in orginal locationDetails
rev pa# 201405307166, keep 3rd & 4th fl. kitchen in orginal location | |
| Oct 31, 2017 | Completed final sign-off Apr 2021 | 178 Jules Av | remodel (e) kitchen. convert one bathroom to two full bathrooms at 2nd floor. construct two bedrooms, two full bathrooms, playroom & laudnry area at ground floor.Details
remodel (e) kitchen. convert one bathroom to two full bathrooms at 2nd floor. construct two bedrooms, two full bathrooms, playroom & laudnry area at ground floor. | $68,000 |
| Jul 1, 2016 | Completed final sign-off Nov 2016 | 2178 18th Av | revision to ref pa 2016 0303 1123: kitchen remodel on 2nd flr. add 1 closet on 2nd. enlarge hallway on 1st flr. relocated furnace & tankless water heaterDetails
revision to ref pa 2016 0303 1123: kitchen remodel on 2nd flr. add 1 closet on 2nd. enlarge hallway on 1st flr. relocated furnace & tankless water heater | $10,000 |
| Apr 28, 2016 | Completed final sign-off Aug 2017 | 2114 32nd Av | 1st flr: 1) add two bedrooms, two bathrms, one mud room per plan, 2nd flr: 2)add one office per plan, eliminated two (e)light well per plan, kitchen remodel per plan. wall removal less than 75%Details
1st flr: 1) add two bedrooms, two bathrms, one mud room per plan, 2nd flr: 2)add one office per plan, eliminated two (e)light well per plan, kitchen remodel per plan. wall removal less than 75% | $70,000 |
| Nov 6, 2015 | Completed final sign-off May 2016 | 1574 Jackson St | relocate kitchen, add half bathroom for unit #1 at 2nd floor; maher n/aDetails
relocate kitchen, add half bathroom for unit #1 at 2nd floor; maher n/a | $18,000 |
| Jun 5, 2014 | Completed final sign-off Dec 2015 | 2 Mercedes Wy | 1)remodel extg kitchen, 2 bath rooms, replace fixtures. counter and flooring at 2n floor. 2)remodel 2 extg bath rooms, replace fixtures, counter and flooring. construct 2 new bathroom at 3rd floor.Details
1)remodel extg kitchen, 2 bath rooms, replace fixtures. counter and flooring at 2n floor. 2)remodel 2 extg bath rooms, replace fixtures, counter and flooring. construct 2 new bathroom at 3rd floor. | $70,000 |
| Mar 21, 2013 | Completed final sign-off Oct 2013 | 1574 Jackson St | unit #4-relocate kitchen, add half bathroom & re-wire lighting for at 2nd floor.Details
unit #4-relocate kitchen, add half bathroom & re-wire lighting for at 2nd floor. | $18,000 |
| Sep 27, 2012 | Completed final sign-off Sep 2013 | 355 Santa Ana Av | add one bedroom, two full bathroom & under-pin. partial (e) footing. remodel (e) kitchen. bathroom & convert a study room to family room at 1st floor. (comply w/complaint #201284293). convert one (e) bathroom to two bath room & add one new bathroom in bedroom at 2nd floor. construct 3'-0" heightDetails
add one bedroom, two full bathroom & under-pin. partial (e) footing. remodel (e) kitchen. bathroom & convert a study room to family room at 1st floor. (comply w/complaint #201284293). convert one (e) bathroom to two bath room & add one new bathroom in bedroom at 2nd floor. construct 3'-0" height | $72,000 |
| Jun 11, 2012 | Completed final sign-off Aug 2012 | 2381 18th Av | remodel kitchen on top level: replace cabinets, countertop, no change of walls/window, remodel 1 bath, bath tub not worked on, min. of 50% kitchen total wattage of permanent lig installed, lighting be high efficacy, bathroom permanent light be high efficacy or control by manual on occupancy seDetails
remodel kitchen on top level: replace cabinets, countertop, no change of walls/window, remodel 1 bath, bath tub not worked on, min. of 50% kitchen total wattage of permanent lig installed, lighting be high efficacy, bathroom permanent light be high efficacy or control by manual on occupancy se | $6,000 |
| Jun 3, 2011 | Completed final sign-off Nov 2011 | 623 37th Av | remodel kitchen and bathroom at 1st floorDetails
remodel kitchen and bathroom at 1st floor | $9,300 |
| Nov 22, 2010 | Completed final sign-off Jun 2011 | 1667 25th Av | remodel ground fl. two (n) bedrooms, 2 (n) full bathrooms, laundry, storage and new fam.room. 2nd fl: new full bath and remodel kitchen (n) siding at rear to match (e).Details
remodel ground fl. two (n) bedrooms, 2 (n) full bathrooms, laundry, storage and new fam.room. 2nd fl: new full bath and remodel kitchen (n) siding at rear to match (e). | $80,000 |
| Jul 14, 2009 | Completed final sign-off Feb 2010 | 2435 16th Av | remodel (e) kitchen, bath room. add one new bathroom and study room. all work at 2nd floor. construct one bedroom, storage room, two bath rooms and upgrade (e) bed room at ground floor.Details
remodel (e) kitchen, bath room. add one new bathroom and study room. all work at 2nd floor. construct one bedroom, storage room, two bath rooms and upgrade (e) bed room at ground floor. | $62,000 |
| Oct 10, 2007 | Completed final sign-off Apr 2008 | 2347 25th Av | remodel kitchen, bath room, and add one new bath, enclose existing lightwell,work at first floor. construct two bedroom, laundry room and two full bath at ground floor, include in-fill under the exist sun room.Details
remodel kitchen, bath room, and add one new bath, enclose existing lightwell,work at first floor. construct two bedroom, laundry room and two full bath at ground floor, include in-fill under the exist sun room. | $80,000 |
| Sep 6, 2007 | Completed final sign-off Oct 2007 | 495 Lakeshore Dr | replace 1 kitchen counter, replace sink in kind, tile floor, replace kitchen cabinets, add 4 electrical outlets, replace dish washer, garbage compactorDetails
replace 1 kitchen counter, replace sink in kind, tile floor, replace kitchen cabinets, add 4 electrical outlets, replace dish washer, garbage compactor | $12,000 |
| Apr 11, 2007 | Completed final sign-off Mar 2011 | 1749 Page St | new rear deck stair accessory stair minor remodel, (kitchen, bath) on upper unit. note: scope of work has changes between the the "site" and the "addendum". the side egress stairs are to remain, with no infill.Details
new rear deck stair accessory stair minor remodel, (kitchen, bath) on upper unit. note: scope of work has changes between the the "site" and the "addendum". the side egress stairs are to remain, with no infill. | $95,000 |
| Sep 8, 2006 | Completed final sign-off Mar 2007 | 1507 31st Av | add 2 bedroom, 1 play room, 2 full bathroom & 1 laundry room on existing ground floor per plan.scope of work on existing 2/fl-add 1 new full bathroom. remodel existing kitchen &bathroom. all new plumbing &rewire.replace exist.interior sheetrock(except living room area.Details
add 2 bedroom, 1 play room, 2 full bathroom & 1 laundry room on existing ground floor per plan.scope of work on existing 2/fl-add 1 new full bathroom. remodel existing kitchen &bathroom. all new plumbing &rewire.replace exist.interior sheetrock(except living room area. | $68,000 |
| Sep 7, 2006 | Completed final sign-off Jan 2007 | 2007 Balboa St | remodel kitchen and bath. expand closet in living room at 3rd floorDetails