Eg Construction Inc
- Based in
- Pacifica
- On San Francisco permits
- Mar 2023 to Sep 2026
- Last 24 months
- 11 permits filed
22 permits since 2000: 14 completed, 8 in progress.
CompletedIn progressNever finaledExpired or cancelled
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 25, 2026 | In progress | 2407 21st Av | repair leak: remove and replace affected shingles on deck in kind. repair water damaged drywall at affected areas. interior and exterior work, not visible from street. no stud or joist replacement, affected area approx. 256 sqft. | $2,000 |
| Sep 15, 2026 | In progress | 1371 45th Av | replace access steps for stairs that lead to yard from deck. replace a couple of rotted deck boards.c | $1,500 |
| May 21, 2026 | In progress | 2002 Bush St | revision to 202604089126. inspector requested structural plans for in kind stringer replacement due to dryrot. | $750 |
| May 11, 2026 | In progress | 280 Spear St | unit# 40-d. remove dry-wall around wall hung toilets. inspect framing around toilet. adjust framing if needed. | $2,500 |
| Apr 15, 2026 | In progress | 1664 Post St | work in front area for replace deck board, replace trim, replace siding front are everything will be replace with same material and design work will be performed on 2nd and 3rd flr. all work in kind. | $6,500 |
| Apr 8, 2026 | In progress | 2002 Bush St | replace siding around front stairs, replace steps, replace handrail, no structural work, all work in-kind. | $7,000 |
| Jan 22, 2026 | Completed | 2500 Pine St | dry rot repair. demo 15 sqft of stucco above garage door. street visible. | $2,500 |
| Nov 3, 2025 | Completed | 425 Staples Av | repair and replace concrete slab on drive way, garage and laurdry room area. street visible. | $2,500 |
| Dec 23, 2024 | Completed | 339 Chattanooga St | revision to 202411265778: add a pantry at kitchen | $1,000 |
| Nov 26, 2024 | Completed | 339 Chattanooga St | install pre-fabricated pantry in kitchen. replace one window in kind - not street visible. in kitchen, replace plumbing and electrical in kind for new washer/dryer. remove existing washer/dryer. | $9,500 |
| Nov 21, 2024 | Completed | 1558 Clay St | revision to pa# 2023-0321-4046 to document the removal of a ground floor, non load bearing wall dividing media room and hallway from original scope of work (per inspector b. tienda request). no other work proposed or authorized, dmj 11/22/204; | |
| Sep 25, 2024 | In progress | 5501 California St | to comply with the abe program abe#201811292684 | $1,000 |
| Jul 25, 2024 | Completed | 1604 Castro St | bath remodel, install new bath-tub at (e) shower location. | $17,000 |
| May 21, 2024 | Completed | 536 Taraval St | exterior dry rot stucco repair in kind located above garage left front side of property | $3,500 |
| Apr 15, 2024 | Completed | 45 San Benito Wy | bath remodel at second floor. half bath remodel at first floor. no change of layout/walls. | $38,000 |
| Mar 11, 2024 | Completed | 425 Staples Av | horizontal addition, 2nd floor wood deck with stairs to grade and interior remodel. | $352,777 |
| Jan 10, 2024 | In progress | 3386 Market St | raise wall from 1 to 2 feet. existing as 4 feet. | $1,500 |
| Dec 4, 2023 | Completed | 3386 Market St | 2 bathroom remodel. no change in location. plumbing and electrical. no walls removed. | $25,000 |
| Aug 31, 2023 | Completed | 122 Collins St | replacement 3 windows back of house, 2 at front and 1 at side. match (e) material. same operation. total 6 windows | $2,700 |
| Aug 31, 2023 | Completed | 80 Palm Av | 3 window replacement side building not facing the street | $1,500 |
| May 16, 2023 | Completed | 3386 Market St | replacing extg facade windows facing market st & windows, apply new stucco finish to facade facing elevation. | $80,000 |
| Mar 21, 2023 | Completed | 1558 Clay St | create new habitable spaces in the existing utility spaces at the g/f, including a kitchenette, a wine room, a gym, a media room and a bathroom. work to include new windows and doors in existing rough openings. | $180,000 |