Permit GraphShortlistSan Francisco building permits since 2000

Del Plata Builders Inc

Contractor license
1043451
State license record
Based in
San Francisco
On San Francisco permits
Jun 2019 to Oct 2026
Last 24 months
8 permits filed

25 permits since 2000: 18 completed, 4 in progress, 3 never finaled.

Of the 3 never-finaled permits, 3 are 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Bathroom remodel permits

AllDeck 1Stairs 7Kitchen remodel 3Bathroom remodel 8

8 bathroom remodel permits: 6 completed, 1 in progress, 1 never finaled. Typically 34 days from filing to permit and 228 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
Jun 24, 2026In progress
issued Jun 2026
2113 Broderick Stbasement level flooded. replace all finishes @ bathroom - living - tv room. replace cabinets + vanity + tile flooring and wall. replace can lights. all work in kind. no wall stud demolition or construction.
Details
Permit
202606243853
Status
issued
Filed
Jun 24, 2026
Permit issued
Jun 24, 2026
Declared cost
$80,000
Address
2113 Broderick St

basement level flooded. replace all finishes @ bathroom - living - tv room. replace cabinets + vanity + tile flooring and wall. replace can lights. all work in kind. no wall stud demolition or construction.

Open the permit page

$80,000
Jun 20, 2025Completed
final sign-off Oct 2025
131 10th Avbathroom remodel on 2nd floor with wall demolition and construction.
Details
Permit
202506209107
Status
complete
Filed
Jun 20, 2025
Permit issued
Jun 25, 2025
Final sign-off
Oct 15, 2025
Declared cost
$40,000
Address
131 10th Av

bathroom remodel on 2nd floor with wall demolition and construction.

Open the permit page

$40,000
Sep 30, 2024Completed
final sign-off Sep 2025
28 Hillway Avinfill lightwell (12 sq ft) including new roof and wall framing, remodel 2nd floor bathroom, install (n) skylight.
Details
Permit
202409301980
Status
complete
Filed
Sep 30, 2024
Permit issued
Jan 7, 2025
Final sign-off
Sep 17, 2025
Declared cost
$150,000
Address
28 Hillway Av

infill lightwell (12 sq ft) including new roof and wall framing, remodel 2nd floor bathroom, install (n) skylight.

Open the permit page

$150,000
Aug 22, 2023Completed
final sign-off Mar 2024
301 Mission Streplace in kind bath tile(3 bathrooms) plumbing fixtures and finishes, cabinets face and counter tops, elec finishes, remove dry wall bed #1, convert bath into powder room
Details
Permit
202308224911
Status
complete
Filed
Aug 22, 2023
Permit issued
Aug 23, 2023
Final sign-off
Mar 13, 2024
Declared cost
$100,000
Address
301 Mission St

replace in kind bath tile(3 bathrooms) plumbing fixtures and finishes, cabinets face and counter tops, elec finishes, remove dry wall bed #1, convert bath into powder room

Open the permit page

$100,000
Apr 21, 2021Completed
final sign-off May 2025
41 05th Avinstall residential elevator from basement to 3/f. reshingle exterior. enlarge garage door in-kind & partially re-brick entry steps & planter. 1/f remodel kitchen, add family room at rear. 2/f add 72 sf to rear bedroom. 3/f add gable roof to integrate previous roof remodels, enlarge & remodel bath,
Details
Permit
202104219055
Status
complete
Filed
Apr 21, 2021
Permit issued
May 10, 2023
Final sign-off
May 16, 2025
Declared cost
$427,065
Address
41 05th Av

install residential elevator from basement to 3/f. reshingle exterior. enlarge garage door in-kind & partially re-brick entry steps & planter. 1/f remodel kitchen, add family room at rear. 2/f add 72 sf to rear bedroom. 3/f add gable roof to integrate previous roof remodels, enlarge & remodel bath,

Open the permit page

$427,065
Mar 30, 2021Never finaled
issued Jun 2021, no final
1518 Guerrero Stthe scope of work is the remodel of an extg home office at level1 and the remodel of an extg bathroom at level 2. the addition of a spiral stair connectting the office to the unit above. the addition of a bathroom at level 1.
Details
Permit
202103307525
Status
issued
Filed
Mar 30, 2021
Permit issued
Jun 2, 2021
Declared cost
$50,000
Address
1518 Guerrero St

the scope of work is the remodel of an extg home office at level1 and the remodel of an extg bathroom at level 2. the addition of a spiral stair connectting the office to the unit above. the addition of a bathroom at level 1.

Open the permit page

$50,000
Sep 30, 2019Completed
final sign-off Jul 2020
20 Caselli Avremodel (e) bathroom, add one half bathroom @ 3rd level. no changes to exterior.
Details
Permit
201909303024
Status
complete
Filed
Sep 30, 2019
Permit issued
Feb 27, 2020
Final sign-off
Jul 1, 2020
Declared cost
$50,000
Address
20 Caselli Av

remodel (e) bathroom, add one half bathroom @ 3rd level. no changes to exterior.

Open the permit page

$50,000
Aug 2, 2019Completed
final sign-off Jun 2020
1584 08th Avinterior remodel to 2nd fl. reconfigure and remodel e bath. water closet same location. no horiz vert additions, no work visible from street
Details
Permit
201908027755
Status
complete
Filed
Aug 2, 2019
Permit issued
Aug 6, 2019
Final sign-off
Jun 3, 2020
Declared cost
$30,000
Address
1584 08th Av

interior remodel to 2nd fl. reconfigure and remodel e bath. water closet same location. no horiz vert additions, no work visible from street

Open the permit page

$30,000