Community Reconstruction Solutions
- Based in
- Burlingame
- On San Francisco permits
- May 2007 to Jul 2026
- Last 24 months
- 17 permits filed
178 permits since 2000: 156 completed, 2 in progress, 14 never finaled, 6 expired or cancelled.
Of the 14 never-finaled permits, 4 are 5 to 10 years old, 10 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Deck permits
21 deck permits: 19 completed, 1 never finaled, 1 expired or cancelled. Typically 0 days from filing to permit and 207 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 30, 2026 | Completed final sign-off Jun 2026 | 1904 Lyon St | exterior renovations. remove & replace deck coating on street facing side with westcoatsystem. remove & replace lap siding and cedar shingles associated with scope. sliding door is (e). install associated metal flashing, slider door pan and metal rail cap. misc wood repair, paint to match. in kind,Details
exterior renovations. remove & replace deck coating on street facing side with westcoatsystem. remove & replace lap siding and cedar shingles associated with scope. sliding door is (e). install associated metal flashing, slider door pan and metal rail cap. misc wood repair, paint to match. in kind, | $11,922 |
| Aug 26, 2025 | Completed final sign-off Mar 2026 | 945 Union St | exterior renovations and painting. remove and replace deck coating at (2) selected balconies (2w and 3w). misc. wood repair at (2) selected units (3w, 1e). install misc sheet metal. paint to match. like in kind. same size, same locations. common area project by hoa.Details
exterior renovations and painting. remove and replace deck coating at (2) selected balconies (2w and 3w). misc. wood repair at (2) selected units (3w, 1e). install misc sheet metal. paint to match. like in kind. same size, same locations. common area project by hoa. | $36,806 |
| Dec 7, 2022 | Completed final sign-off Sep 2024 | 200 Portola Dr | exterior renovations: balcony restorations at 10 locations (3201, 101, 202a, 202b, 102a, 102b, 230, 201 garage side, 101 garage side, 270). deni 12" + stucco perimeter, demo deck membrane, install westcoast pro system, install flashings, install deck drain, paint to match. topcoat balconies (7)totalDetails
exterior renovations: balcony restorations at 10 locations (3201, 101, 202a, 202b, 102a, 102b, 230, 201 garage side, 101 garage side, 270). deni 12" + stucco perimeter, demo deck membrane, install westcoast pro system, install flashings, install deck drain, paint to match. topcoat balconies (7)total | $63,368 |
| Mar 29, 2021 | Completed final sign-off Jul 2021 | 2009 Divisadero St | unit 3c remove and replace deck coatings and flashings. remove perimeter lap siding. westcoat rcx deck coating. paint to match existing. like in kindDetails
unit 3c remove and replace deck coatings and flashings. remove perimeter lap siding. westcoat rcx deck coating. paint to match existing. like in kind | $6,259 |
| Oct 25, 2019 | Completed final sign-off May 2020 | 2801 Jackson St | deck coating @ 3 decks w/westcoat alx.Details
deck coating @ 3 decks w/westcoat alx. | $4,679 |
| Dec 18, 2018 | Completed final sign-off Mar 2019 | 1488 Sanchez St | deck coating w/west coat alxDetails
deck coating w/west coat alx | $3,473 |
| May 19, 2017 | Completed final sign-off Aug 2017 | 63 Lafayette St | repair balcony deck, & patio deck. membranes. in kind only.Details
repair balcony deck, & patio deck. membranes. in kind only. | $7,300 |
| Mar 22, 2017 | Completed final sign-off May 2017 | 2506 Leavenworth St | deck balcony repair & sliding door replacement in-kind, not visible from street, less than 50%Details
deck balcony repair & sliding door replacement in-kind, not visible from street, less than 50% | $3,300 |
| Sep 1, 2016 | Completed final sign-off Jul 2017 | 1 Baker St | bldg b - working common area, 6 units form 5a to 6c. replace siding/trim/windows/deck coatings.Details
bldg b - working common area, 6 units form 5a to 6c. replace siding/trim/windows/deck coatings. | $180,898 |
| Sep 1, 2016 | Completed final sign-off Jul 2017 | 1 Baker St | bldg a - working common area. 12 units form 1a to 4c. replace siding/trim/windows/deck coatings.Details
bldg a - working common area. 12 units form 1a to 4c. replace siding/trim/windows/deck coatings. | $121,346 |
| Jul 26, 2016 | Never finaled issued Jul 2016, no final | 4155 Cesar Chavez St | replace 12 (e) sliding glass doors with (n) fiberglass doors at front of building-will match size and dimensions. recoat deck.Details
replace 12 (e) sliding glass doors with (n) fiberglass doors at front of building-will match size and dimensions. recoat deck. | $37,000 |
| Jun 16, 2016 | Expired or cancelled expired Jul 2026 | 1391 Clayton St | enlarge scope of work finish deck with ceramic tile. revision permit application # 201605066763. entire front of deck 2nd and 3rd floorsDetails
enlarge scope of work finish deck with ceramic tile. revision permit application # 201605066763. entire front of deck 2nd and 3rd floors | $14,500 |
| Nov 20, 2012 | Completed final sign-off Mar 2013 | 1011 23rd St | remove/replace deck membrane &tile surface @ back of buildingDetails
remove/replace deck membrane &tile surface @ back of building | $43,500 |
| Jun 26, 2012 | Completed final sign-off Oct 2012 | 575 Mangels Av | replace flashing at 5 doors & 6 windows. replace siding at rear elevation with cement lap siding w/ new trim. replace 3rd floor deck tile & membrane at rear elevation. all work not visible from street, no structural work.Details
replace flashing at 5 doors & 6 windows. replace siding at rear elevation with cement lap siding w/ new trim. replace 3rd floor deck tile & membrane at rear elevation. all work not visible from street, no structural work. | $18,000 |
| Oct 4, 2011 | Completed final sign-off Aug 2012 | 1900 Eddy St | revision to pa# 2009.12.11.3056 to comply with nov# 20068532. replace (e) deck and repair rotted substandard framing, install new water proofing. same for same.Details
revision to pa# 2009.12.11.3056 to comply with nov# 20068532. replace (e) deck and repair rotted substandard framing, install new water proofing. same for same. | $17,500 |
| Aug 6, 2010 | Completed final sign-off Feb 2011 | 937 Mcallister St | unit#913,915,917,921,923 - replace deck coating, repair dividing fence. unit #903-909 - replace 1 window, not visable from street, replace in kind. no structural changes, u-factor =0.40Details
unit#913,915,917,921,923 - replace deck coating, repair dividing fence. unit #903-909 - replace 1 window, not visable from street, replace in kind. no structural changes, u-factor =0.40 | $32,500 |
| Sep 22, 2008 | Completed final sign-off Feb 2010 | 903 Mcallister St | bldg 2: units 907-917 & 923-929 repair platform below fire escape. units 903-929 replace deck coating, repair dividing fences & gates. units 903-929 replace sliding doors, windows, & patch stucco.Details
bldg 2: units 907-917 & 923-929 repair platform below fire escape. units 903-929 replace deck coating, repair dividing fences & gates. units 903-929 replace sliding doors, windows, & patch stucco. | $137,187 |
| Sep 22, 2008 | Completed final sign-off Nov 2009 | 916 Buchanan St | bldg 5- units 916-944: repair platforms below fire escape. units 916-936: replace deck coating, repair dividing fences& gates. units 916-944: replace sliding glass doors and windows, patch stuccoDetails
bldg 5- units 916-944: repair platforms below fire escape. units 916-936: replace deck coating, repair dividing fences& gates. units 916-944: replace sliding glass doors and windows, patch stucco | $83,217 |
| Sep 22, 2008 | Completed final sign-off Nov 2009 | 636 Fulton St | bldg 6- units 636-644: repair platforms below fire escapes, replace deck coating, repair dividing fences and gates, replace sliding glass doors and windows, patch stucco.Details
bldg 6- units 636-644: repair platforms below fire escapes, replace deck coating, repair dividing fences and gates, replace sliding glass doors and windows, patch stucco. | $67,150 |
| Sep 22, 2008 | Completed final sign-off Nov 2009 | 803 Laguna St | bldg 3-units 819-837 replace deck coating, repair dividing fences & gates. units 815-837 replace sliding glass doors & windows. units 811,813,819-837 - repair platforms below fire escape.Details
bldg 3-units 819-837 replace deck coating, repair dividing fences & gates. units 815-837 replace sliding glass doors & windows. units 811,813,819-837 - repair platforms below fire escape. | $113,616 |
| Jul 20, 2007 | Completed final sign-off Jan 2008 | 290 Roosevelt Wy | repairs to address leakage, including reflashing and replacing selected doors and windows, localized tie ins to existing deck waterproofing, remove and replace stucco to facilitate repairs, replace e greenhouse, decay repairs as neededDetails
repairs to address leakage, including reflashing and replacing selected doors and windows, localized tie ins to existing deck waterproofing, remove and replace stucco to facilitate repairs, replace e greenhouse, decay repairs as needed | $124,920 |