Bluefield Construction
- Based in
- Hayward
- On San Francisco permits
- Jul 2013 to Jun 2026
- Last 24 months
- 3 permits filed
38 permits since 2000: 25 completed, 5 in progress, 3 never finaled, 5 expired or cancelled.
Of the 3 never-finaled permits, 1 is 3 to 5 years old, 1 is 5 to 10 years old, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for roof deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Roof deck permits
2 roof deck permits: 1 completed, 1 in progress. Typically 588 days from filing to permit and 374 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 7, 2022 | Completed final sign-off Jul 2023 | 2262 26th Av | 1st floor: add 2 bedroom, media and 2 full bath. 2nd floor: remodel kitchen, bathroom add 1 full bath. infill lightwell. add roof deck.Details
1st floor: add 2 bedroom, media and 2 full bath. 2nd floor: remodel kitchen, bathroom add 1 full bath. infill lightwell. add roof deck. | $120,000 |
| Aug 27, 2020 | In progress issued Oct 2023 | 54 Sunview Dr | attached adu addition in the rear per ordinance #162-16.roof deck/open space for adu, new windows. new garage doors.Details
attached adu addition in the rear per ordinance #162-16.roof deck/open space for adu, new windows. new garage doors. | $150,000 |