Bevilacqua & Sons
- Based in
- So San Francisco
- On San Francisco permits
- Jan 2000 to Aug 2026
- Last 24 months
- 21 permits filed
467 permits since 2000: 376 completed, 5 in progress, 61 never finaled, 25 expired or cancelled.
Of the 61 never-finaled permits, 4 are 3 to 5 years old, 18 are 5 to 10 years old, 39 are over 10 years old. 2 were filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Deck permits
6 deck permits: 2 completed, 2 never finaled, 2 expired or cancelled. Typically 42 days from filing to permit and 206 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 30, 2025 | Completed final sign-off Jan 2026 | 180 Geary St | remove existing sidewalk around existing elevator opening. attach new l 4x4 3/8 around inside of face of (e) sidewalk elevator opening concrete walls. weld (n) steel deck and place concrete topping over steel deck. place (n) sidewalk topping slab around (e) grade and over (n) opening elevatorDetails
remove existing sidewalk around existing elevator opening. attach new l 4x4 3/8 around inside of face of (e) sidewalk elevator opening concrete walls. weld (n) steel deck and place concrete topping over steel deck. place (n) sidewalk topping slab around (e) grade and over (n) opening elevator | $30,000 |
| Apr 12, 2022 | Completed final sign-off Nov 2022 | 108 Cole St | demo of restroom on 2nd fl, including accessories, adjacent bedroom closet and (1) water closet. at exterior, deck slats to be demo and replaced with (n). 2nd fl receives (2) restrooms with (n) floring and accessories.Details
demo of restroom on 2nd fl, including accessories, adjacent bedroom closet and (1) water closet. at exterior, deck slats to be demo and replaced with (n). 2nd fl receives (2) restrooms with (n) floring and accessories. | $100,000 |
| Aug 18, 2016 | Never finaled issued Oct 2016, no final | 600 Townsend St | demo & removal w/minor steel bracing of steel deck. replacement of hvac units with overall reduction in platform height. maher naDetails
demo & removal w/minor steel bracing of steel deck. replacement of hvac units with overall reduction in platform height. maher na | $75,000 |
| Jan 25, 2011 | Expired or cancelled cancelled Jun 2016 | 999 Brannan St | tube steel frame and glass block in-fill at 2nd story deck (front exterior)Details
tube steel frame and glass block in-fill at 2nd story deck (front exterior) | $8,000 |
| Jan 21, 2011 | Expired or cancelled withdrawn May 2016 | 999 Brannan St | tube steel frame and glass block infill at 2nd story deckDetails
tube steel frame and glass block infill at 2nd story deck | $8,000 |
| Dec 6, 2007 | Never finaled issued Dec 2007, no final | 595 Rhode Island St | improvement to patio areas, landscaping. exterior lighting including removal of (e) deck and construct new concrete stairs, retaining wall, slab on grade and trellis. revision to pa# 2006.04.21.9602Details
improvement to patio areas, landscaping. exterior lighting including removal of (e) deck and construct new concrete stairs, retaining wall, slab on grade and trellis. revision to pa# 2006.04.21.9602 | $20,000 |