Block 4175, lot 006
1201 Illinois St
The city’s assessor roll has no record for this parcel.
Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
13 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 15, 2017 | Never finaled issued Aug 2017, no final | 1201 Illinois St | Cape Environment Mnagement Inc | demolition of a 1-story haz mat storage shed in power plant.Details
demolition of a 1-story haz mat storage shed in power plant. | $15,000 |
| May 3, 2017 | Completed final sign-off Oct 2017 | 1201 Illinois St | T R C Solutions Inc. | disconnect and remove approx 1350 lf of above ground fire suppression piping at a former power plant (retired 2011). piping to be removed to facilitate access to 3 aboue ground storage tanks (being demo'd 2017-0317-1790. upstream piping to remain pressured; downstream piping to be converted to dryDetails
disconnect and remove approx 1350 lf of above ground fire suppression piping at a former power plant (retired 2011). piping to be removed to facilitate access to 3 aboue ground storage tanks (being demo'd 2017-0317-1790. upstream piping to remain pressured; downstream piping to be converted to dry | $15,000 |
| Mar 17, 2017 | Completed final sign-off Oct 2017 | 1201 Illinois St | Ferma Corporation | demolish 3 tanks in same lot 4175/006. maher ord n/a.Details
demolish 3 tanks in same lot 4175/006. maher ord n/a. | $54,000 |
| Mar 10, 2017 | Never finaled issued Jun 2017, no final | 1201 Illinois St | American Integrated Services Inc, Haley & Aldrich Construction Services | soil remediation: remove(e)utilities&buried struc excavte soil to 5-8' below grd surface.in site solidification of soil,jet grouting,replc(e)bulkhead w/new sheetpile bulkhead,backfill w/clean imported fill& instl/repair durable covers gravel,or asphalt pavement,demo,elec&plumb obtain seated/complianDetails
soil remediation: remove(e)utilities&buried struc excavte soil to 5-8' below grd surface.in site solidification of soil,jet grouting,replc(e)bulkhead w/new sheetpile bulkhead,backfill w/clean imported fill& instl/repair durable covers gravel,or asphalt pavement,demo,elec&plumb obtain seated/complian | $5,448,339 |
| Feb 7, 2017 | Completed final sign-off Oct 2017 | 1201 Illinois St | T R C Solutions Inc. | install access points in three above ground storage tanks and associated secondary containment walls to facilitate tank cleaning. maher naDetails
install access points in three above ground storage tanks and associated secondary containment walls to facilitate tank cleaning. maher na | $38,000 |
| Mar 15, 2016 | Completed final sign-off Jan 2021 | 1201 Illinois St | Cosco Fire Protection Inc. | install new fire sprinkler system in 1 story (29' high) substation plus basement. ref app#201407010205. n/a for maher ordinance no. 155-13.Details
install new fire sprinkler system in 1 story (29' high) substation plus basement. ref app#201407010205. n/a for maher ordinance no. 155-13. | $114,000 |
| Dec 22, 2015 | Completed final sign-off Sep 2020 | 1201 Illinois St | C. Overaa & Co | steel stair drawing (deferred submittal)Details
steel stair drawing (deferred submittal) | $50,000 |
| Jan 13, 2015 | Never finaled issued Jan 2015, no final | 1201 Illinois St | Haley & Aldrich Construction Services | removal and disposal of degraded cover materials and shallow soils. installation of durable cover per plan.Details
removal and disposal of degraded cover materials and shallow soils. installation of durable cover per plan. | $250,000 |
| Dec 2, 2014 | Never finaled issued Dec 2014, no final | 1201 Illinois St | street spaceDetails
street space | ||
| Oct 30, 2014 | Completed final sign-off May 2015 | 1201 Illinois St | revision appl 2014.0919.6865. installing additional 9ft chain link fence at 22nd strret and 80' chain link fence at humbolt street. maher n/a.Details
revision appl 2014.0919.6865. installing additional 9ft chain link fence at 22nd strret and 80' chain link fence at humbolt street. maher n/a. | $7,000 | |
| Sep 19, 2014 | Completed final sign-off May 2015 | 1201 Illinois St | replacing 210 ft of 7ft fence w/ 9ft high fence w/ barb wire. replacing existing 20ft long 7ft high gate w/ 9ft gate. replacing e 20ft long rolling gate w 9ft high rolling gate. replacing 465ft 7ft fence w 9ft fence, installing 285ft guardrail on 22nd st. area of work is in c section of property.Details
replacing 210 ft of 7ft fence w/ 9ft high fence w/ barb wire. replacing existing 20ft long 7ft high gate w/ 9ft gate. replacing e 20ft long rolling gate w 9ft high rolling gate. replacing 465ft 7ft fence w 9ft fence, installing 285ft guardrail on 22nd st. area of work is in c section of property. | $200,000 | |
| Jul 1, 2014 | Completed final sign-off Sep 2020 | 1201 Illinois St | C. Overaa & Co | demo & grading: remove ac pavement + subbase, concrete slabs, fencing, concrete walls, concrete pad & utilities. ground improvements: consist of concrete, ac paving, fencing & improving the density, strength & stifness of wet & loose soil. n/a ordinance #155-13Details
demo & grading: remove ac pavement + subbase, concrete slabs, fencing, concrete walls, concrete pad & utilities. ground improvements: consist of concrete, ac paving, fencing & improving the density, strength & stifness of wet & loose soil. n/a ordinance #155-13 | $140,000 |
| Feb 27, 2014 | Never finaled issued Mar 2014, no final | 1201 Illinois St | Haley & Aldrich Inc | perform iss testing on 2 areas (a & b) to solidify subsurface soil. remove and replace pavement. compliance with maher ordinance #155-13 required; routed to dph.Details
perform iss testing on 2 areas (a & b) to solidify subsurface soil. remove and replace pavement. compliance with maher ordinance #155-13 required; routed to dph. | $700,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- C. Overaa & Co (2), Haley & Aldrich Construction Services (2), T R C Solutions Inc. (2), American Integrated Services Inc, Cape Environment Mnagement Inc, Cosco Fire Protection Inc., Ferma Corporation, Haley & Aldrich Inc
- Engineers
- Hui Li (2), Mennor Chan
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.