Block 3775, lot 048
22 South Park
- City’s use
- Commercial Hotel
- Built
- 1915
- Stories
- 3
- Units
- 3
- Rooms
- 16 bathrooms
- Building
- 12,729 sq ft
- Lot
- 4,893 sq ft
- Zoning
- SPD
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
15 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 12, 2023 | Completed final sign-off Sep 2023 | 22 South Park | Pac Integrations Inc | common areas/kitchens 2&3: add magnetic door holders on (2) kitchen doors, smoke detectors in (2) kitchen rooms.Details
common areas/kitchens 2&3: add magnetic door holders on (2) kitchen doors, smoke detectors in (2) kitchen rooms. | $6,000 |
| May 24, 2023 | Completed final sign-off Aug 2023 | 22 South Park | Saarman Construction,Ltd. | mitigate water infilltration at light well due to main water leaking into basement this includes removing bottom of siding, epoxy application to concrete, and waterproofing.Details
mitigate water infilltration at light well due to main water leaking into basement this includes removing bottom of siding, epoxy application to concrete, and waterproofing. | $95,317 |
| Mar 28, 2023 | Never finaled issued Apr 2023, no final | 22 South Park | Saarman Construction,Ltd. | repair exterior awning at madrid, new paint and laminated safety glass.Details
repair exterior awning at madrid, new paint and laminated safety glass. | $73,000 |
| Sep 22, 2021 | Completed final sign-off Mar 2022 | 22 South Park | Emkjer Enterprises Inc Dba Sign Co Usa | evacuation maps and installationDetails
evacuation maps and installation | $3,660 |
| Jun 21, 2021 | Completed final sign-off Jan 2022 | 22 South Park | Pac Integrations Inc | as-built changes to approved plan (pa #2021-0331-7660 r1). had to change legend symbol from wall to ceiling room horns and some hallway horn strobes. made some hallway h/s strobe only due to high sound levels, added a 2nd tamper switch, change both room h/s to strobe only, change make & model of lfhDetails
as-built changes to approved plan (pa #2021-0331-7660 r1). had to change legend symbol from wall to ceiling room horns and some hallway horn strobes. made some hallway h/s strobe only due to high sound levels, added a 2nd tamper switch, change both room h/s to strobe only, change make & model of lfh | |
| May 19, 2021 | Completed final sign-off Oct 2021 | 22 South Park | Ayoob & Peery Plumbing Co Inc | 1st floor: as-built for #2020-0904-3778. relocate (7) and change out (1) sprinkler. basement: add (3), relocate (7) and change out (4) sprinklers per t.i.Details
1st floor: as-built for #2020-0904-3778. relocate (7) and change out (1) sprinkler. basement: add (3), relocate (7) and change out (4) sprinklers per t.i. | |
| May 17, 2021 | Completed final sign-off Mar 2022 | 22 South Park | Bbi - Con Inc | revision to pa# 201912189908. sow: addition of power door operator in lieu of level landing due to (e) site conditions. (n) casework in unit 101. (n) utiliy sink at mep room. no other changes in this revision. no work in prow.Details
revision to pa# 201912189908. sow: addition of power door operator in lieu of level landing due to (e) site conditions. (n) casework in unit 101. (n) utiliy sink at mep room. no other changes in this revision. no work in prow. | $45,000 |
| Mar 31, 2021 | Completed final sign-off Jan 2022 | 22 South Park | Pac Integrations Inc | as built changes to approved plan/permit # 2020-0912-4009 !. due to items discovered during construction new conduit and wire was installed to all existing notification device. 2. due to plan changes the elevator equipment room was relocated. 3. door swings to lunch room were changed.Details
as built changes to approved plan/permit # 2020-0912-4009 !. due to items discovered during construction new conduit and wire was installed to all existing notification device. 2. due to plan changes the elevator equipment room was relocated. 3. door swings to lunch room were changed. | |
| Sep 12, 2020 | Completed final sign-off Mar 2022 | 22 South Park | Pac Integrations Inc | modify (e) fire alarm systemDetails
modify (e) fire alarm system | $50,000 |
| Sep 9, 2020 | Completed final sign-off Oct 2021 | 22 South Park | Ayoob & Peery Plumbing Co Inc | 1st fl tenant improvement: add 1 and relocate 5 sprinklers to conform with the wall/ ceiling layout of the tenant improvement. ref pa# 201912189908Details
1st fl tenant improvement: add 1 and relocate 5 sprinklers to conform with the wall/ ceiling layout of the tenant improvement. ref pa# 201912189908 | $1,650 |
| Aug 5, 2020 | Never finaled issued Aug 2020, no final | 24 South Park | street spaceDetails
street space | ||
| Dec 18, 2019 | Completed final sign-off Mar 2022 | 22 South Park | Bbi - Con Inc | rehab/renovaiton improvement to sro (n) interiors. new mep. fire alarm & sprinkler deferred. repair & replace roofing drains gutters, repair exterior paint in kind. maher na.Details
rehab/renovaiton improvement to sro (n) interiors. new mep. fire alarm & sprinkler deferred. repair & replace roofing drains gutters, repair exterior paint in kind. maher na. | $2,100,000 |
| Jul 24, 2017 | Expired or cancelled withdrawn Dec 2019 | 22 South Park | residential: seismic retrofit to comply with mandotary soft story ordinace per sfebc chapter 4d, asce41-13, to comly with nov#201642251, a residential hotel. maher ordinance not required.Details
residential: seismic retrofit to comply with mandotary soft story ordinace per sfebc chapter 4d, asce41-13, to comly with nov#201642251, a residential hotel. maher ordinance not required. | $25,000 | |
| Jul 24, 2017 | Expired or cancelled withdrawn Dec 2019 | 22 South Park | commercial: seismic retrofit to comply with mandotary soft story ordinace per sfebc chapter 4d, asce41-13, to comly with nov#201642251, a residential hotel. maher ordinance not required.Details
commercial: seismic retrofit to comply with mandotary soft story ordinace per sfebc chapter 4d, asce41-13, to comly with nov#201642251, a residential hotel. maher ordinance not required. | $25,000 | |
| Aug 16, 2011 | Completed final sign-off Apr 2012 | 22 South Park | Ameritech | fire alarm system upgrade. new system & sprinkler monitoring: 80 horn/strobes; 21 smoke detectors; 1 pull station; 2 modulesDetails
fire alarm system upgrade. new system & sprinkler monitoring: 80 horn/strobes; 21 smoke detectors; 1 pull station; 2 modules | $10,000 |