Block 1430, lot 044
212 04th Ave
- City’s use
- Multi-Family Residential
- Built
- 1904
- Stories
- 3
- Units
- 8
- Rooms
- 9 bathrooms
- Building
- 11,400 sq ft
- Lot
- 6,424 sq ft
- Zoning
- RM1
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
33 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 25, 2026 | In progress issued Feb 2026 | 212 04th Av | G M Building And Construction Inc | recommencement and completion of work approved under pa#202407226993Details
recommencement and completion of work approved under pa#202407226993 | $42,000 |
| Feb 25, 2026 | In progress issued Feb 2026 | 214 04th Av | G M Building And Construction Inc | recommencement and completion of work approved under pa#202411014204Details
recommencement and completion of work approved under pa#202411014204 | $67,000 |
| Feb 25, 2026 | In progress issued Feb 2026 | 210 04th Av | G M Building And Construction Inc | recommencement and completion of work approved under pa#202407176707Details
recommencement and completion of work approved under pa#202407176707 | $57,000 |
| Feb 25, 2026 | In progress issued Feb 2026 | 208 04th Av | G M Building And Construction Inc | recommencement and completion of work approved under pa#202407176703Details
recommencement and completion of work approved under pa#202407176703 | $57,000 |
| Dec 3, 2025 | Completed final sign-off Mar 2026 | 200 04th Av | Fog City Roofiing Llc | re-roofing ( overlaying composition chingles.) no hot works.Details
re-roofing ( overlaying composition chingles.) no hot works. | $73,900 |
| Sep 3, 2025 | In progress issued Sep 2025 | 200 04th Av | G M Building And Construction Inc | revision to pa# 202405242971 & 202412106484: remodel 5 bathrooms on 3/f; change 5 windows for egress; provide rated walls as shown; show reinforced floor joists and reduce beam span with new walsl and posts; replace wall heaters to furnace and tank to tankless water heaters; new drywall throughout,Details
revision to pa# 202405242971 & 202412106484: remodel 5 bathrooms on 3/f; change 5 windows for egress; provide rated walls as shown; show reinforced floor joists and reduce beam span with new walsl and posts; replace wall heaters to furnace and tank to tankless water heaters; new drywall throughout, | $200,000 |
| Dec 10, 2024 | In progress issued Dec 2024 | 200 04th Av | P Jordan Builders Llc | voluntary adding plywood at existing walls at partial basement, entire first, second and third floor and simpson strong walls at front on 4th avenue, finished with 5/8" type x gyp board at each side of walls.Details
voluntary adding plywood at existing walls at partial basement, entire first, second and third floor and simpson strong walls at front on 4th avenue, finished with 5/8" type x gyp board at each side of walls. | $30,000 |
| Nov 1, 2024 | In progress issued Nov 2024 | 214 04th Av | G M Building And Construction Inc | remodel ktichen & bathroom in-kind. remove cabinet lath & plaster. electrical and plumbing fixtures as neededDetails
remodel ktichen & bathroom in-kind. remove cabinet lath & plaster. electrical and plumbing fixtures as needed | $45,000 |
| Jul 22, 2024 | In progress issued Jul 2024 | 212 04th Av | G M Building And Construction Inc | renovate kitchen and batroom in-kind remove latch and plaster kitchen batroom hallways bedroom, provide 5/8 gypsum where needed electrical and plumbing as needed. no wall removalDetails
renovate kitchen and batroom in-kind remove latch and plaster kitchen batroom hallways bedroom, provide 5/8 gypsum where needed electrical and plumbing as needed. no wall removal | $45,000 |
| Jul 18, 2024 | In progress issued Jul 2024 | 208 04th Av | G M Building And Construction Inc | recommencement and completion of work approved under pa#2012-0724-5657Details
recommencement and completion of work approved under pa#2012-0724-5657 | |
| Jul 17, 2024 | In progress issued Jul 2024 | 208 04th Av | G M Building And Construction Inc | renovate 1 kitchen and 1 bathroom in kind remove latch and plaster as needed (in kitchen and bath) upgrade electrical and plumbing no wall removalDetails
renovate 1 kitchen and 1 bathroom in kind remove latch and plaster as needed (in kitchen and bath) upgrade electrical and plumbing no wall removal | $45,000 |
| Jul 17, 2024 | In progress issued Jul 2024 | 210 04th Av | G M Building And Construction Inc | remodel 1 kitchen and 1 bathroom in kind remove latch and plaster as needed (in kitchen and bath) upgrade electrical and plumbing as needed no wall removalDetails
remodel 1 kitchen and 1 bathroom in kind remove latch and plaster as needed (in kitchen and bath) upgrade electrical and plumbing as needed no wall removal | $45,000 |
| May 30, 2024 | In progress issued May 2024 | 202 04th Av | G M Building And Construction Inc | remodel kitchen and bathroom in kind. remove less than 50% lath and plaster. provide 5/8 fire rate sheet rock as needed. electrical and plumbing as needed.Details
remodel kitchen and bathroom in kind. remove less than 50% lath and plaster. provide 5/8 fire rate sheet rock as needed. electrical and plumbing as needed. | $45,000 |
| May 30, 2024 | In progress issued May 2024 | 206 04th Av | G M Building And Construction Inc | renovate (e) bathroom and kitchen in-kind. remove lathe & plaster 50% as needed to upgrade electricla and plumbing as needed.Details
renovate (e) bathroom and kitchen in-kind. remove lathe & plaster 50% as needed to upgrade electricla and plumbing as needed. | $45,000 |
| May 30, 2024 | In progress issued May 2024 | 204 04th Av | G M Building And Construction Inc | to comply nov complaint #201940132. replace in kind back stair less than 50% w/ p.t. 2x12.Details
to comply nov complaint #201940132. replace in kind back stair less than 50% w/ p.t. 2x12. | $14,950 |
| May 24, 2024 | In progress issued May 2024 | 200 04th Av | G M Building And Construction Inc | remodel kitchen and bathroom in kind. remove lath and plaster less than 50% - provide 5/8 fire rated sheetrock as needed. plumbing and electrical as needed.Details
remodel kitchen and bathroom in kind. remove lath and plaster less than 50% - provide 5/8 fire rated sheetrock as needed. plumbing and electrical as needed. | $45,000 |
| May 24, 2024 | In progress issued May 2024 | 204 04th Av | G M Building And Construction Inc | to comply w/ nov# 201935741: remodel unit kitchen and bathroom in kind. remove lath and plaster less than 50% provide 5/8 fire rate sheetrock as needed. plumbing and electrical as needed.Details
to comply w/ nov# 201935741: remodel unit kitchen and bathroom in kind. remove lath and plaster less than 50% provide 5/8 fire rate sheetrock as needed. plumbing and electrical as needed. | $45,000 |
| Oct 15, 2019 | Completed final sign-off Jun 2020 | 210 04th Av | Y D Construction Co. Inc. | kitchen and bathroom remodel in kind.Details
kitchen and bathroom remodel in kind. | $15,000 |
| Jun 26, 2019 | Never finaled issued Jun 2019, no final | 200 04th Av | street spaceDetails
street space | ||
| Jan 16, 2018 | Completed final sign-off Sep 2019 | 200 04th Av | Tai Lam Mak | soft story retrofit per sfebc chapter 4d: 2016 cebc cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d: 2016 cebc cebc appendix a-4 | $75,000 |
| Nov 22, 2016 | Completed final sign-off Jan 2017 | 200 04th Av | Y D Construction Co. Inc. | to obtain a final inspectoin for work approved under pa#201301178182 & 201507131282. all work is complete.Details
to obtain a final inspectoin for work approved under pa#201301178182 & 201507131282. all work is complete. | |
| Jul 13, 2015 | Never finaled issued Jul 2015, no final | 200 04th Av | Y D Construction Co. Inc. | to comply with his nov# 201484741: correct violation #3, 9, and 10. handrail repairing in kind and in basement for installation of hot water heater, repair wiring.Details
to comply with his nov# 201484741: correct violation #3, 9, and 10. handrail repairing in kind and in basement for installation of hot water heater, repair wiring. | $2,000 |
| Feb 12, 2013 | Expired or cancelled cancelled Nov 2016 | 200 04th Av | Kin Fai Construction Co. | remove extg un permitted railings at roof top. to comply with nov #201268561. repair deteriorated stairs on item 2 of #201268561Details
remove extg un permitted railings at roof top. to comply with nov #201268561. repair deteriorated stairs on item 2 of #201268561 | $2,000 |
| Jan 17, 2013 | Never finaled issued Jan 2013, no final | 200 04th Av | Jian Lou Construction Co. | repair/replace some stair treads, hand/guard raisl landing (less than 50%) nov #201268561Details
repair/replace some stair treads, hand/guard raisl landing (less than 50%) nov #201268561 | $800 |
| Jul 24, 2012 | Never finaled issued Jul 2012, no final | 206 04th Av | Kin Fai Construction Co. | replace or repair kitchen tiles. need district inspector to verify the roof deck.Details
replace or repair kitchen tiles. need district inspector to verify the roof deck. | $550 |
| Jul 24, 2012 | Never finaled issued Jul 2012, no final | 208 04th Av | Kin Fai Construction Co. | replace or repair kitchen cabinet & tiles. need district inspector to verify the roof deck.Details
replace or repair kitchen cabinet & tiles. need district inspector to verify the roof deck. | $4,000 |
| Jan 5, 2012 | Expired or cancelled cancelled Jan 2026 | 200 04th Av | Ground Up Construction Dba Edge Roofing | remove & replace 49 windows, some seen from street, vinyl to aluminum clad wood hung windows, same size, same location, replace in kind.Details
remove & replace 49 windows, some seen from street, vinyl to aluminum clad wood hung windows, same size, same location, replace in kind. | $5,000 |
| Jun 23, 2011 | Never finaled issued Jun 2011, no final | 200 04th Av | additional to m265866-street space permitDetails
additional to m265866-street space permit | ||
| Dec 3, 2010 | Completed final sign-off Feb 2011 | 200 04th Av | Kin Fai Construction Co. | to comply with nov 201078406; convert one bath to two baths & remodel kitchen on second floor unit #202 only.Details
to comply with nov 201078406; convert one bath to two baths & remodel kitchen on second floor unit #202 only. | $18,000 |
| Aug 21, 2009 | Expired or cancelled expired Dec 2010 | 200 04th Av | Current Construction Co. | replace in kind 61 existing windows.new windows to be wood sash double hung 3 x 2 and 3 x 4 muntin. comply with nov 200854850.Details
replace in kind 61 existing windows.new windows to be wood sash double hung 3 x 2 and 3 x 4 muntin. comply with nov 200854850. | $24,000 |
| Feb 1, 2008 | Never finaled issued Feb 2008, no final | 200 04th Av | street space for scaffoldDetails
street space for scaffold | ||
| Nov 28, 2007 | Completed final sign-off Mar 2009 | 200 04th Av | Y D Construction Co. Inc. | repair (e) brick foundation by constructing a new supplemental, reinforcing conrete foundation/retaining wall along east side. structural work only, no internal remodelling or exterior work in this permit.Details
repair (e) brick foundation by constructing a new supplemental, reinforcing conrete foundation/retaining wall along east side. structural work only, no internal remodelling or exterior work in this permit. | $50,000 |
| May 24, 2007 | Completed final sign-off Mar 2009 | 200 04th Av | repair back stairs and exterior paint, less than 50%, in kind repair only.Details
repair back stairs and exterior paint, less than 50%, in kind repair only. | $8,800 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- G M Building And Construction Inc (15), Kin Fai Construction Co. (4), Y D Construction Co. Inc. (4), Current Construction Co., Fog City Roofiing Llc, Ground Up Construction Dba Edge Roofing, Jian Lou Construction Co., P Jordan Builders Llc, Tai Lam Mak
- Architects
- Simon Kwan
- Engineers
- Horon Lee, Lok C. Kwan
Find contractors for work like this