Block 0596, lot 024
1595 Pacific Av
47 permits filed for this property since 2000.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 19, 2024 | Completed | 1595 Pacific Av | Bay Alarm Company | to verify existing sound levels in sleeping areas, complying with sffc sec 1103.7.6.1 | |
| Oct 28, 2019 | Completed | 1998 Polk St | Upkeep Industries Inc | ti minor modification of food service area. replace 4 exterior light fixtures and replace exterior deco tiles | $8,800 |
| Jul 21, 2017 | Expired or cancelled | 1998 Polk St | minor modification to (e) belcampo restaurant dining area. includes demo non-bearing partition walls, demo of (e) built in seating banquettes & tables, installation of new dining table and chairs (including ada seat) and 4 new duplex outlets | $25,000 | |
| Mar 3, 2015 | Completed | 1958 Polk St | Leonardo Construction Inc | to erect non electric double faced sign | $250 |
| Dec 31, 2014 | Completed | 1958 Polk St | James A Keenan | addendum - revision to scope of work, removal of arches, new structural plans submitted rendering special inspections not required revision to permit 201401105974 | |
| Sep 8, 2014 | Never finaled | 1958 Polk St | Magnum Construction Group Inc | extent existing pendent heads to new ceiling height; total 7 heads pa# 201401105974 | $4,000 |
| Aug 21, 2014 | Completed | 1998 Polk St | record change of use from limited restaurant to restaurant. add full size sheet of conditions to bpa. all t.i. construction has been completed under bpa 201306129363. | ||
| Jul 30, 2014 | Never finaled | 1942 Polk St | Cim Group Inc | revision to app#201406249332. change address from 1595 pacific ave to 1942 polk st. same block and lot number. | |
| Jun 24, 2014 | Never finaled | 1595 Pacific Av | James A Keenan | revision to appl #2013.0930.8064 - changed framing from wood to metal framing, non-combustable. | |
| Jun 9, 2014 | Never finaled | 1595 Pacific Av | street space | ||
| May 23, 2014 | Never finaled | 1998 Polk St | Ewingcraft | to erect electrical wall sign | $4,500 |
| May 22, 2014 | Never finaled | 1998 Polk St | Artisan Awning Co | install 5 new awnings, no signage on awnings. all 48" projection, 2 @ 10-1/6" w x 3 @ 7-1/6" w. all with min. 8' clearance from sidewalk. | $4,000 |
| May 8, 2014 | Never finaled | 1595 Pacific Av | Mina-Tree Signs, Inc | install (1) illuminated double faced projecting sign | $2,500 |
| May 8, 2014 | Never finaled | 1595 Pacific Av | Mina-Tree Signs, Inc | install (1) illuminated wall sign | $3,000 |
| May 6, 2014 | Expired or cancelled | 1998 Polk St | hanging of exhaust hoods ref 201306129363, 201312093702 | $7,000 | |
| Apr 10, 2014 | Expired or cancelled | 1998 Polk St | Terra Nova Industries | mechanical for the installation of the smog hog captive air systems. arch under 201306129363, mep 201312093702 | $30,000 |
| Apr 9, 2014 | Completed | 1595 Pacific Av | Firemaster | furnish and install one (1) ansul fire system in he main kitchen area. | $2,500 |
| Mar 26, 2014 | Completed | 1998 Polk St | Cosco Fire Protection Inc. | ground floor - design & install new fire alarm devices for property protection for a tenant improvement space. | $9,557 |
| Mar 21, 2014 | Completed | 1998 Polk St | Certified Fire & Safety Co | install ul300 fire system to protect pollition control unit located in duct end on roof of bldg. ref app#201306129363 | $5,000 |
| Mar 21, 2014 | Completed | 1998 Polk St | Cisco Fire Sprinklers, Inc. | fire sprinkler tenant improvements effecting 18 new sprinklers in new ceilings. ref. appl. 201306129363. | $8,000 |
| Mar 12, 2014 | Completed | 1998 Polk St | Integrity Air Systems Corporation | replace existing 20x20 grease duct in shaft with new 16x16 gease duct. new grease duct to have cleanout on every floor and have 2 layers thermal ceramics fire master (ul g18) duct wrap. ref. 201306129363 | $14,000 |
| Mar 5, 2014 | Completed | 1998 Polk St | Terra Nova Industries | clarification to 201306129363. verification of occupant load for assembly space. spearate assembly permit required | |
| Jan 10, 2014 | Completed | 1958 Polk St | James A Keenan | first time tenant improvement, install new kitchen & one ada restroom, new counters, new finishes & lighting, add 210 sf mezzanine partially oever adjacent tenant space & add spiral stair for access. replace fixed window with operable winodw. | $131,000 |
| Dec 9, 2013 | Completed | 1998 Polk St | Terra Nova Industries | structural work for new mezzanine and roof mechanical equipment platform. t.i. under pa#2013-06-12-9363. | $50,000 |
| Dec 9, 2013 | Completed | 1998 Polk St | Terra Nova Industries | mep work associated with tenant improvement pa#2013-0612-9363. captive-air system under separate permit | $100,000 |
| Sep 30, 2013 | Never finaled | 1595 Pacific Av | Cim Group Inc | non-structural demo, new raised floor. new drywall partitions and ceiling, new electrical, subpanel,lighting. install new atm. alarm/video equipment, finishes.sprinklers separate permit. frontage not more than 11'-0". interior not to exceed 150 s.f. | $14,300 |
| Jun 12, 2013 | Completed | 1998 Polk St | Terra Nova Industries | this appln is for a first time tenant improvement at the above address. no physical changes to the exterior of the bldg will occur. we would like to begin the neighborhood notification prior to submitting full cds. mech under seperate permit. | $250,000 |
| May 20, 2013 | Expired or cancelled | 1595 Pacific Av | Palisade Builders Inc | roof level - install four (4) new sprinklers to project currently in construciton - as built. | $2,000 |
| Mar 19, 2013 | Never finaled | 1595 Pacific Av | Ross Douglas Construction | revision to 2007-11-14-8042 s/1 to supplement construction documents. steel stairs-wood trusses-mechanical equip anchorage. electrical switchgear anchorage-window washing system. | |
| Feb 15, 2013 | Never finaled | 1595 Pacific Av | street space | ||
| Dec 14, 2012 | Never finaled | 1595 Pacific Av | street space permit | ||
| Nov 21, 2012 | Completed | 1595 Pacific Av | Ross Douglas Construction | clarification to building permit #2007-11-14-8042s/s1-addendum #2-architectural finishes clarified on drawings. per planning dept request. | |
| Nov 7, 2012 | Completed | 1595 Pacific Av | Weidner Architectural Signage | fabricate and install evacuation plans (20) | $6,000 |
| Jul 3, 2012 | Completed | 1595 Pacific Av | Ross Douglas Construction | revision to pa# 2007-1114-8042-addendum #2-use og cpvc pipe & fitness in lieu of copper piping | |
| May 3, 2012 | Expired or cancelled | 1595 Pacific Av | J. Flores Construction Company Inc | installation of fire servcie underground. approved oh sprinkler under pa # 2012-0228-5003 | |
| Feb 28, 2012 | Completed | 1595 Pacific Av | Thorpe Design Inc | install (n) nfpa 13 overhead fire sprinkler system & (n) nfpa 14 standpipe. sprinkler underground separate permit. | $100,000 |
| Feb 28, 2012 | Completed | 1595 Pacific Av | S J Cimino Electric, Inc. | install (n) fire alarm panel w/ smoke detectors, heat detectors, moduals to supervise water flow, tampers. add moduals to activate horns/strobes to evacuate bldg. add moduals to control elevator recall, install communicator to call monitor station for proper dispatch (rev #200711148042) | $22,000 |
| Jan 17, 2012 | Completed | 1595 Pacific Av | Ross Douglas Construction | refer to pa# 2007-1114-8042/s1-engineered shoring design for construction of foundation | $35,000 |
| Dec 20, 2011 | Completed | 1595 Pacific Av | Ross Douglas Construction | structural revisions to approved pa #200711148042-s1 per field conditions & contractor coordination. | |
| Dec 1, 2011 | Completed | 1595 Pacific Av | Ross Douglas Construction | revision to drilled pier approved under 200711148042 s1 | |
| Jul 7, 2011 | Never finaled | 1595 Pacific Av | change address on existing block lot from 1591 pacific ave to 1595 pacific ave. | ||
| Jul 7, 2011 | Never finaled | 1958 Polk St | add two new address for futre commercial units. | ||
| Apr 27, 2010 | Never finaled | 1942 Polk St | street space, sidewalk repair and mta parking | ||
| May 29, 2009 | Completed | 1946 Polk St | Evans Signs | new electric wall sign | $5,000 |
| May 29, 2009 | Completed | 1946 Polk St | Stars Awning Co Inc | change copy on existing sign | $1,400 |
| Nov 14, 2007 | Completed | 1946 Polk St | Ross Douglas Construction, Johnstone Moyer Inc | demolition of two -story retail sale. | $24,000 |
| Nov 14, 2007 | Completed | 1591 Pacific Av | Johnstone Moyer Inc | construction of type 5 over 1 5-story 41 dwelling units/retail space. | $15,312,408 |