Block 0467A, lot 011
3535 Fillmore St
- City’s use
- Multi-Family Residential
- Built
- 1929
- Stories
- 3
- Units
- 12
- Rooms
- 15 bathrooms
- Building
- 12,702 sq ft
- Lot
- 5,392 sq ft
- Zoning
- RH3
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
18 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 13, 2024 | Completed final sign-off Jun 2024 | 3535 Fillmore St | Crime Watch Security Sys Llc | upgrade existing fire alarm system to comply with sffc section 1103.7.6.1. installation of low frequency sounders in all living and bedrooms.Details
upgrade existing fire alarm system to comply with sffc section 1103.7.6.1. installation of low frequency sounders in all living and bedrooms. | $36,720 |
| Sep 19, 2020 | Completed final sign-off Nov 2021 | 3535 Fillmore St | Cpb Construction Corporation | apt 304: 4/f: relocate kitchen, convert (e) kitchen to (n) bedroom, rmeodel (e) bathroom, conver (e) closet to (n) bathroom, (n) laundry. no exterior work.Details
apt 304: 4/f: relocate kitchen, convert (e) kitchen to (n) bedroom, rmeodel (e) bathroom, conver (e) closet to (n) bathroom, (n) laundry. no exterior work. | $45,000 |
| Nov 12, 2019 | Completed final sign-off Mar 2020 | 3535 Fillmore St | Sft Construction Corp | supercede previously approved soft story retrofit app#20170403017. change engineer. comply with 2016 sfebc chapter 4d per 2016 cebc appendix a-4Details
supercede previously approved soft story retrofit app#20170403017. change engineer. comply with 2016 sfebc chapter 4d per 2016 cebc appendix a-4 | |
| Aug 27, 2018 | Expired or cancelled cancelled Jan 2026 | 3535 Fillmore St | work only in unit #204 at 3rd flr - relocate kitchen. connvert kitchen room in new bedroom. remodel (e) bath. convert (e) closet into new bath. new laundry maher naDetails
work only in unit #204 at 3rd flr - relocate kitchen. connvert kitchen room in new bedroom. remodel (e) bath. convert (e) closet into new bath. new laundry maher na | $30,000 | |
| Aug 25, 2017 | Never finaled issued Feb 2018, no final | 3535 Fillmore St | Flores General Building | units #103 & #202; remodel, install new bedroomn and bathroom for total of 2 bdroom & 2 bath in each unit: relocate non structural walls. relocate extg kitchen, renovate extg bath, new cabinets, appliances, finishes; new plumbing and electrical. n/a maher ordinanceDetails
units #103 & #202; remodel, install new bedroomn and bathroom for total of 2 bdroom & 2 bath in each unit: relocate non structural walls. relocate extg kitchen, renovate extg bath, new cabinets, appliances, finishes; new plumbing and electrical. n/a maher ordinance | $40,000 |
| Jun 28, 2017 | Expired or cancelled cancelled Jul 2024 | 3535 Fillmore St | convert (e) garage into (4)(n) units @ grnd flr (ord no 162-16). soft story pa #2017-0403-3017. area of work & egress path to be sprinklered. entire grnd flr ceiling assembly to be upgraded to a 1-hr rated assembly per information sheet sf-05. structural covered by separate permit.Details
convert (e) garage into (4)(n) units @ grnd flr (ord no 162-16). soft story pa #2017-0403-3017. area of work & egress path to be sprinklered. entire grnd flr ceiling assembly to be upgraded to a 1-hr rated assembly per information sheet sf-05. structural covered by separate permit. | $140,000 | |
| Jun 9, 2017 | Never finaled issued Jun 2017, no final | 3535 Fillmore St | G R C Roofing Inc. | re-roofingDetails
re-roofing | $48,000 |
| Apr 3, 2017 | Completed final sign-off Mar 2020 | 3535 Fillmore St | soft story retrofit per sfbc chapter 34b:2012 iebc appendix a-4. add anchor sill bolting, shearwalls, 4 ordinary moment frames located at front opening and middle of bldg at ground floor.Details
soft story retrofit per sfbc chapter 34b:2012 iebc appendix a-4. add anchor sill bolting, shearwalls, 4 ordinary moment frames located at front opening and middle of bldg at ground floor. | $85,000 | |
| Nov 23, 2015 | Completed final sign-off Apr 2016 | 3535 Fillmore St | Flores General Building | unit 303, add 1 bathroom, relocate kitchen, move non bearing walls, remodel (e) bathroom, drywall, paint & refinish floors. add bedroom where kitchenDetails
unit 303, add 1 bathroom, relocate kitchen, move non bearing walls, remodel (e) bathroom, drywall, paint & refinish floors. add bedroom where kitchen | $45,000 |
| Nov 23, 2015 | Never finaled issued Nov 2015, no final | 3535 Fillmore St | Flores General Building | unit #201: convert (e) closet to bathroom, relocate kitchen, move non bearing walls, drywall, paint and refinish hardwood floors, convert (e) kitchen to office. maher naDetails
unit #201: convert (e) closet to bathroom, relocate kitchen, move non bearing walls, drywall, paint and refinish hardwood floors, convert (e) kitchen to office. maher na | $45,000 |
| Sep 15, 2015 | Completed final sign-off Jan 2016 | 3535 Fillmore St | Flores General Building | remodel (e) kitchen & bathroom in unit 104. move non-bearing walls, electrical, plumbing, drywall, paint and floor refinish. add bathroomDetails
remodel (e) kitchen & bathroom in unit 104. move non-bearing walls, electrical, plumbing, drywall, paint and floor refinish. add bathroom | $30,000 |
| Apr 20, 2015 | Completed final sign-off Sep 2015 | 3535 Fillmore St | Flores General Building | unit 302: update electrical and plumbing, relocate kitchen, add a bath, add laundry hook ups, paint, refinish floors. remove non load bearing walls to abate complaint 201480181Details
unit 302: update electrical and plumbing, relocate kitchen, add a bath, add laundry hook ups, paint, refinish floors. remove non load bearing walls to abate complaint 201480181 | $31,000 |
| Mar 16, 2015 | Completed final sign-off Sep 2015 | 3535 Fillmore St | Flores General Building | update electrical & plumbing, relocate kitchen add a bathrom, add laundry hook up, paint, refinish floors, remove non-load bearing walls. turn existing kitchen and dining room into bedroomDetails
update electrical & plumbing, relocate kitchen add a bathrom, add laundry hook up, paint, refinish floors, remove non-load bearing walls. turn existing kitchen and dining room into bedroom | $32,000 |
| Jul 2, 2014 | Completed final sign-off Mar 2015 | 3535 Fillmore St | C N A Construction | #202, 203, 204, 303- to comply with nov #201479891 #201479901 #201479911 #201479921 #201480181 #201480271 & #201480281. kitchen remodel, in-kind replacement of two (e)bedroom windows located at side of bldg, not facing street. replace (e)washer & dryer in garage. (n) light fixtures in lobby.Details
#202, 203, 204, 303- to comply with nov #201479891 #201479901 #201479911 #201479921 #201480181 #201480271 & #201480281. kitchen remodel, in-kind replacement of two (e)bedroom windows located at side of bldg, not facing street. replace (e)washer & dryer in garage. (n) light fixtures in lobby. | $2,500 |
| Jan 14, 2014 | Completed final sign-off Feb 2014 | 3535 Fillmore St | S E Clare Construction & General Contr. | remodel kitchen, replace existing kitchen cabinets, counter tops, flooring, receptacles, no change in layout & openings, lighting shall have min 50% wattage high efficiancyDetails
remodel kitchen, replace existing kitchen cabinets, counter tops, flooring, receptacles, no change in layout & openings, lighting shall have min 50% wattage high efficiancy | $8,000 |
| Jan 21, 2010 | Completed final sign-off Apr 2010 | 3535 Fillmore St | David Adam Iseman | unit #201-cosmetic kitchen & bathroom face lift. new cabinets installed, new bathroom fixtures & new tiles. no structural work or wall relocation. new lighting at unit #201. no door work & no windows work on this permitDetails
unit #201-cosmetic kitchen & bathroom face lift. new cabinets installed, new bathroom fixtures & new tiles. no structural work or wall relocation. new lighting at unit #201. no door work & no windows work on this permit | $13,000 |
| Jun 11, 2007 | Never finaled issued Jun 2007, no final | 3535 Fillmore St | street space permit only.Details
street space permit only. | ||
| Dec 13, 2006 | Never finaled issued Dec 2006, no final | 3535 Fillmore St | street spaceDetails
street space |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Flores General Building (6), C N A Construction, Cpb Construction Corporation, Crime Watch Security Sys Llc, David Adam Iseman, G R C Roofing Inc., S E Clare Construction & General Contr., Sft Construction Corp
- Architects
- Brandon Quan, Jorge Carbonell, Terryl Lofrano
- Engineers
- Alexander Santos
Find contractors for work like this