Block 0314, lot 007
200 Powell St
- City’s use
- Commercial Retail
- Built
- 1933
- Stories
- 2
- Units
- 6
- Rooms
- 9 bathrooms
- Building
- 8,243 sq ft
- Lot
- 2,147 sq ft
- Zoning
- C3R
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
33 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 22, 2025 | Completed final sign-off Oct 2025 | 200 Powell St | Pacific Wide Builders Inc. | revision to 202507020036: structural detail & calculation provided for new suspended light boxDetails
revision to 202507020036: structural detail & calculation provided for new suspended light box | |
| Aug 26, 2025 | Completed final sign-off Mar 2026 | 200 Powell St | Golden Gate Sign Company Inc. | install (1) illuminated projecting sign: "pop mart"Details
install (1) illuminated projecting sign: "pop mart" | $11,000 |
| Aug 26, 2025 | Completed final sign-off Mar 2026 | 200 Powell St | Golden Gate Sign Company Inc. | install (1) banner onto existing supports. "pop mart"Details
install (1) banner onto existing supports. "pop mart" | $3,000 |
| Aug 26, 2025 | Completed final sign-off Mar 2026 | 200 Powell St | Golden Gate Sign Company Inc. | install (2) halo-lit wall signs: "pop mart"Details
install (2) halo-lit wall signs: "pop mart" | $14,000 |
| Jul 2, 2025 | Completed final sign-off Oct 2025 | 200 Powell St | Pacific Wide Builders Inc. | ti of (e) 2 story w/ basement retail building. scope includes but not limited to removal of non-structural partitions, relocation of (e) restroom sinks and adding (n) retail display tables, shelves and cashier counter. no exterior changes. mep shall be designed/built under separate permit.Details
ti of (e) 2 story w/ basement retail building. scope includes but not limited to removal of non-structural partitions, relocation of (e) restroom sinks and adding (n) retail display tables, shelves and cashier counter. no exterior changes. mep shall be designed/built under separate permit. | $250,000 |
| Oct 28, 2024 | In progress issued Jul 2025 | 200 Powell St | Bay Area Lightworks Inc | replacement of concrete sidewalk topping & regrading of curbramps, installation of steel st light & traffic signal pole w/ steel column support in basement. no work to the building nor facadeDetails
replacement of concrete sidewalk topping & regrading of curbramps, installation of steel st light & traffic signal pole w/ steel column support in basement. no work to the building nor facade | $90,000 |
| Nov 16, 2015 | Never finaled issued Nov 2015, no final | 200 Powell St | street space and mta parkingDetails
street space and mta parking | ||
| Oct 15, 2015 | Never finaled issued Oct 2015, no final | 200 Powell St | street space permitDetails
street space permit | ||
| Sep 3, 2015 | Never finaled issued Feb 2016, no final | 200 Powell St | Alpha Restoration & Wateproof | repair & maintenance only -scaffold bld. caulk windows. selectively repoint failed mortar joints, repair glazed spalls and bisque spalls in terra cotta. replace sealant joints in frp parapet.Details
repair & maintenance only -scaffold bld. caulk windows. selectively repoint failed mortar joints, repair glazed spalls and bisque spalls in terra cotta. replace sealant joints in frp parapet. | $40,000 |
| Jun 23, 2015 | Never finaled issued Jun 2015, no final | 200 Powell St | street spaceDetails
street space | ||
| Jun 8, 2009 | Never finaled issued Jun 2009, no final | 200 Powell St | street space permit.Details
street space permit. | ||
| Oct 3, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Innovative Technologies | as-built drawing incorporating applications #200709132561 and 200807247497 indicates added/new duct smoke detectors - provided & installed.Details
as-built drawing incorporating applications #200709132561 and 200807247497 indicates added/new duct smoke detectors - provided & installed. | $500 |
| Sep 9, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | installation of storage shelves at 2nd floor/revision to app#200712311619Details
installation of storage shelves at 2nd floor/revision to app#200712311619 | $10,000 | |
| Jul 29, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Signs Of All Kinds | to erect single face electric sign at exteriorDetails
to erect single face electric sign at exterior | $12,000 |
| Jul 29, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Signs Of All Kinds | to erect non-electric signs (banners)Details
to erect non-electric signs (banners) | $12,000 |
| Jul 29, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Signs Of All Kinds | to erect double faced electric blade sign at ofarrel sideDetails
to erect double faced electric blade sign at ofarrel side | $12,000 |
| Jul 24, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Innovative Technologies | fire alarm sytem tenant improvement as-built drawings. reference pa #2007091321561.Details
fire alarm sytem tenant improvement as-built drawings. reference pa #2007091321561. | $500 |
| Jul 22, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | installation of storage shelving at basement level/revision to app #200712311619Details
installation of storage shelving at basement level/revision to app #200712311619 | $20,000 | |
| Jun 27, 2008 | Completed final sign-off Jun 2009 | 200 Powell St | Dpw Inc. | all floors-modify (e) sprinkler system for new tenant work on 71 sprinkler headsDetails
all floors-modify (e) sprinkler system for new tenant work on 71 sprinkler heads | $15,000 |
| Dec 31, 2007 | Completed final sign-off Jun 2009 | 200 Powell St | interior tenant improvements in (e) two stories over basement bldg. no exterior work, no change in occupancy. accessibility upgrades to bathrooms, path of travel, stairs. minor partitions etc.Details
interior tenant improvements in (e) two stories over basement bldg. no exterior work, no change in occupancy. accessibility upgrades to bathrooms, path of travel, stairs. minor partitions etc. | $200,000 | |
| Sep 21, 2007 | Never finaled issued Sep 2007, no final | 200 Powell St | street spaceDetails
street space | ||
| Sep 13, 2007 | Completed final sign-off Jan 2009 | 200 Powell St | Innovative Technologies | new alarm system installation for the core and shell.Details
new alarm system installation for the core and shell. | $4,000 |
| Jun 6, 2007 | Completed final sign-off Jan 2009 | 200 Powell St | Dpw Inc. | install a new fire sprinkler system in basement, 1st and 2nd floors. total 0f 29 heads.Details
install a new fire sprinkler system in basement, 1st and 2nd floors. total 0f 29 heads. | $38,000 |
| Feb 16, 2007 | Completed final sign-off Jan 2009 | 200 Powell St | new storefront and facade repair, new stairs and elevator for future retail tenant. fire alarm and sprinkler under seperate permit. demolish existing sidewalk slab, construct new concrete slab and beam over sub-sidewalk.Details
new storefront and facade repair, new stairs and elevator for future retail tenant. fire alarm and sprinkler under seperate permit. demolish existing sidewalk slab, construct new concrete slab and beam over sub-sidewalk. | $400,000 | |
| Jan 30, 2007 | Completed final sign-off Jan 2009 | 200 Powell St | umb upgrade of vacant retail building.Details
umb upgrade of vacant retail building. | $1,400,000 | |
| Nov 30, 2006 | Completed final sign-off Jan 2009 | 200 Powell St | Fine Line Group Inc | demolition of first mezzanaine and second mezzanine. all other work is under separate permit.Details
demolition of first mezzanaine and second mezzanine. all other work is under separate permit. | $3,100 |
| Nov 20, 2006 | Never finaled issued Nov 2006, no final | 200 Powell St | street spaceDetails
street space | ||
| Nov 16, 2006 | Completed final sign-off Jan 2009 | 200 Powell St | Fine Line Group Inc | work to include soft demolition of inter spaces and clean up to a presentable state. exterior work to be removal of canopies and general clean up of facadeDetails
work to include soft demolition of inter spaces and clean up to a presentable state. exterior work to be removal of canopies and general clean up of facade | $45,000 |
| Jun 20, 2003 | Expired or cancelled withdrawn Nov 2006 | 200 Powell St | provide seismic upgrade and accessibility to the entire structure including g/f entrances and exitsDetails
provide seismic upgrade and accessibility to the entire structure including g/f entrances and exits | $200,000 | |
| Sep 6, 2002 | Never finaled issued Sep 2002, no final | 200 Powell St | street spaceDetails
street space | ||
| Aug 1, 2002 | Completed final sign-off Sep 2002 | 200 Powell St | basement and ground floor soft demo, remove all wall and ceiling sheathings including basement ductDetails
basement and ground floor soft demo, remove all wall and ceiling sheathings including basement duct | $4,500 | |
| Oct 25, 2000 | Expired or cancelled expired Feb 2001 | 208 Powell St | revision to 200007125021 remove 3 non bearing partiton on mezzanine floorDetails
revision to 200007125021 remove 3 non bearing partiton on mezzanine floor | $2,000 | |
| Jul 12, 2000 | Expired or cancelled expired Nov 2000 | 208 Powell St | soft demo: rmve non-bearing,non structural wall & ceilingDetails
soft demo: rmve non-bearing,non structural wall & ceiling | $3,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Golden Gate Sign Company Inc. (3), Innovative Technologies (3), Signs Of All Kinds (3), Dpw Inc. (2), Fine Line Group Inc (2), Pacific Wide Builders Inc. (2), Alpha Restoration & Wateproof, Bay Area Lightworks Inc
- Architects
- Tecta Associates (2), Charles Kridler, Marc Dimalanta
- Engineers
- Alfonso Aguilera, Kevin S. Morton, Markus Williams