Block 0311, lot 013
57 Post St
- City’s use
- Commercial Office
- Built
- 1909
- Stories
- 9
- Units
- 3
- Rooms
- 15 bathrooms
- Building
- 59,751 sq ft
- Lot
- 6,991 sq ft
- Zoning
- C3O
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
66 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 15, 2026 | In progress issued Sep 2026 | 57 Post St | Singular Builders | 2nd & 3rd/f t.i. build out individual study rooms at 3rd/f. general update to finieshes, repainting walls and ceiling, carpeting floors, staining wood. replacement of light & casework, upgrade to mech cooling in the 3rd/f it closetDetails
2nd & 3rd/f t.i. build out individual study rooms at 3rd/f. general update to finieshes, repainting walls and ceiling, carpeting floors, staining wood. replacement of light & casework, upgrade to mech cooling in the 3rd/f it closet | $1,880,000 |
| Sep 3, 2025 | Completed final sign-off Oct 2025 | 57 Post St | Apollo Building & Roofing Group Inc. | re-roofing with hot works.Details
re-roofing with hot works. | $12,000 |
| Sep 10, 2021 | Never finaled issued Feb 2022, no final | 57 Post St | Nor-Cal Scaffolding Inc., Sullivan / Thompson Masonry & Restoratio | in-kind facade masonry repairs of east elevation of historic mechanics institute. full assessment of necessary repair extents via scaffold removal of loose materials, followed by in-kind repair of deteriorated plaster parge coat,loose bride tie backs and lintels. e windows painted in place.Details
in-kind facade masonry repairs of east elevation of historic mechanics institute. full assessment of necessary repair extents via scaffold removal of loose materials, followed by in-kind repair of deteriorated plaster parge coat,loose bride tie backs and lintels. e windows painted in place. | $750,000 |
| Jun 21, 2019 | Completed final sign-off Aug 2019 | 57 Post St | Belfor Usa Group Inc | demo repair and replace drywall around the windows in units 512-812. drywall damage due to water leakage. repair and replace drywall that is demo'ed. replace baseboards and carpet at the affected areas. all interior drywall.Details
demo repair and replace drywall around the windows in units 512-812. drywall damage due to water leakage. repair and replace drywall that is demo'ed. replace baseboards and carpet at the affected areas. all interior drywall. | $100,000 |
| Oct 24, 2016 | Never finaled issued Oct 2016, no final | 57 Post St | Century Sprinkler Holdings Corp. | basement & 1st flr: 5 new heads, triming 13 drops to match ceiling htDetails
basement & 1st flr: 5 new heads, triming 13 drops to match ceiling ht | $7,000 |
| Oct 20, 2016 | Never finaled issued Oct 2016, no final | 61 Post St | street space permit and mta permit. renewal of permit # m723850Details
street space permit and mta permit. renewal of permit # m723850 | ||
| Oct 7, 2016 | Completed final sign-off Mar 2021 | 65 Post St | Red Hawk Fire & Security Ca Llc | 1/f- fire alarm t.i., add (4) horn/strobe, (1) duct detector air handling unit & relay for shut down. t.i.pa#201605056614.Details
1/f- fire alarm t.i., add (4) horn/strobe, (1) duct detector air handling unit & relay for shut down. t.i.pa#201605056614. | $4,000 |
| Sep 20, 2016 | Never finaled issued Sep 2016, no final | 61 Post St | street space permit, renewal of permit # m714607Details
street space permit, renewal of permit # m714607 | ||
| Sep 2, 2016 | Completed final sign-off Dec 2016 | 61 Post St | Connemara Fine Trim Inc Dba Highland Bui | revision to pa# 2016-0513-7385 to protect door opening from boiler room to exit passageway with a water curtain in lieu of fire rated vestibule.Details
revision to pa# 2016-0513-7385 to protect door opening from boiler room to exit passageway with a water curtain in lieu of fire rated vestibule. | $1,000 |
| Aug 18, 2016 | Never finaled issued Aug 2016, no final | 61 Post St | street space and mta parking.Details
street space and mta parking. | ||
| May 13, 2016 | Completed final sign-off Mar 2021 | 61 Post St | Connemara Fine Trim Inc Dba Highland Bui | new secondary egress with a 2 hour rated corridor and 90 minute doors. shell improvement for ti, a.d.a. compliance will be under separate permit as allowed in ab-017.Details
new secondary egress with a 2 hour rated corridor and 90 minute doors. shell improvement for ti, a.d.a. compliance will be under separate permit as allowed in ab-017. | $5,000 |
| May 5, 2016 | Completed final sign-off Dec 2016 | 65 Post St | Connemara Fine Trim Inc Dba Highland Bui | change of use from bank to bar. interior remodeling of (e) commercial tenant space for new bar tavern. upgrade bathrooms to (n) ada compliant bathrooms.Details
change of use from bank to bar. interior remodeling of (e) commercial tenant space for new bar tavern. upgrade bathrooms to (n) ada compliant bathrooms. | $86,400 |
| Mar 15, 2016 | Completed final sign-off Apr 2016 | 61 Post St | Zebra Awning Co Inc | to erect non-structural sign. change copy on signDetails
to erect non-structural sign. change copy on sign | $2,500 |
| Jan 13, 2016 | Never finaled issued Jan 2016, no final | 57 Post St | street space permitDetails
street space permit | ||
| Dec 10, 2015 | Never finaled issued Dec 2015, no final | 57 Post St | street spaceDetails
street space | ||
| Nov 5, 2015 | Never finaled issued Nov 2015, no final | 57 Post St | street space w/mtaDetails
street space w/mta | ||
| Oct 1, 2015 | Never finaled issued Oct 2015, no final | 57 Post St | street spaceDetails
street space | ||
| Jun 18, 2015 | Never finaled issued Jun 2015, no final | 65 Post St | street space w/mtaDetails
street space w/mta | ||
| Jun 18, 2015 | Never finaled issued Jun 2015, no final | 57 Post St | street spaceDetails
street space | ||
| Feb 2, 2015 | Expired or cancelled cancelled Apr 2018 | 65 Post St | new infill storefront at 61, 65 post. vacant tenant space. entry to be unpgraded to compliance.Details
new infill storefront at 61, 65 post. vacant tenant space. entry to be unpgraded to compliance. | $20,000 | |
| Jan 28, 2015 | Completed final sign-off Jun 2015 | 65 Post St | San Francisco Commercial Builders Inc | documentation of as built conditions. revision to app#201308164551 and 201311252804. vacant space. all accessiblity will be done per ab-017 under t.i. permit. no work to be done under this permit.Details
documentation of as built conditions. revision to app#201308164551 and 201311252804. vacant space. all accessiblity will be done per ab-017 under t.i. permit. no work to be done under this permit. | |
| Nov 26, 2014 | Completed final sign-off Feb 2015 | 57 Post St | work @ suite# 813 only. change of use only to massage therapy in existing office space on 8th floor. no modifications necessary.Details
work @ suite# 813 only. change of use only to massage therapy in existing office space on 8th floor. no modifications necessary. | ||
| Oct 8, 2014 | Expired or cancelled withdrawn Mar 2016 | 61 Post St | recover existing awning and banner flag with new copyDetails
recover existing awning and banner flag with new copy | $4,900 | |
| May 20, 2014 | Never finaled issued May 2014, no final | 65 Post St | street spaceDetails
street space | ||
| Dec 6, 2013 | Completed final sign-off May 2014 | 65 Post St | Superior Automatic Sprinkler | bsmt. t.i. pa 2013-0816-4551. add 4 spinklers for removed valt, elevator and stair.Details
bsmt. t.i. pa 2013-0816-4551. add 4 spinklers for removed valt, elevator and stair. | $1,700 |
| Nov 25, 2013 | Completed final sign-off May 2015 | 65 Post St | structural infill of opening at first floor (street level). sprinklers requested for new ceiling.Details
structural infill of opening at first floor (street level). sprinklers requested for new ceiling. | $25,000 | |
| Aug 16, 2013 | Completed final sign-off Aug 2015 | 65 Post St | demolition of t.i. in a vacant retail space. no primary structural will be removed. space will remain vacant at end of work. no changes to exterior of bldg. per ab -017Details
demolition of t.i. in a vacant retail space. no primary structural will be removed. space will remain vacant at end of work. no changes to exterior of bldg. per ab -017 | $32,000 | |
| Nov 15, 2012 | Expired or cancelled cancelled Jul 2016 | 65 Post St | Young Electric Sign Co. | to erect 1 non electric, projecting, double faced sign.Details
to erect 1 non electric, projecting, double faced sign. | $12,000 |
| Nov 15, 2012 | Expired or cancelled cancelled Jul 2016 | 65 Post St | Young Electric Sign Co. | to erect non electric, wall, single faced sign.Details
to erect non electric, wall, single faced sign. | $12,000 |
| Sep 22, 2011 | Completed final sign-off Jan 2012 | 57 Post St | barrier removal to create an accessible countertop sapce at the existing library checkout desk on 2nd floor.Details
barrier removal to create an accessible countertop sapce at the existing library checkout desk on 2nd floor. | $32,000 | |
| Nov 10, 2006 | Completed final sign-off Mar 2007 | 61 Post St | revision to pa# 200608018228 two changes: now providing full 24" strike side clearance on exterior door-removing hardship & automatic door closing. new unisex signage on bathrooms-4 employees max. usage. no other work.Details
revision to pa# 200608018228 two changes: now providing full 24" strike side clearance on exterior door-removing hardship & automatic door closing. new unisex signage on bathrooms-4 employees max. usage. no other work. | $1,000 | |
| Oct 31, 2006 | Completed final sign-off Mar 2007 | 61 Post St | Mc Millan Electric | install 3 smoke det, 7 horn strobes, audible/visual notification of appliances to tie into existing booster power supply. basment:1 smk det,2 horn str, 1st fl: 2 smk det, 5 horn strDetails
install 3 smoke det, 7 horn strobes, audible/visual notification of appliances to tie into existing booster power supply. basment:1 smk det,2 horn str, 1st fl: 2 smk det, 5 horn str | $9,500 |
| Oct 17, 2006 | Completed final sign-off Mar 2007 | 61 Post St | revision to app #200608018228. this scope of work is to retrofit a new stair between street level and basement in same location as extg stair. extg stringer to remain with new stringer placed inside extg stringer. install new risers, treads, railings, and bolts to floorDetails
revision to app #200608018228. this scope of work is to retrofit a new stair between street level and basement in same location as extg stair. extg stringer to remain with new stringer placed inside extg stringer. install new risers, treads, railings, and bolts to floor | $15,000 | |
| Oct 5, 2006 | Completed final sign-off Mar 2007 | 61 Post St | R L H Fire Protection Inc | t/i upgrade on fire sprinkler system; relocate 6 sprinkler heads.Details
t/i upgrade on fire sprinkler system; relocate 6 sprinkler heads. | $1,500 |
| Sep 7, 2006 | Completed final sign-off Nov 2006 | 57 Post St | renewl of expired app#200509233690 & #200506074454 for final inspection.Details
renewl of expired app#200509233690 & #200506074454 for final inspection. | ||
| Aug 1, 2006 | Completed final sign-off Mar 2007 | 61 Post St | t.i. for new retail shoe store, including new partitions, fixtures, equipment, shelving, new storefront, new pre-fab stairway, new lighting. no mechanical system in this building. fire protection under separate permit.Details
t.i. for new retail shoe store, including new partitions, fixtures, equipment, shelving, new storefront, new pre-fab stairway, new lighting. no mechanical system in this building. fire protection under separate permit. | $300,000 | |
| Feb 17, 2006 | Completed final sign-off Nov 2006 | 57 Post St | rvision to approved building permit application #200509233690 structural work only under this permitDetails
rvision to approved building permit application #200509233690 structural work only under this permit | ||
| Sep 23, 2005 | Expired or cancelled expired Nov 2006 | 57 Post St | rev.appl#200506074454 mark as 3,revised drawing shows roof mounted anchors to be directly on top of concrete instead of chipping the concrete to expose steel beam.Details
rev.appl#200506074454 mark as 3,revised drawing shows roof mounted anchors to be directly on top of concrete instead of chipping the concrete to expose steel beam. | ||
| Jun 7, 2005 | Expired or cancelled expired Nov 2006 | 57 Post St | install window washing roof mounted anchors & fall restraint horizontal cable on the roof.Details
install window washing roof mounted anchors & fall restraint horizontal cable on the roof. | $18,000 | |
| Mar 4, 2005 | Never finaled issued Mar 2005, no final | 57 Post St | street spaceDetails
street space | ||
| Mar 3, 2005 | Completed final sign-off Jul 2005 | 57 Post St | install seven inch (7") concrete overlay on top of (e) concreteslab in (e) basement storage area.Details
install seven inch (7") concrete overlay on top of (e) concreteslab in (e) basement storage area. | $42,500 | |
| Nov 24, 2004 | Completed final sign-off Sep 2005 | 65 Post St | Mc Millan Electric | life safety devices- 1 smoke detector, 1 heat detector, 9 horn/strobes, 6 strobes.Details
life safety devices- 1 smoke detector, 1 heat detector, 9 horn/strobes, 6 strobes. | $10,000 |
| Jul 22, 2004 | Completed final sign-off Sep 2005 | 57 Post St | Mc Millan Electric | all floors - life safety workDetails
all floors - life safety work | $175,000 |
| May 19, 2004 | Completed final sign-off Aug 2004 | 65 Post St | S C S Construction | remove patched are in wall where atm was before and instll new atm.Details
remove patched are in wall where atm was before and instll new atm. | $2,000 |
| Apr 14, 2004 | Never finaled issued Apr 2004, no final | 57 Post St | street space permitDetails
street space permit | ||
| Mar 4, 2004 | Completed final sign-off Jun 2004 | 57 Post St | R L H Fire Protection Inc | 4/f- fire sprinkler t.i. women room,relocate 3,add 2 pendent sprinklerDetails
4/f- fire sprinkler t.i. women room,relocate 3,add 2 pendent sprinkler | $1,000 |
| Feb 3, 2004 | Completed final sign-off Jun 2004 | 57 Post St | Rudolph Commercial Interiors Inc, Rci | install new accessible women's restroom on the 4th floorDetails
install new accessible women's restroom on the 4th floor | $25,000 |
| May 22, 2003 | Completed final sign-off Jan 2004 | 57 Post St | Zebra Awning Co Inc | erect signDetails
erect sign | $600 |
| Jan 17, 2003 | Completed final sign-off Apr 2003 | 57 Post St | Rudolph Commercial Interiors Inc, Rci | to renew app#2000/08/18/8187 for final final inspection.Details
to renew app#2000/08/18/8187 for final final inspection. | |
| Nov 19, 2002 | Completed final sign-off Jan 2003 | 57 Post St | Rudolph Commercial Interiors Inc, Rci | renew appl#200203252229 for final inspectionDetails
renew appl#200203252229 for final inspection | |
| Nov 19, 2002 | Completed final sign-off Jan 2003 | 57 Post St | Rudolph Commercial Interiors Inc, Rci | renew appl#200106121358, 200106222215 & 200108035227 for final inspection & correct # of stores 8 -9Details
renew appl#200106121358, 200106222215 & 200108035227 for final inspection & correct # of stores 8 -9 | |
| May 17, 2002 | Never finaled issued May 2002, no final | 57 Post St | install a new accessible women's restrm. on the 4th flr in a location that was pre. part of the acesDetails
install a new accessible women's restrm. on the 4th flr in a location that was pre. part of the aces | $25,000 | |
| Mar 25, 2002 | Expired or cancelled expired Feb 2003 | 57 Post St | renew expired permits for final: 200106121358,200106222215,200108035227Details
renew expired permits for final: 200106121358,200106222215,200108035227 | ||
| Mar 4, 2002 | Completed final sign-off Mar 2002 | 65 Post St | Zebra Awning Co Inc | renew appl#200108075532 for final inspectionDetails
renew appl#200108075532 for final inspection | |
| Feb 7, 2002 | Expired or cancelled withdrawn Feb 2002 | 61 Post St | revise to app #9903212 provide accessible entranceDetails
revise to app #9903212 provide accessible entrance | $25,000 | |
| Aug 7, 2001 | Expired or cancelled expired Feb 2002 | 65 Post St | Zebra Awning Co Inc | sign permit-non-electric, double faced.Details
sign permit-non-electric, double faced. | $300 |
| Aug 3, 2001 | Expired or cancelled expired Dec 2001 | 57 Post St | Pribuss Engineering Inc | new piping for sprinkler headsDetails
new piping for sprinkler heads | $5,000 |
| Aug 2, 2001 | Completed final sign-off Oct 2001 | 57 Post St | in kind repair to e cornice parapet at top of build n wtrprf membrane new sheet copper/sht mtl copinDetails
in kind repair to e cornice parapet at top of build n wtrprf membrane new sheet copper/sht mtl copin | $60,000 | |
| Jul 19, 2001 | Expired or cancelled expired Jul 2002 | 57 Post St | street spaceDetails
street space | ||
| Jun 22, 2001 | Expired or cancelled expired Jan 2002 | 57 Post St | rev. to pa#2001/06/12/1358: to provide structural & mech. drawings not included in original permitDetails
rev. to pa#2001/06/12/1358: to provide structural & mech. drawings not included in original permit | $500 | |
| Jun 12, 2001 | Never finaled issued Jun 2001, no final | 57 Post St | install 2nd exit connecting the (e) retail space at 61 post to the ped plaza along the east side ofDetails
install 2nd exit connecting the (e) retail space at 61 post to the ped plaza along the east side of | $30,000 | |
| Mar 7, 2001 | Completed final sign-off Mar 2001 | 57 Post St | renew expired pa 9917211 for final inspections work was to create a new coffee breakroom in office aDetails
renew expired pa 9917211 for final inspections work was to create a new coffee breakroom in office a | ||
| Jan 26, 2001 | Expired or cancelled expired May 2001 | 57 Post St | Pribuss Engineering Inc | fire sprikr t. i. relocate women's bathroom sprinkler head & change to sidewalls-making pipe one & oDetails
fire sprikr t. i. relocate women's bathroom sprinkler head & change to sidewalls-making pipe one & o | $1,200 |
| Aug 18, 2000 | Expired or cancelled expired Aug 2001 | 57 Post St | alteration of extg 2nd floor bthroom into 2 handicapped accessible bthrmDetails
alteration of extg 2nd floor bthroom into 2 handicapped accessible bthrm | $35,000 | |
| Mar 1, 2000 | Expired or cancelled expired Sep 2000 | 57 Post St | Rudolph Commercial Interiors Inc, Rci | replace vinyl wall covering in 3 elevators with new wood paneling.Details
replace vinyl wall covering in 3 elevators with new wood paneling. | $15,000 |
| Feb 10, 2000 | Expired or cancelled withdrawn Feb 2000 | 61 Post St | exterior remodel front and sidewalkDetails
exterior remodel front and sidewalk | $3,000 |