Block 0209, lot 017
745 Kearny St
- City’s use
- Miscellaneous/Mixed-Use
- Built
- 1962
- Stories
- 4
- Units
- 1
- Rooms
- 4 bathrooms
- Lot
- 57,516 sq ft
- Zoning
- P
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
26 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 4, 2025 | Completed final sign-off Aug 2025 | 745 Kearny St | Johnson Controls Fire | as built for approved fls pa # 2024-0730-7583 pen state inspection comment add 1 heat detector add 3 relay to replace 3 existing relaysDetails
as built for approved fls pa # 2024-0730-7583 pen state inspection comment add 1 heat detector add 3 relay to replace 3 existing relays | $700 |
| Apr 23, 2025 | Completed final sign-off Aug 2025 | 745 Kearny St | revision to permit 202311281504 to modify electrical design. modifications are the result of state elevator inspection. scope includes rerouting conduits providing power to devices in storage room so they are connected to panel a on level-1.Details
revision to permit 202311281504 to modify electrical design. modifications are the result of state elevator inspection. scope includes rerouting conduits providing power to devices in storage room so they are connected to panel a on level-1. | ||
| Jul 30, 2024 | Completed final sign-off Jul 2025 | 745 Kearny St | Johnson Controls Fire | ref pa # 2023-1128-1504 sprinkler & 2024-0207-5404 bldg elevator modernization remove existing smoke sensor, aim & heat detectors. add 2 new relays replace 4 smoke detectors & 2 duct detectorsDetails
ref pa # 2023-1128-1504 sprinkler & 2024-0207-5404 bldg elevator modernization remove existing smoke sensor, aim & heat detectors. add 2 new relays replace 4 smoke detectors & 2 duct detectors | $10,000 |
| Feb 7, 2024 | Completed final sign-off Feb 2025 | 745 Kearny St | Walschon Fire Protection Inc | demo extg sprinkler in mech. room and elevator shaft in garage room.Details
demo extg sprinkler in mech. room and elevator shaft in garage room. | $20,545 |
| Nov 28, 2023 | Completed final sign-off Aug 2025 | 745 Kearny St | repair and replacement of (3) passenger elevators that serve the (e) portsmouth square parking garage under declaration of emergency per board of supervisors resolution 455-23Details
repair and replacement of (3) passenger elevators that serve the (e) portsmouth square parking garage under declaration of emergency per board of supervisors resolution 455-23 | $1,500,000 | |
| Apr 26, 2022 | In progress issued Jun 2026 | 733 Kearny St | Swinerton Builders | priority processing ab-004. demolition of existing facilities exposing existing garage roof structure. installation of new waterproofing over existing garage roof structure. construction of new clubhouse and landscape/playground elements. miscellaneous offsite sidewalk and crosswalk improvements.Details
priority processing ab-004. demolition of existing facilities exposing existing garage roof structure. installation of new waterproofing over existing garage roof structure. construction of new clubhouse and landscape/playground elements. miscellaneous offsite sidewalk and crosswalk improvements. | $43,000,000 |
| Aug 13, 2019 | Completed final sign-off Apr 2020 | 733 Kearny St | Lmnop-Design Inc. | revision to 201511233400 due to reduction in project scope. no back up generator, no security gates at main entry (existing open entry to remain), existing slab opening @ floor 1 to remain (no infill), old office area to remain as is (no remodel); existing #2 enclosure to remainDetails
revision to 201511233400 due to reduction in project scope. no back up generator, no security gates at main entry (existing open entry to remain), existing slab opening @ floor 1 to remain (no infill), old office area to remain as is (no remodel); existing #2 enclosure to remain | |
| May 21, 2018 | Completed final sign-off Aug 2021 | 733 Kearny St | Edward W. Scott | new diesel generator with fuel tank to serve (e) publiv parking garage generator will be housed in an interior room maher naDetails
new diesel generator with fuel tank to serve (e) publiv parking garage generator will be housed in an interior room maher na | $40,000 |
| Oct 17, 2017 | Completed final sign-off Mar 2020 | 733 Kearny St | Johnson Controls Fire | provide new fire alarm system at parking garage. new 4007es fire alarm control panel to be installed. (2) additional power supplies required to power horn/strobe notification appliances. elevator monitoring devices to be provided as requiredDetails
provide new fire alarm system at parking garage. new 4007es fire alarm control panel to be installed. (2) additional power supplies required to power horn/strobe notification appliances. elevator monitoring devices to be provided as required | $34,041 |
| Sep 11, 2017 | Completed final sign-off Jul 2018 | 733 Kearny St | Value Fire Protection Inc | replace extg upright sprinkler at parking garage, 1815 heads. connect standpipe at lower level. n/a for maher. ref app #201511233400Details
replace extg upright sprinkler at parking garage, 1815 heads. connect standpipe at lower level. n/a for maher. ref app #201511233400 | $350,000 |
| Jun 2, 2017 | Never finaled issued Jun 2017, no final | 733 Kearny St | Value Fire Protection Inc | replace (18) sprinklers for tenant improvements at existing parking garage. ref pa #201511233400. n/a maher ordinanceDetails
replace (18) sprinklers for tenant improvements at existing parking garage. ref pa #201511233400. n/a maher ordinance | $6,800 |
| Nov 23, 2015 | Completed final sign-off Apr 2020 | 733 Kearny St | Alpha Bay Builders, Inc., Arana Group, Inc., Lmnop-Design Inc. | renov of an(e)parking garage. upgrades to(e)mech,elec,plumb & lighting systems; ada upgrades; waterproofing improvements & repair of(e)structure; reolocation of interior prog areas; replace interior stairs; enclosure of exterior stairs & mech openings; infill of interior structural bay (floor slab)Details
renov of an(e)parking garage. upgrades to(e)mech,elec,plumb & lighting systems; ada upgrades; waterproofing improvements & repair of(e)structure; reolocation of interior prog areas; replace interior stairs; enclosure of exterior stairs & mech openings; infill of interior structural bay (floor slab) | $1,987,718 |
| Oct 21, 2014 | Completed final sign-off May 2015 | 733 Kearny St | Chiang C M Construction Inc. | revision to ap #2013.1127.2982 - revisions include additional grade beam rebar, landscape wall layout, downspouts, access panel locations. n/a maher ordinanceDetails
revision to ap #2013.1127.2982 - revisions include additional grade beam rebar, landscape wall layout, downspouts, access panel locations. n/a maher ordinance | $5,000 |
| Dec 24, 2013 | Completed final sign-off Jun 2014 | 733 Kearny St | ada accessible barrier removal for chapter 1134b 2.1 par 3.6. revision to (e) accessible parking with path of travel. update accessible parking, existing 6 spaces to 10 spaces with 2 van accessible(compli. w/maher ordin.extended ordin. #155-13 not req'd. excavation less than 50 cu.yd.)Details
ada accessible barrier removal for chapter 1134b 2.1 par 3.6. revision to (e) accessible parking with path of travel. update accessible parking, existing 6 spaces to 10 spaces with 2 van accessible(compli. w/maher ordin.extended ordin. #155-13 not req'd. excavation less than 50 cu.yd.) | $5,000 | |
| Nov 27, 2013 | Completed final sign-off May 2015 | 733 Kearny St | to erect 1 story, no basement, public restrooms.Details
to erect 1 story, no basement, public restrooms. | $650,000 | |
| Nov 22, 2013 | Completed final sign-off Apr 2015 | 733 Kearny St | demolish old restroom & build a new one. (corner of portsmouth square)Details
demolish old restroom & build a new one. (corner of portsmouth square) | $20,000 | |
| Nov 18, 2013 | Never finaled issued Nov 2013, no final | 733 Kearny St | American Mechanical Inc | installation of an automatic carbon monoxide sensing (amcs) system to modulate existing garage ventilation system. 40 sensors totalDetails
installation of an automatic carbon monoxide sensing (amcs) system to modulate existing garage ventilation system. 40 sensors total | $168,000 |
| Jul 30, 2013 | Completed final sign-off Oct 2013 | 733 Kearny St | Wong Ho Yu/Ho's Electric Co | per notice of correction from dbi and sffd, install new self illuminated ext sings in garage and stair enclosure and floor numbering signs and directional ext signs leading to extg discharge and new signage for sprinkler controls and valves.Details
per notice of correction from dbi and sffd, install new self illuminated ext sings in garage and stair enclosure and floor numbering signs and directional ext signs leading to extg discharge and new signage for sprinkler controls and valves. | $1,000 |
| May 18, 2010 | Completed final sign-off Jun 2013 | 745 Kearny St | accessible barrier removal: removal of (e) doors, interior painting, floor finish & electrical work (all interior work).Details
accessible barrier removal: removal of (e) doors, interior painting, floor finish & electrical work (all interior work). | $20,000 | |
| Apr 12, 2010 | Completed final sign-off Aug 2010 | 733 Kearny St | Huey Const Mngmt Co Inc - Dba M H Const. | renew application 200811217105 for final inspectionDetails
renew application 200811217105 for final inspection | |
| May 15, 2009 | Completed final sign-off Sep 2009 | 733 Kearny St | Saarman Construction,Ltd. | remove & replace exterior cladding, remove & reinstall aluminum doors & windows w/new flashing & water proofing. remove pavers & concrete slab & install new waterproofing & concrete, remove soil at planters, install drain & waterproofing.Details
remove & replace exterior cladding, remove & reinstall aluminum doors & windows w/new flashing & water proofing. remove pavers & concrete slab & install new waterproofing & concrete, remove soil at planters, install drain & waterproofing. | $353,249 |
| Nov 21, 2008 | Expired or cancelled expired Jan 2010 | 733 Kearny St | renovation of existing restroom facilities.Details
renovation of existing restroom facilities. | $82,000 | |
| Jun 21, 2007 | Completed final sign-off Aug 2007 | 733 Kearny St | Solid Builders | to renew pa#200609111961,#200402196714,#200505021338 for final inspection.Details
to renew pa#200609111961,#200402196714,#200505021338 for final inspection. | |
| Sep 11, 2006 | Expired or cancelled expired Jan 2010 | 733 Kearny St | Solid Builders | renew expired pa# 200505021338-remaining work: concrete curb and electrical wiring ($10k)Details
renew expired pa# 200505021338-remaining work: concrete curb and electrical wiring ($10k) | $10,000 |
| May 2, 2005 | Expired or cancelled expired Jan 2010 | 733 Kearny St | Solid Builders | for sheetrock work only & finishingDetails
for sheetrock work only & finishing | $30,000 |
| Feb 19, 2004 | Expired or cancelled expired Jan 2010 | 733 Kearny St | construct pre -pay cashier station, install pre-pay stations and associated ticker machines and gateDetails
construct pre -pay cashier station, install pre-pay stations and associated ticker machines and gate |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.