Block 0112, lot 007
120 Green St
- City’s use
- Commercial Office
- Built
- 1904
- Stories
- 3
- Units
- 3
- Rooms
- 6 bathrooms
- Building
- 9,000 sq ft
- Lot
- 3,000 sq ft
- Zoning
- C2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
17 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 3, 2025 | In progress filed Sep 2025, not yet issued | 120 Green St | installation of roll up security gate at 120 green street entrance.revision to pa #202410233581 and pa #202507171057. revise door at 120 green to be out swinging. reconfigure stair shaft at 2nd and 3rd floor. relocate fire/atmospheric. seperation from previously approved plans.Details
installation of roll up security gate at 120 green street entrance.revision to pa #202410233581 and pa #202507171057. revise door at 120 green to be out swinging. reconfigure stair shaft at 2nd and 3rd floor. relocate fire/atmospheric. seperation from previously approved plans. | $1,000 | |
| Jul 17, 2025 | In progress issued Oct 2025 | 100 Green St | De Brus Construction Inc | revision and deferred electrical for office ti permit 202410233581. reconfigure previously approved ada bathroom #2. replace entry door at 120 green. remove non load bearing walls at ground floor meeting rooms.Details
revision and deferred electrical for office ti permit 202410233581. reconfigure previously approved ada bathroom #2. replace entry door at 120 green. remove non load bearing walls at ground floor meeting rooms. | |
| Oct 23, 2024 | In progress issued Mar 2025 | 100 Green St | De Brus Construction Inc | commercial ti: reconfigure ground fl lobby. reframe (e) stairs at 2nd fl. installation of (n) ada bathroom. upgrade (e) bathroom for ada complianceDetails
commercial ti: reconfigure ground fl lobby. reframe (e) stairs at 2nd fl. installation of (n) ada bathroom. upgrade (e) bathroom for ada compliance | $300,000 |
| Jun 26, 2018 | Never finaled issued Jun 2018, no final | 1011 Battery St | per pa #201508043320, add address to new food service restaurant at block 0112, lot 007 as; 1011 battery streetDetails
per pa #201508043320, add address to new food service restaurant at block 0112, lot 007 as; 1011 battery street | ||
| Dec 19, 2016 | Completed final sign-off Feb 2017 | 100 Green St | San Francisco Fire Protection | as builts to pa 201608034096 existing local system. install one pull station & smoke det at (e)fire control panel per ahj request.; maher n/aDetails
as builts to pa 201608034096 existing local system. install one pull station & smoke det at (e)fire control panel per ahj request.; maher n/a | |
| Aug 3, 2016 | Never finaled issued Aug 2016, no final | 100 Green St | San Francisco Fire Protection | due to interior remodeling on 1st floor retail space, 4 new notifiaction appliances will be install and tie-in to existing control panel located on 2nd floor. local system ti 2015-0804-3320 maher naDetails
due to interior remodeling on 1st floor retail space, 4 new notifiaction appliances will be install and tie-in to existing control panel located on 2nd floor. local system ti 2015-0804-3320 maher na | $2,000 |
| Jun 28, 2016 | Completed final sign-off Jul 2016 | 100 Green St | Theodore Design & Constr | construction of (n) concrete slab about 4200 sq ft and 13 lf of concrete wall 6"x2' tallDetails
construction of (n) concrete slab about 4200 sq ft and 13 lf of concrete wall 6"x2' tall | $2,500 |
| Mar 16, 2016 | Expired or cancelled withdrawn Jul 2016 | 100 Green St | remodel & partial seismic retrofit.Details
remodel & partial seismic retrofit. | $10,000 | |
| Oct 6, 2015 | Never finaled issued Oct 2015, no final | 100 Green St | All Air Mechanical Contractors Inc. | install split system fan coil & condensor air ductDetails
install split system fan coil & condensor air duct | $15,000 |
| Aug 4, 2015 | Never finaled issued May 2016, no final | 100 Green St | Theodore Design & Constr | change of use. install (n) storefront window on battery facade. install of (n) door assembly on battery facade. install (n) retail space in (e) office. n/a for maher ordinance.Details
change of use. install (n) storefront window on battery facade. install of (n) door assembly on battery facade. install (n) retail space in (e) office. n/a for maher ordinance. | $15,000 |
| Jan 20, 2015 | Completed final sign-off Jan 2015 | 100 Green St | Innovative Technologies | 1st fl: relocate one horn/strobe due to t. i. per app#201405054905. n/a for the maherDetails
1st fl: relocate one horn/strobe due to t. i. per app#201405054905. n/a for the maher | $400 |
| Nov 12, 2014 | Never finaled issued May 2015, no final | 100 Green St | K & M Construction | revision to 201405054905, change to interior partition framing, non load bearing. n/a maher ord. # 155-13Details
revision to 201405054905, change to interior partition framing, non load bearing. n/a maher ord. # 155-13 | |
| Oct 8, 2014 | Never finaled issued Oct 2014, no final | 100 Green St | Daniel Knight Construction | change of use - installation of limited service restaurant in an existing office space. n/a maher ordinanceDetails
change of use - installation of limited service restaurant in an existing office space. n/a maher ordinance | $5,000 |
| May 5, 2014 | Never finaled issued Sep 2014, no final | 100 Green St | Daniel Knight Construction | office tenant improvement on the ground floor. new offices, accessible restroom, stairsDetails
office tenant improvement on the ground floor. new offices, accessible restroom, stairs | $62,520 |
| Mar 18, 2014 | Never finaled issued Mar 2014, no final | 100 Green St | street spaceDetails
street space | ||
| Aug 2, 2012 | Never finaled issued Aug 2012, no final | 100 Green St | meters for parkingDetails
meters for parking | ||
| Aug 1, 2012 | Completed final sign-off Nov 2012 | 100 Green St | Acker & Guerrero Roof Co | reroofingDetails
reroofing | $22,500 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Daniel Knight Construction (2), De Brus Construction Inc (2), San Francisco Fire Protection (2), Theodore Design & Constr (2), Acker & Guerrero Roof Co, All Air Mechanical Contractors Inc., Innovative Technologies, K & M Construction
- Architects
- Serina Calhoun (4)
- Engineers
- Donald David
Find contractors for work like this