Permit GraphShortlistSan Francisco building permits since 2000

Permit 202507171057

100 Green St

revision and deferred electrical for office ti permit 202410233581. reconfigure previously approved ada bathroom #2. replace entry door at 120 green. remove non load bearing walls at ground floor meeting rooms.

Outcome
In progress (city status: issued, Oct 28, 2025)
Filed
Jul 17, 2025
Permit issued
Oct 28, 2025
Building use
office
Neighborhood
Financial District/South Beach
Contractor
De Brus Construction Inc (license 1008313)
Project type
Bathroom remodel
Property
All permits at this address (block 0112, lot 007)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
De Brus Construction Inc (license 1008313)
Architect
Serina Calhoun, Syncopated Arch (license C30744)
Authorized agent-others
Gustavo Souza (no license listed)