Zachary Westling
- Listed as
- engineer
- Firm
- Wm Structural
- Based in
- Oakland
- On San Francisco permits
- Mar 2020 to Aug 2026
17 permits since 2000 (engineer on 17 permits): 6 completed, 6 in progress, 3 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 25, 2026 | In progress issued Oct 2026 | 50 Capra Wy | Felix G Sanchez (Touch Design And Build | unit# 4 - revision to pa# 202604229909, no change to ext, relocate kitchen. move bedroom wall. install beam kitchen wall. add an officeDetails
unit# 4 - revision to pa# 202604229909, no change to ext, relocate kitchen. move bedroom wall. install beam kitchen wall. add an office | $10,000 |
| Jul 24, 2026 | In progress issued Jul 2026 | 28 Raleigh St | Structural Integrity | shoring for addition foundation, ref bpa#202512182208Details
shoring for addition foundation, ref bpa#202512182208 | $100 |
| Mar 13, 2026 | In progress issued Apr 2026 | 2906 Cesar Chavez St | Daaron Builders | remove & replace (e) stair. replace w/new stair as per sec.1881.(a) and sec.188Details
remove & replace (e) stair. replace w/new stair as per sec.1881.(a) and sec.188 | $10,000 |
| Feb 25, 2026 | In progress filed Feb 2026, not yet issued | 1658 23rd Av | 1/f: enclose & remodel entry and staircase, add 1/2 bath. 2/f: remodel kitchen and relocate interior stair, relocate 1-bath, add 1-pantry, add 1-office. 3/f: relocate interior stair, add 1-bathroom, new horizontal addition with office, walk-in-close, and roof deck.Details
1/f: enclose & remodel entry and staircase, add 1/2 bath. 2/f: remodel kitchen and relocate interior stair, relocate 1-bath, add 1-pantry, add 1-office. 3/f: relocate interior stair, add 1-bathroom, new horizontal addition with office, walk-in-close, and roof deck. | $480,000 | |
| Dec 5, 2025 | Completed final sign-off Jul 2026 | 30 Rockwood Ct | Sigma Construction Company | renovation of (e) 2 story residence including reconfiguration of internal stair, addition full bath @ 2nd fl; convertion of 1st fl storage area into habitable space & laundry room; new wood deck @ existing rear yardDetails
renovation of (e) 2 story residence including reconfiguration of internal stair, addition full bath @ 2nd fl; convertion of 1st fl storage area into habitable space & laundry room; new wood deck @ existing rear yard | $175,000 |
| Nov 13, 2025 | In progress filed Nov 2025, not yet issued | 2667 21st St | new bathroom in garage and sesmic upgraded.Details
new bathroom in garage and sesmic upgraded. | $20,000 | |
| Aug 2, 2024 | Completed final sign-off Jun 2026 | 1068 Noe St | Plath & Company Inc | interior remodel of a two unit building. all new exterior windows and doors will be energy-efficient models. some windows and doors locations will be modified. guards at bbalconies will be replaced.Details
interior remodel of a two unit building. all new exterior windows and doors will be energy-efficient models. some windows and doors locations will be modified. guards at bbalconies will be replaced. | $500,000 |
| May 9, 2024 | Completed final sign-off Jan 2025 | 395 Collingwood St | Lyons Building & Associates Inc. | revision to permit 202111162548. remove (e) post and beam, replace with new built up beam at 3/f. add a beam at the roof. add support posts tracked down to foundation.Details
revision to permit 202111162548. remove (e) post and beam, replace with new built up beam at 3/f. add a beam at the roof. add support posts tracked down to foundation. | $100 |
| Jan 30, 2024 | In progress filed Jan 2024, not yet issued | 2870 16th St | Delsur Construction | revision to pa# 202009214648, revise ceiling condition in the 3/f units 2878 & 2878a to retain the (e) dropped ceiling and attic space above-upgrade pg&e electrical meters closet on basement lvl. revise the basement flr plan for western units 1 & 3 to accommodate (e) foundation encroachment from theDetails
revision to pa# 202009214648, revise ceiling condition in the 3/f units 2878 & 2878a to retain the (e) dropped ceiling and attic space above-upgrade pg&e electrical meters closet on basement lvl. revise the basement flr plan for western units 1 & 3 to accommodate (e) foundation encroachment from the | $30,000 |
| Nov 27, 2023 | Completed final sign-off Oct 2024 | 125 Cerritos Av | California Custom Construction | voluntary strengthening @ garage.Details
voluntary strengthening @ garage. | $45,000 |
| May 16, 2023 | Completed final sign-off Mar 2026 | 1220 Treat Av | Hungto Co Incorporation | convert unimproved space at g/l into living space included living rm w/ kitchenette, bedrooms, bathrooms, laundry rm, and new interior stair connecting to main fl above. (net new sf: 1280 sf)Details
convert unimproved space at g/l into living space included living rm w/ kitchenette, bedrooms, bathrooms, laundry rm, and new interior stair connecting to main fl above. (net new sf: 1280 sf) | $312,550 |
| Dec 16, 2022 | Expired or cancelled withdrawn Apr 2024 | 395 Collingwood St | Lyons Building & Associates Inc. | expansion of roof volume within (e) atrium footprint, ref approved site pa# 201810304503-sr1. replace (e) glazed atrium @ 3rd floor with new sloped roof & glazing in (e) footprint. remopve (e) atrium slope & gable roof & replace with new sloped roof.Details
expansion of roof volume within (e) atrium footprint, ref approved site pa# 201810304503-sr1. replace (e) glazed atrium @ 3rd floor with new sloped roof & glazing in (e) footprint. remopve (e) atrium slope & gable roof & replace with new sloped roof. | $25,000 |
| Dec 2, 2022 | Never finaled issued Dec 2022, no final | 210 Frederick St | Mario Sarmento | revision to pa#2022-0622-6802, structural changes resubmitting for exposure of existing framing.Details
revision to pa#2022-0622-6802, structural changes resubmitting for exposure of existing framing. | |
| Nov 3, 2022 | Never finaled filed Nov 2022, never issued | 30 Blackstone Ct | deck rebuiltDetails
deck rebuilt | $5,000 | |
| Aug 20, 2021 | Never finaled issued Nov 2021, no final | 620 La Grande Av | Dmg Enterprises Inc | new wet bar & office & bath @ 1st/f. remodel kitchen & bathrooms. relocate interior staircase, replace (e) windows w/ glass doors in rear of house. replace (e) window in-kind. repair dry rot front deck. new glass door & glass guardrail @ front.Details
new wet bar & office & bath @ 1st/f. remodel kitchen & bathrooms. relocate interior staircase, replace (e) windows w/ glass doors in rear of house. replace (e) window in-kind. repair dry rot front deck. new glass door & glass guardrail @ front. | $290,000 |
| Feb 5, 2021 | Expired or cancelled withdrawn Mar 2021 | 395 Collingwood St | replace 2 windows & add new windows as noted. reorginize 2/f layout, remove bay at kitchen and relocate (e) stair to 3/f. reorginize 3/f owners suite to include a closet and study.replace rear roof structure & deck. add 2 new dormers onthe rear facade.Details
replace 2 windows & add new windows as noted. reorginize 2/f layout, remove bay at kitchen and relocate (e) stair to 3/f. reorginize 3/f owners suite to include a closet and study.replace rear roof structure & deck. add 2 new dormers onthe rear facade. | $400,000 | |
| Mar 3, 2020 | Completed final sign-off Nov 2022 | 1887 45th Av | remove wall and wight bearing post, replace door on west wall, restore ceiling and roof joistsDetails
remove wall and wight bearing post, replace door on west wall, restore ceiling and roof joists | $5,000 |