Paul Veryle Morford
- Listed as
- architect
- Firm
- Gensler
- On San Francisco permits
- Feb 2017 to May 2024
7 permits since 2000 (architect on 7 permits): 5 completed, 2 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 22, 2024 | Completed final sign-off Aug 2024 | 120 Kearny St | Hathaway Dinwiddie Co. | 38th floor: demo of (e) kitchen equipment & tile finishes. ceiling to remain. ab-017Details
38th floor: demo of (e) kitchen equipment & tile finishes. ceiling to remain. ab-017 | $10,000 |
| May 22, 2024 | Completed final sign-off Aug 2024 | 120 Kearny St | Hathaway Dinwiddie Co. | 38th floor: demo of interior finishes & fixtures to shell of existing data center room. no ceiling demo. ab-017Details
38th floor: demo of interior finishes & fixtures to shell of existing data center room. no ceiling demo. ab-017 | $15,000 |
| May 22, 2024 | Completed final sign-off Feb 2025 | 120 Kearny St | Hathaway Dinwiddie Co. | 37th & 38th floor: revise layout of communication room on 37th floor. add new communication room on 38th floor..Details
37th & 38th floor: revise layout of communication room on 37th floor. add new communication room on 38th floor.. | $50,000 |
| Aug 11, 2023 | In progress issued Oct 2023 | 1 Montgomery St | Hathaway Dinwiddie Co. | 38/f: demo interior fimnishes/fixtures to smell of (e) data center room. ab-017 shall apply to this permit. no ceiling demo(deferred accessibility requirements)Details
38/f: demo interior fimnishes/fixtures to smell of (e) data center room. ab-017 shall apply to this permit. no ceiling demo(deferred accessibility requirements) | $5,000 |
| Jun 2, 2023 | In progress issued Dec 2023 | 1 Montgomery St | Hathaway Dinwiddie Co. | 38th fl - demo of (e) kitchen equipoment & tile finishes. no wall demolition. ceiling to remain in place. ab-017Details
38th fl - demo of (e) kitchen equipoment & tile finishes. no wall demolition. ceiling to remain in place. ab-017 | $150,000 |
| Mar 20, 2017 | Completed final sign-off Jan 2018 | 720 California St | Gci, Inc | ground floor- commercial t.i., non structural partitions, millwork, ceiling system, door & frames, carpet, paint & finishes. ref. to demo pa#201702159435. mep deferred.Details
ground floor- commercial t.i., non structural partitions, millwork, ceiling system, door & frames, carpet, paint & finishes. ref. to demo pa#201702159435. mep deferred. | $15,319 |
| Feb 22, 2017 | Completed final sign-off Jan 2018 | 720 California St | Gci, Inc | 5th floor- commercial t.i., non bearing partitions, millwork, ceiling, door & frames, paint & finishes. ref. to demo pa#201702159435. mep deferred.Details
5th floor- commercial t.i., non bearing partitions, millwork, ceiling, door & frames, paint & finishes. ref. to demo pa#201702159435. mep deferred. | $33,743 |