Cameron Funk
- Listed as
- authorized agent-others, contractor
- Firm
- In Charge Energy Inc
- Based in
- Los Angeles
- On San Francisco permits
- Jan 2022 to Jul 2025
5 permits since 2000 (contractor on 5 permits, authorized agent-others on 1 permit): 3 completed, 1 in progress, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. Their ranked record as a contractor is on their contractor page. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Engineers
- Laureano Brown (2), Dustin James Colwell, Matthew Myres
- Authorized agents
- Anthony Hoac
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 0
- Commercial 1
- Other or unknown 4
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 18, 2025 | In progress issued Nov 2025 | 1401 Folsom St | In Charge Energy Inc | installation of ev charging station and their accompany civil and electrical infrastructure. demolition of existing surfaces. grading of 37 cubic yards of soil. insall 1 utitlity transform, 1 switchboard assembly, 5 400kw alpitronic hyc400 ev chargers, 8 ev sign posts, 2 accessible ev sign posts,Details
installation of ev charging station and their accompany civil and electrical infrastructure. demolition of existing surfaces. grading of 37 cubic yards of soil. insall 1 utitlity transform, 1 switchboard assembly, 5 400kw alpitronic hyc400 ev chargers, 8 ev sign posts, 2 accessible ev sign posts, | $400,000 |
| Mar 21, 2023 | Completed final sign-off Jan 2024 | 855 Geary St | In Charge Energy Inc | revision to pa#: 202204132175. 1st flr installation of ev chargers within eixsting parking garage. added 2 mini-split condenser/fan coil units for the elec distribution room. added direct-current fast charging. relocated distrib. panel. misc chnages per plansDetails
revision to pa#: 202204132175. 1st flr installation of ev chargers within eixsting parking garage. added 2 mini-split condenser/fan coil units for the elec distribution room. added direct-current fast charging. relocated distrib. panel. misc chnages per plans | $60,000 |
| Nov 7, 2022 | Never finaled filed Nov 2022, never issued | 855 Geary St | In Charge Energy Inc | install new electrical service/room, electrical equipment, pipe, wire, etc., for insall of (22) 180kw dc ev chargers & (17) 40a level 2 chargersDetails
install new electrical service/room, electrical equipment, pipe, wire, etc., for insall of (22) 180kw dc ev chargers & (17) 40a level 2 chargers | $1,100,000 |
| Apr 13, 2022 | Completed final sign-off Jan 2024 | 855 Geary St | In Charge Energy Inc | basement/2 & ground floors: installation of charging infrastructure for plug-in hybrid electric vehicles, including: new electrical service & switch gear. electrical distribution equipment, ac/dc charging equipment. chargers @ gr/f to be installed in future permit.Details
basement/2 & ground floors: installation of charging infrastructure for plug-in hybrid electric vehicles, including: new electrical service & switch gear. electrical distribution equipment, ac/dc charging equipment. chargers @ gr/f to be installed in future permit. | $65,000 |
| Jan 14, 2022 | Completed final sign-off Jan 2023 | 333 Brannan St | In Charge Energy Inc | installation of charging infrastructure for plug-in hybrid electric vehicle chargers. not for public use.Details
installation of charging infrastructure for plug-in hybrid electric vehicle chargers. not for public use. | $150,000 |